RESOLVED that Council approves the LDP Consultation Report and LDP Background Papers covering Affordable Housing; Play Space Requirements; Infrastructure and Phasing; Green Wedges; and Minerals, prior to them being submitted to the Welsh Assembly Government and the Planning Inspectorate marking the commencement of the LDP Examination. Councillor B Carter left at 6.40pm. Councillor J Amos left and returned for comfort break during the discussion of the item but did not vote.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 6th July 2009 REPORT AUTHOR Chris Edwards HEAD OF SERVICE A N Davies COMMITTEE Full Council COMMITTEE DATE 22nd July 2009
TO: Mayor, Ladies and Gentlemen
MERTHYR TYDFIL LOCAL DEVELOPMENT PLAN (LDP) 2006 – 2021
PURPOSE OF REPORT: To seek Council’s approval of the LDP Consultation Report and the LDP Background Papers prior to their submission to the Welsh Assembly Government and Planning Inspectorate with all other LDP documentation.
1.0INTRODUCTION AND BACKGROUND
1.1Councillors will be aware of the statutory responsibility this Authority has under the Planning and Compulsory Purchase Act 2004 to prepare a local development plan. The LDP is one of 4 top tier strategies produced by the Authority and sets out the Council’s priorities for the development and use of land in the County Borough up to 2021 including policies to assist in implementing them.
2.0PROGRESS TO DATE
2.1A full timetable for the LDP’s preparation was set out in the LDP Delivery Agreement (as revised) which was agreed with the Welsh Assembly Government in January 2008. The preparation process culminated with publication of the Deposit LDP in October 2008 and its public consultation between 30th October and 12th December 2008.
3.0RESPONSES TO DEPOSIT CONSULTATION
3.179 representors responded to public consultation on the Deposit Plan submitting 388 separate representations. Those representations that related to particular site allocations were advertised and further comments invited in accord with the LDP Regulations between 29th January and 13th March 2009. This included those representations that proposed adding a site or altering/deleting a site. 39 representors responded to this consultation with 124 separate representations being received.
4.0NEXT STEPS
4.1As part of the process, the Town Planning Division has formulated responses to each of the representations received and this response includes a recommendation to an appointed Planning Inspector on whether any changes to the LDP are considered necessary. These responses are included in the LDP Consultation Report which was considered and approved by the LDP Steering Group on 13th July 2009 and is available for inspection in the Councillors’ Library.
4.2To accompany the Consultation Report and in order to provide further evidence supporting the LDP’s strategy prior to its Examination, a number of LDP Background Papers have been produced by the Town Planning Division. These cover:-
- Affordable Housing - Play Space Requirements - Infrastructure and Phasing - Green Wedges - Minerals
4.3These background papers were considered and approved by the LDP Steering Group on 13th July and are also available for inspection in the Councillors’ Library.
5.0NEXT STEPS
5.1Subject to approval by Full Council, the LDP Consultation Report and the LDP Background Papers will be forwarded to both the Welsh Assembly Government (WAG) and the Planning Inspectorate (PINS) along with all other LDP documentation that has been produced since the inception of the LDP process in 2006.
Submission of all documents to WAG/PINS represents the start of the LDP Examination which will include a Public Hearing in December 2009 when any outstanding objections to the Plan will be heard by an independent Planning Inspector and the Council will be given the opportunity to respond/re-affirm its position.
5.2The Planning Inspector will deliver his/her report following the Hearing and the recommendations contained therein will be binding on the Council in its subsequent adoption of the LDP. Upon adoption, Merthyr Tydfil County Borough Council is likely to be the first local authority in Wales to have an adopted LDP in place and will be considered as the forerunner in bringing the new development plan system in Wales to fruition.
6.0RESOURCE IMPLICATIONS
6.1Both the staff and financial implications of LDP preparation have previously been agreed by Full Council. There are no additional costs arising from this report.
7.0RECOMMENDATION: That:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.