RESOLVED that Cabinet accepts the grant funding to enable two feasibility studies on potential new school builds to be undertaken this year A report on the findings of the feasibility studies be presented to Cabinet as soon as practicable in the new financial year, 2010-2011.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 29th December 2009 REPORT AUTHOR Joyce Crandon HEAD OF SERVICE Chris Abbott COMMITTEE DIVISION Strategic COMMITTEE Cabinet COMMITTEE DATE 3 February 2010
TO: Chairman, Ladies and Gentlemen
WELSH ASSEMBLY GOVERNMENT TRANSITIONAL GRANT 2009-2010 (SECOND TRANCHE)
PURPOSE OF REPORT: To seek Councillors’ approval for progressing feasibility studies on potential new school builds this financial year.
1.0INTRODUCTION AND BACKGROUND
1.1In May 2009 the authority bid to the Welsh Assembly Government for funding for several potential schemes which are priorities within the School Organisation Plan. The authority’s strategic aims, which underpin all investment in school building improvement by Merthyr Tydfil County Borough Council, include:
• raising standards of educational attainment; • enabling inclusion as far as possible of pupils with disabilities into mainstream schools; • ensuring provision of safe and secure buildings; and • reducing surplus places.
1.2In July 2009 the Welsh Assembly Government agreed to provide additional funding of £3,000,000 towards an extension at Cyfarthfa High (Upper) School. The extension will assist in moving pupils out of the Castle building and accommodating all year groups on one site. This project is being taken forward with approval and financial support from Council and will commence in the new financial year.
1.3At the same time as bidding for funding for an extension to Cyfarthfa High School, the authority also requested funding from the Welsh Assembly Government to enable two feasibility studies, as follows:
• Afon Taf High School Feasibility study to evaluate the benefits of building a replacement secondary school for Afon Taf High School and a new replacement primary school (Troedyrhiw Primary) on the same site. • Ysgol y Graig Primary Feasibility study to agree a site for a new primary school and to explore the option to close the local nursery school (Trefechan Nursery) and amalgamate this with the proposed new primary school.
1.4The Welsh Assembly Government has recently awarded the authority £180,000 for each of these feasibility studies (£360,000 in total) to be carried out before the end of the financial year.
2.0THE WAY FORWARD
2.1The ICS department has discussed this grant funding with Estates and Property Services who, subject to Councillors’ approval, will assist in determining the most appropriate (in accordance with procurement regulations) and best value options in taking the proposed feasibility studies forward.
2.2The Welsh Assembly Government has indicated that the launch of its 21st Century Schools’ Programme, March 2010, will see significant investment for school building development, supporting large scale re-organisation and transformational proposals. Such proposals may be linked to changes in post-16 provision, such as the implementation of tertiary provision in a local authority and the attendant need to review secondary school organisation to ensure good quality pre-16 provision. Proposals should be prepared in the light of sound forecasting and take account of:
• the decline in the number of pupils in the school system overall, which is expected to continue until at least 2016; • population projections and forecasts of inward and outward migration; • birth rates within the local authority; • changes in demand for a particular type of provision, for example Welsh-medium education; • local plans for economic and housing development; • the need to ensure that the local authority has the right number of schools of the right type and size and in the right locations to meet the needs of the pupil population and the requirements of the curriculum at all ages; • the effect on the standard of education to be provided in the area; • the extent to which proposals will improve efficiency and the match between the number and location of school places and demand.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.