RESOLVED that Council support taking forward the Critical Path (the next stage being the Outline Business Case) to DCELLS (which recommends a full Tertiary solution to the challenges which face the County Borough’s post 16 learning communities) with a view to securing “in principle” funding for the MLQ . Council removes the requirement for a delay of 1 month prior to submission of the OBC to DCELLS to avoid the risk of currently available funding being allocated to alternative projects.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 19th June 2009 REPORT AUTHOR [name removed] OF SERVICE Alistair Neill COMMITTEE Council COMMITTEE DATE 29th June 2009
TO: Mayor, Ladies and Gentlemen
Merthyr Learning Quarter (MLQ) Progress Report PURPOSE OF REPORT:
To report to Council on progress with the development of the Outline Business Case (OBC); to seek Council’s approval to take forward the Critical Path (the next stage of which is the submission of the OBC to DCELLS seeking ‘in principle’ funding) and to seek Council’s approval to proceed in doing so without delay.
1.0Introduction/Background
1.1Councillors will be aware from previous reports regarding the above that the fundamental objective of the Merthyr Learning Quarter (MLQ) is radically to improve learning and employment opportunities for the whole population of Merthyr Tydfil and the wider Heads of Valleys region.
1.2On June 25th 2008, the Council resolved:
“That Council agrees to the development of a Business Plan on the basis of Option 4, the full tertiary model, (to be progressed by the Directors of Integrated Adult Services and Children’s Services), which will be brought to Council in due course for approval, and that this Business Plan will address the range of issues identified in 6.2 of the report as part of the whole Business Plan. That Council considers a Business Plan on the basis of a full tertiary model to be sufficiently different to that of the business case previously presented for the MLQ as to require further examination by Council, and requires that, in line with conditions set out in the July 2007 Council Meeting, this new Business Case be presented to Councillors and all key partners for comment, at least one month prior to its submission to potential funders”
1.3On 14th December 2005, Full Council resolved that: “the principles of the ELWA [now DCELLS] Geographical Pathfinder recommendations are accepted [full tertiary option].” 1.4 Update reports on progress of the MLQ development were provided to Council on November 12th 2008 and April 1st 2009. These reports included clarification that the Welsh Assembly Government’s (WAG) Finance Directorate had altered its requirement for Business Plan development in late 2008, such that all education-related business cases seeking ‘substantial funding’ should be constructed and assessed on HM Treasury’s ‘Green Book 5 case model’ promoted by the Office of Government Commerce.
1.5The 5 case model requires:
1) a strategic outline programme - SOP;
2) a strategic outline case - SOC;
3) an outline business case - OBC;
4) a full business case -FBC; and
5) a business justification - BJ.
The 5 case model involves a strategic and financial evaluation of a range of options which are then systematically reduced and expanded through the remaining stages, resulting in a comprehensive justification of the preferred option.
1.6The key elements of this model, the SOC, OBC and FBC, must be developed as five different aspects (cases) that address specific elements of business planning which are interconnected but distinct. This will enable assessors to ascertain that proposals for funding:
- are supported by a robust case for change – the Strategic Case; - optimise value for money – the Economic Case; - are commercially viable – the Commercial Case; - are financially affordable – the Financial Case; and - can be delivered successfully – the Management Case.
2.0Strategic Outline Case (SOC)
2.1As reported to Council at its meeting on 1st April 2009, the Strategic Outline Case was submitted to DCELLS by the required date (15th January 2009) and following a successful compliance audit by an external organisation (Capital Project Consultancy - CPC) formal confirmation of acceptance of the SOC by WAG was received in a letter from the Head of Learning & Providers Division (DCELLS).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.