Merthyr Tydfil County Borough Council
Cabinet, Wednesday 28 October 2009 at 2.30pm

Prevent 14-19 Convergence Project

Approved Executive 1 paper

Cabinet approved this item on Wednesday 28 October 2009. Below is the council's own wording, with the papers it was decided on.

Item430

Resolved

RESOLVED that Cabinet approves the ‘Prevent 14-19’ Business Plan which sets out the delivery and cost model, provision and risks for the local delivery of the project. Cabinet agrees the actions identified in the Follow-On Action Plan (as Appendix 1 of the report).
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 7 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 13 October 2009 REPORT AUTHOR Nicola Kingham HEAD OF SERVICE Sue Hughes COMMITTEE DIVISION Portfolio COMMITTEE Cabinet COMMITTEE DATE 28th October 2009

TO: Chairman, Ladies and Gentlemen

‘Prevent 14-19’ Convergence Project

PURPOSE OF REPORT: To seek approval from Cabinet for the submission of the ‘Prevent 14-19’ Business Plan and agree the follow-on actions that have been identified to prepare for the delivery of the project, prior to any approval of funding.

1.0INTRODUCTION

1.1The ‘Prevent 14-19’ project is being led by the Heads of the Valleys Consortium on behalf of five joint sponsor local authorities and four Further Education colleges. Funding is being sought from Priority 1 of the EU Convergence programme to deliver activities to prepare young people aged 14-19 for future employment, raising their aspirations and increasing participation in learning.

2.0CONTENT

2.1Delivery Model

2.1.1 The delivery model for Merthyr Tydfil will incorporate pre and post 16 support, focussed on the 4 secondary schools, Merthyr College and the town centre- based Information Shop.

2.1.2 Each of these ‘Prevent Centres’ will employ a full-time Co-ordinator/Learning Coach who will be the first point of contact for the project participants, enrolling them and carrying out initial needs assessments. In each of the schools and the Information Shop this post will be 50% funded by the European Social Fund (ESF) grant with the other 50% being met by ANDP and PIG funding, the latter being allocated in 2009/10 only. The schools and the Information Shop provision will be defined, agreed and monitored via a Service Level Agreement and Memorandum of Understanding. 2.1.3 The College will also employ a Centre Co-ordinator and will focus provision on basic skills development for participants aged 16 plus. This will be defined, agreed and monitored via a Service Contract.

2.1.4 A Project Co-ordinator, based within the 14-19 Learning Pathways Team, will be responsible for the central co-ordination of the project, receiving information on targets and expenditure from the Centre Co-ordinators, monitoring performance and submitting quarterly reports to the Lead Partner. This post will also have responsibility for central commissioning of additional services which will be identified by the schools prior to the start of the project.

2.2Schools Provision

2.2.1 Each of the secondary schools will be allocated funding for additional non- statutory provision. The proportion allocated to each school has been calculated based on data provided by ESIS on the KS3 Teacher Assessment performance of pupils in 2008 and will be as follows:

Afon Taf – 27% Bishop Hedley – 15% Cyfarthfa – 23% Penydre – 35%

2.2.2 There will be a degree of flexibility for the schools to decide what specific activities will be delivered. This would need to be commissioned centrally to ensure that it complies with the requirements of the grant.

2.3Business Plan

2.3.1 The Business Plan for Merthyr Tydfil has been based on an estimated ESF allocation of £809,373 over 3 years. With the grant intervention rate being 65.43% the total project cost for Merthyr Tydfil is £1,237,006. The target number of participants for Merthyr Tydfil is 865.

2.3.2 The draft Business Plan is currently being appraised by the Welsh European Funding Office (WEFO) and it is not known when a decision will be made on approval of funding. To minimise any risks, the delivery of the project will not commence until approval has been received.

3.0Project Risks

3.1The top risks and associated mitigating actions are detailed in the table below. Risk Mitigating Action(s) Risk Owner(s)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prevent 14-19 Convergence ProjectReport 7 pages DownloadRead as text

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies