EXTRA ITEM Damage to Pant Culvert: Emergency Repairs

Approved Committee 1 paper

Full Council approved this item on Wednesday 14 October 2009. Below is the council's own wording, with the papers it was decided on.

Item406

Resolved

RESOLVED that Councillors note and approve the urgent steps already taken to initiate repairs, including the allocation of unbudgeted funding. Councillors note the need for future protection measures and the intention to include a fresh bid via the capital programme. Councillors note and approve the strategic, without prejudice approach to the urgent repairs whilst reserving the right of Council to recover costs should circumstances require this. All potentially affected residents within the Nant Morlais development be informed of the situation in order that they are reassured of the Council’s support in dealing with the identified defects in the culvert subject to the caveat in (3) above regarding costs.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 3 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 13th October 2009 REPORT AUTHOR E Foley HEAD OF SERVICE E Foley COMMITTEE Full Council COMMITTEE DATE 14th October 2009

TO: Mayor, Ladies and Gentlemen

DAMAGE TO PANT CULVERT: EMERGENCY REPAIRS

PURPOSE OF REPORT: To inform Councillors of damage discovered during inspection of the Pant Culvert, the possible implications for local properties and urgent actions put in place for remediation.

1.0INTRODUCTION AND BACKGROUND

1.1On Thursday October 8th staff from the Engineering Department carried out a “walk through” visual inspection of the Pant Culvert, which extends from its entry point at the rear of Glanmorlais to its exit at Rhodfa’r. The culvert provides a route for the Morlais Brook which eventually flows through several other culverts, eventually draining into the Taff adjacent to Ty Keir Hardie.

1.2The survey revealed extensive erosion damage to the base of the masonry culvert exposing the foundations to the arch structure itself. A substantial portion of these foundations had also been damaged and a considerable length was missing entirely, almost certainly washed away during repeated storm flows.

1.3The inspection team were unable to travel the whole length of the culvert from its entry, due to safety concerns and instead completed the task by retreating to the point of entry and then resuming the inspection from the downstream end. By this means all but a short length has been inspected at close quarters.

2.0HISTORY OF CONSTRUCTION

2.1Although very few records remain, it appears that the culvert was constructed over a period of at least a century with the earliest phase for railway building in the mid nineteenth century. A second phase seems to have been introduced between 1900 and 1910 with a significant final section being constructed between 1910 and 1957. It is the mid section which currently gives rise to concern, probably dating from 1910 to 1920.

3.0PRESENT POSITION 3.1 The later, most northerly section of culvert which lies largely under the present Caeracca sports field is in reasonable condition and of no immediate concern. Clearly the degree of risk arising from a failure of the culvert in this area is small given the use of the overlying land. The same condition of the fabric (masonry) was recorded in the older southern end of the structure near its outfall at Rhodfa’r.

3.2The mid section of the culvert which is in a damaged condition underlies the former Caeracca Farm, developed as a housing estate now known as Nant Morlais in the 1980’s. A study of plans dating back to 1900 reveals that the culvert lies in the bed of a now filled valley, the fill being of unknown nature and quality. The effects of a failure within the culvert during storm conditions cannot therefore be predicted with accuracy as this would depend on depth, position, nature of the fill and of course the extent of the failure itself. It is certain however that any sizeable failure will affect the dwellings and infrastructure (road, utility services etc). For this reason, urgent repairs are required.

3.3In terms of responsibility for the culvert and its care/maintenance, the position is one of “riparian” ownership – essentially this means that unless there is express provision to the contrary, responsibility lies with the owner of the land beneath which the culvert lies. In this particular example there is multiple ownership by a number of property owners, the Council in its capacity as a landowner (e.g. below the sports field) and the Council as Highway Authority (e.g. where the culvert lies beneath a maintainable road or footway). I return to this topic below.

4.0PROPOSED ACTIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXTRA ITEM Damage to Pant Culvert: Emergency RepairsReport 3 pages DownloadRead as text

At this meeting

Whole meeting

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open
30 Sep 2026 Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies