RESOLVED that Cabinet notes the report, supports the requirement that all substantive projects to be delivered using effective project management and recognises that this will involve further training of individuals and may require future investment by the Council. In order to give the public clear lines of political accountability the Leader or his appointed port folio member sits on all future major project board meetings. A further report be brought back to cabinet in due course that sets out options and costings to ensure delivery of the above recommendation
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To report back to Cabinet, conclusions regarding the joint-working between departments in developing the Model Railway as part of the Cyfarthfa Park Tourism Project.
Background
1.1At the Cabinet of 24th June, the Chief Executive was tasked to “bring back to Cabinet a report on the initial development of this project and the working relationship between departments”.
1.2Subsequently, the process of this project’s management, leading up to Cabinet of 24th June was considered by the Chief Executive, and a number of points have presented which are identified below.
Summary
2.1Within a wider regeneration project, the Cyfarthfa Park Tourism Project, proposals were developed for the relocation of the Model Railway within Cyfarthfa Park, with a projected cost of £103,000, to be fully funded by the Heads of the Valleys Convergence Programme. This relocation of the model railway, one part of the wider scheme is the specific subject of this report.
2.2Following a lengthy period of project development, involving some initial consultation with the Planning Department, the Cabinet report of 24th June 2009 made clear that the Planning Department was unable to support the Model Railway project moving forward on the proposed site.
2.3Separately, but consistent with the views of the Planning Department, CADW – a key consultee – also concluded that the project could not proceed as was proposed. 2.4 Consequently, the project as previously defined was unable to progress: one consequence of this was the risk this placed upon the funding opportunity itself.
2.6Action has subsequently been taken by the departments involved, Planning, Engineering and Regeneration – along with CADW – to review how the project may be effectively delivered and what changes would need to be made to the project to make this possible.
2.7The causes of the initial failed outcome for the relocation of the Model Railway are clear:
- they stem from an inadequate level of project management: the fact that the project changed substantially in development tested the project management and exposed this weakness. - there was a breakdown in internal communications between departments involved, who behaved as individual departments following individual processes as opposed to a project team with varied departmental accountabilities, focused on delivering a project. - as far back as May / June 2008, and through the September 2008 Cabinet report, there was an inadequate level of prior discussion between Regeneration, Planning and Engineering on the matter of the railway. - only when the Planning Application was lodged on 21st January 2009 was the full extent of the proposal known. I could not identify any pre-application discussions in the preceding months to ensure that the project was on track to be delivered without unplanned – but predictable – hindrances. - there then followed a lengthy delay (30th March until 20th May 2009) in response to important issues raised by Planning – at a point where it was very evident that project-jeopardizing issues had developed. - there was a lack of communication with other key groups or individuals, including Councillors, to ensure that these issues were well-understood, or for plans to be put in place to address these issues.
3.0KEY ISSUES ARISING
3.1The Cyfarthfa Tourism Project required the effective joint-working of a number of departments, specifically: Regeneration, Planning, Engineering, Leisure and Parks Departments.
3.2This did not happen effectively in the case of the Model Railway. The key issues emerging following consideration of the process that led to 24th June Cabinet, are that:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.