RESOLVED that Approval is given to the revised project implementation plan as set out at Paragraph 3.2 of the report. A further report to be brought back to Cabinet in relation to the current situation with a revised scheme for implementation The Chief Executive to bring back to Cabinet a report on the initial development of this project and the working relationship between departments
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To update Councillors on the Heads of the Valleys / Convergence funded tourism developments at Cyfarthfa Park and Parc Taf Bargoed; and to seek approval for a revision of project implementation timescales in line with funding requirements.
1.0INTRODUCTION AND BACKGROUND
1.1In September 2008 and November 2008, Cabinet gave approval for a range of project proposals to be implemented at Cyfarthfa Park and Parc Taf Bargoed. The projects are funded by the Heads of the Valleys and Convergence Programmes, with a notional budget allocation of £1.65 million.
2.0CURRENT PROGRESS
2.1The Cyfarthfa Park and Parc Taf Bargoed Development Group, which includes representation from the Council’s Regeneration, Leisure, Parks, Estates, Engineers and Planning Departments, together with Cyfarthfa High School has progressed and monitored the development of approved projects to date. Progress to date is as follows: 2.2 Tourist Information Centre Refurbishment
Project Cost: £57,000; A medium term internal refurbishment of the Tourist Information Centre (TIC) was completed in April 2009, incorporating a complete internal re-modernisation of the facility.
2.4CYFARTHFA PARK PROJECTS
2.4.1 Visitor Centre & Splash & Junior Play Pad facilities
Project Cost: £600,000 / £250,000 respectively; Under the Council’s existing Joint Venture Agreement, Capita Glamorgan have been commissioned to progress the Visitor Centre and Splash Pad projects to detailed development stage. During this detailed development work, a need for additional DDA compliance works and further engineering and environmental improvements has emerged, necessitating an additional funding requirement of £400,000. This has resulted in the total costs for these specific project elements increasing from £850,000 to £1,250,000 collectively. This additional finance is currently being sought from the Heads of the Valley programme, with a decision anticipated shortly. Planning applications for the projects are pending.
2.4.2 Cyfarthfa Park Entrance features
Project Cost: £67,600; At the Cyfarthfa Junior School entrance, Brecon Road, existing railings and entrance gates have been replaced in keeping with the existing heritage features of the park boundary. At the Pandy field entrance, the gates and railings have been refurbished, whilst at the Lakeside Entrance (adjacent to Cefn Road / Lakeside Gardens) new heritage style, vehicular and pedestrian gates and railings have been installed. This project has enhanced the Parks gateways, creating an identifiable and uniform entrance features for visitors.
2.4.3 Museum Tea Rooms
Project Cost: £110,000; Initial development work has been undertaken to investigate potential options for renewing the existing roof of the tearooms at Cyfarthfa Castle Museum and extending it into the external adjacent courtyard area, creating an additional capacity for 16 visitors. However, due to technical complexities in creating the new structure within the confines of the listed castle and potential difficulties that could be caused in relation to the existing School, it has been agreed that this project will be delayed until the future vision for the Castle is developed.
2.4.4 Relocation of the Miniature Railway
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.