The Draft South East Wales Regional Transport Plan

Decided Executive 1 paper

Cabinet decided this item on Wednesday 22 July 2009. Below is the council's own wording, with the papers it was decided on.

Item159

Resolved

RESOLVED that Cabinet notes the progress made to produce the draft Regional Transport Plan and supports Sewta by commending it for submission to the Welsh Assembly Government in September 2009.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 5 pages

Background

1.1The Welsh Assembly Government (WAG) acquired new transport powers and responsibilities as a result of the Railways Act 2005 and the Transport (Wales) Act 2006. As a result, the Assembly has requested each of the four transport consortia in Wales to produce a Regional Transport Plan.

1.2Since 2005, the Regional Transport Plan covering the South East region of Wales has been developed by the South East Wales Transport Alliance (Sewta) of which Merthyr Tydfil County Borough Council is a partner.

1.3My report to Cabinet dated 7th September 2005 (Minute Number 114) secured a recommendation that Council notes the outline Plan (drafted at that time) and supports Sewta by endorsing the Policies and Recommendations it contains to enable work to continue on the production of the Draft and Final plans by the due dates.

1.4The Plan will aim to deliver improvements to address identified transport problems in the region including the need to deliver initiatives to reduce the effect that transport may contribute to future climate change. An outline of the Plan was submitted to the Assembly in December 2008 and after receiving comments from them in March 2009 a final draft of the full Plan has been prepared for submission in September 2009. The final plan will be presented to WAG in December 2009.

1.5Attached at Appendix 1 is a copy of a report outlining the proposed timetable for submission to WAG which was approved by the SEWTA Board on 26th June 2009. 1.6 Two copies of the draft Regional Transport Plan as accepted and approved by the Sewta Board have been placed in the Councillors’ library for reference purposes

Financial implications

2.1The draft RTP will inform WAG of the transport needs of the Region and it will effectively become the bidding document for future allocations of Transport Grant to implement the RTP programme of works covering road and rail infrastructure improvements, park and ride schemes, bus corridor and service improvements and sustainable transport solutions, i.e. cycling and walking schemes

2.2There are no direct financial implications associated with the production of the draft Plan. However, there will be an ongoing resource implication which requires officers to attend meetings relating to the production of the final Plan and thereafter the implementation of the Plan’s objectives to ensure that the Authority’s interests are properly represented and addressed.

3.0ENVIRONMENTAL IMPLICATIONS

3.1The environmental implications of the transport policies that the draft Regional Transport Plan identifies and/or recommends will be addressed appropriately.

4.0RECOMMENDATION THAT:

Cabinet notes the progress made to produce the draft Regional Transport Plan and supports Sewta by commending it for submission to the Welsh Assembly Government in September 2009.

GARETH CHAPMAN DEPUTY CHIEF EXECUTIVE & DIRECTOR OF CUSTOMER CORPORATE SERVICES

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Director of Director of Director of Director of Director of Integrated Integrated Adult Customer Corporate Finance, Audit Children’s Services Community Centre and Risk Services Services Management

Background papers

Title of Document(s) Document(s) Date Document Location Draft Regional Transport Plan Ongoing Engineering Files, Ty Keir Hardie Appendix 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Draft South East Wales Regional Transport PlanReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. The Draft South East Wales Regional Transport PlanThis decision
  2. P/23/0197 - Land adjoining (South of) Swansea Road to the East of Waunbant Court and North West of Old Winchfawr Road Swansea Road, Merthyr TydfilApproved
  3. Scrutiny Arrangements Of The South East Wales Corporate Joint CommitteeApproved
  4. Implementing The South East Wales Corporate Joint CommitteeNoted
  5. P/18/0316 - Land Adjoining (south of) Swansea Road to the east of Waunbant Court and north west of Old Winchfawr Road, Merthyr TydfilApproved
  6. P/18/0316 - Land Adjoining (south of) Swansea Road to the east of Waunbant Court and north west of Old Winchfawr Road, Swansea Road, Merthyr TydfilDecided

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies