Resolved
RESOLVED that The visit to the KLV plant in Slovenia for a representative of MTCBC at the expense of the tenderer Biffa Waste Services be approved.
Cabinet approved this item on Wednesday 14 October 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that The visit to the KLV plant in Slovenia for a representative of MTCBC at the expense of the tenderer Biffa Waste Services be approved.
To advise Councillors of a proposed site visit to a residual waste treatment plant in Slovenia for members of the Tomorrow’s Valley/ Cwm Yfory Project Team and to make a recommendation.
1.1Councillors will be aware of the joint working arrangements between Merthyr Tydfil County Borough Council and Rhondda Cynon Taf County Borough Council (TVCY) for the procurement of food (Lot 1) and residual (Lot 2) waste treatment facilities.
1.2During the Outline Solution Stage of the Competitive Dialogue Procurement Process, Biffa Waste Services (the only remaining bidder for Lot 2 & Lot 3) proposed a partnership with KIV to provide a gasification treatment solution for residual waste. KIV is a Slovenian company that has widespread experience in Eastern Europe but is not a name known in the UK.
2.0PROCUREMENT PROCESS
2.1The Detailed Solution Stage has been planned to commence in October 2009. Before the Detailed Solution Stage can commence, the Project Team needs to be assured that the proposed KIV gasification plant is suitable and robust enough to treat TVCY residual waste.
2.2In order to ascertain the suitability and robustness of KIV’s treatment solution, the Project Team has agreed that a visit to KIV’s reference plant is essential. The plant is in Celje, a city 50 miles east of the capital Ljubljana. The plant has been in operation since September 2008 and operates on a similar feedstock to the plant required by TVCY. The site visit was endorsed by the Project Board, which includes Councillors and officers from both RCT and MTCBC at the meeting of the 21st July 2009.
2.3The visit is to be at the expense of the tenderer (Biffa) and the visit will be made by the Project Manager of RCTCBC, the Project Officer of MTCBC and one specialist consultant from Hyder Environmental Consultants.
3.0LEGAL POSITION
3.1Legal advice has been obtained from TVCY legal advisers Clarkslegal in respect of the funding of a site visit by officers and technical experts in accordance with the codes for the acceptance of gifts and hospitality in both Councils and is specified as a background paper to this report.
3.2The advice states that the visit is an essential part of the tender process and therefore does not fall within the ambit of the Code.
3.3As the site visit forms an essential part of the bid and its evaluation it is normal practice for the bidder to bear the cost as part of the overall cost of the bid. This cost will include travel to and from the site and accommodation there as the distance precludes a day-trip. As it is necessary to stay overnight, the costs will also include a reasonable sum for meals and light refreshments as appropriate. Care should be taken to ensure that there is no additional ‘hospitality’ accepted, over and above that essential to facilitate the site visit.
3.4At Merthyr Tydfil CBC the Code specifies that the Authority should meet the cost of inspection visits for ‘purchasing’ inspections on the basis that travelling at the supplier’s expense may ‘jeopardise the integrity of subsequent purchasing decisions’. It is our advice that, although an obvious analogy may be drawn between the current proposed site visit and a purchasing inspection, the correct interpretation is that they are quite different. This is part of a major collaborative procurement subject to European rules and therefore very different from the routine purchasing of equipment as part of an ongoing supplies programme. Therefore, in our view the Merthyr Tydfil Code is not triggered.
3.5However, notwithstanding this advice, authorisation should also be sought in compliance with the Code as set out prior to embarking on the proposed site visit.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tomorrow's Valley / CwmYfory (TVCY) Waste Management Partnership Rhondda Cynon Taff CBCReport | 4 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.