RESOLVED that A full and comprehensive report to comprise Council’s Local Impact Report will be presented to Council for its determination at the appropriate time; and That the responses specified at 2.5.1 to 2.5.5 of the report be dealt with under delegated powers by the Deputy Chief Executive and Director of Customer Corporate Services or Head of Town Planning in consultation with the Leader of the Council or, in his absence or if he is unable to act, the Chair of Planning and Regulatory Committee. Councillor A Kitcher and R Griffin returned to the meeting.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 8th February 2010 REPORT AUTHOR Norman Davies/Judith Jones HEAD OF SERVICE Norman Davies COMMITTEE Full Council COMMITTEE DATE 3rd March 2010
TO: Mayor, Ladies and Gentlemen
PROPOSED ENERGY FROM WASTE PLANT (COVANTA LIMITED), BRIG-Y-CWM, CWMBARGOED – APPLICATION PROCESS
PURPOSE OF REPORT: To establish a decision-making process for the proposed infrastructure project.
1.0INTRODUCTION
1.1Council will be aware that for some time Covanta Energy has been pursuing the development of an Energy from Waste facility (EfW) at the above site. This report addresses the decision making process to consider the development rather than the details and merits of such a proposal. Other reports will be submitted to Council as appropriate.
1.2The facility is intended to generate approximately 65 megawatts (MW) of electricity, available for use by local residents and business, as well as providing a heat supply for local businesses. The energy will be produced by treating and disposing of approx. 700,000 tonnes of municipal and commercial waste per annum from the South Wales region by means of incineration.
1.3As the development will generate more than 50MW of electricity, the application decision making process will be via the Infrastructure Planning Commission (IPC) and not by means of a planning application.
2.0THE INFRASTRUCTURE PLANNING COMMISSION APPLICATION PROCESS
2.1The 2008 Planning Act (the Act) has transformed the arrangements for obtaining development consent for nationally significant infrastructure projects. The stated advantages of this new process include improved opportunities for the public, local authorities, consultees and objectors to become involved in the process at pre application stage. Importantly, all participants now have the opportunity to make their views known.
The IPC is an independent body, charged with making decisions on nationally significant infrastructure projects.
The IPC can refuse to accept an application if the applicant (the Promoter) has not demonstrated there has been adequate or proper consultation.
2.2Whereas the normal planning application process is “end loaded” (that is a detailed report and recommendation are presented to Committee or Council after a period of consultation and consideration), the IPC process comprises a series of separate submissions by the Promoter. Each requires input and responses within a defined, limited timescale from consultees, including Council. The required response times are (typically) 28 or 42 days.
2.3For clarity, under this process Council is not the determining authority, but an important consultee albeit a significant one. The Act recognises that local authorities are key to the process, but are not the only participants to it.
2.4The IPC process is a clear, iterative consultation process. Therefore between now and the formal submission of an application to the IPC for a Development Consent Order (DCO), Council will receive a series of submissions, each of which will require a formal response from Council within the defined timescales referred to at 2.2.
2.5The submissions will include:-
2.5.1 Draft Statement of Community Consultation; 2.5.2 Consultation under Section 42 of the Act or Preliminary Environmental Information (PEI); 2.5.3 Statement of Common Ground; 2.5.4 Draft Development Consent Order; and 2.5.5 Section 106 Agreement/s.
Upon submission of the DCO application to the IPC, the following input is required by Council:-
• Council’s representations to the IPC on the adequacy of consultation; and • Council’s Local Impact Report (LIR).
2.6The LIR will allow Council to identify areas of concern. It will weigh which matters are most significant, in its consideration, to the local impact of the proposal. It will allow Council to indicate which of those issues have been weighed most and those which have been weighed least in Council’s LIR.
2.7The IPC must have regard to the LIR report in making its determination. 3.0 WORKING ARRANGEMENTS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.