RESOLVED that Building contracts for extensions/refurbishments to educational establishments where deemed appropriate by the Head of Estates are let under the LHC’s EF1 arrangement. Building contracts for Group Repair Schemes are awarded to the Apollo Group, via the LHC’s EX1 arrangement
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 18th January 2010 REPORT AUTHOR Cheryllee Evans HEAD OF SERVICE Gary Thomas COMMITTEE DIVISION Portfolio COMMITTEE Cabinet COMMITTEE DATE 17th February 2010
PROCUREMENT OF ADDITIONAL BUILDING CONTRACTS VIA LONDON HOUSING CONSORTIUM (LHC).
PURPOSE OF REPORT: To obtain Cabinet approval to award further building contracts via the London Housing Consortium.
1.0INTRODUCTION AND BACKGROUND
1.1The Council’s procurement strategy reinforces the requirement to use innovative procurement methods in order to achieve tangible efficiency gains without compromising on quality. One such approach that has been utilised successfully in the past involves the procurement of building works via the London Housing Consortium.
1.2The London Housing Consortium (LHC) Network is a specialist public sector building procurement consortium set up for use, free of charge, by any public sector organisation.
1.3The LHC is a not-for-profit organisation which offers its members access to OJEU compliant, pre-tendered framework arrangements. Each arrangement offers robust specifications which address the latest technical, environmental and health and safety requirements.
1.4On 27th June 2007, Cabinet approved the awarding of two building contracts for its housing stock via the LHC (Minute No.159).
1.5The arrangements proved to be particularly successful and resulted in the delivery of high quality projects on time and within budget. Moreover, both kitchen and PVC window installation contracts achieved a high customer satisfaction rating. 2.0 BENEFITS OF USING LHC
2.1Savings in time and resources
Because all the products and services offered through the LHC Network have been evaluated and selected in strict accordance with the European Directive for Public Works, Supplies and Contracts, they are ready-to-use and therefore eliminate the lengthy process of specifying and tendering every project. This also saves on tendering costs and frees up valuable resources.
2.2Quality Standards
All LHC specifications are fully researched and developed to ensure that the latest technology is incorporated with minimum environmental impact and the latest building regulations and standards are adhered to.
2.3Best Value
The LHC Network is designed to maximise Best Value. That is, to obtain the best products and services for the best prices with the best outcomes for the community. Each framework arrangement incorporates competitive prices.
2.4Project Performance
LHC suppliers are selected according to their proven ability to carry out work to high standards of quality and safety in occupied properties.
To maximise performance, LHC will monitor the performance of the LHC Network supplier with periodic site inspections, to ensure that products comply with specification and are installed in accordance with the latest codes and standards.
2.5Annual rebates
In addition to the above, LHC Associate members also receive the additional benefit of potential annual rebates as shown below:
Value of transactions £ Rebate per year £200,000 - £999,000 0.5% of total transactions above £200,000
£1,000,000 - £1,499,000 1.0% as above
£1,500,000 - £1,999,000 2.0% as above
£2,000,000 + 2.0% below full members' return up to a maximum of 4.5% of transactions above £200,000 To date, MTCBC has received the following rebates:
2007/8 LHC rebate £701.00
2008/9 LHC rebate £1702.94
3.0NEW OPPORTUNITIES VIA LHC
The LHC now offers a wider range of products and services which will maximise best value for other sectors of the Council:
3.1.2 This agreement covers all external repairs to properties including roofing and window & door replacement and it is therefore particularly suited to Group Repair Envelope Schemes undertaken within the Council’s formally declared Renewal Areas.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.