Merthyr Tydfil County Borough Council
Full Council, Wednesday 3 March 2010 at 5.30pm

Proposed Energy From Waste Plant (Covanta Limited), Brig-Y-Cwm, Cwmbargoed - Application Process

Decided Committee 1 paper

Full Council decided this item on Wednesday 3 March 2010. Below is the council's own wording, with the papers it was decided on.

Item740

Resolved

RESOLVED that A full and comprehensive report to comprise Council’s Local Impact Report will be presented to Council for its determination at the appropriate time; and That the responses specified at 2.5.1 to 2.5.5 of the report be dealt with under delegated powers by the Deputy Chief Executive and Director of Customer Corporate Services or Head of Town Planning in consultation with the Leader of the Council or, in his absence or if he is unable to act, the Chair of Planning and Regulatory Committee. Councillor A Kitcher and R Griffin returned to the meeting.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 4 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 8th February 2010 REPORT AUTHOR Norman Davies/Judith Jones HEAD OF SERVICE Norman Davies COMMITTEE Full Council COMMITTEE DATE 3rd March 2010

TO: Mayor, Ladies and Gentlemen

PROPOSED ENERGY FROM WASTE PLANT (COVANTA LIMITED), BRIG-Y-CWM, CWMBARGOED – APPLICATION PROCESS

PURPOSE OF REPORT: To establish a decision-making process for the proposed infrastructure project.

1.0INTRODUCTION

1.1Council will be aware that for some time Covanta Energy has been pursuing the development of an Energy from Waste facility (EfW) at the above site. This report addresses the decision making process to consider the development rather than the details and merits of such a proposal. Other reports will be submitted to Council as appropriate.

1.2The facility is intended to generate approximately 65 megawatts (MW) of electricity, available for use by local residents and business, as well as providing a heat supply for local businesses. The energy will be produced by treating and disposing of approx. 700,000 tonnes of municipal and commercial waste per annum from the South Wales region by means of incineration.

1.3As the development will generate more than 50MW of electricity, the application decision making process will be via the Infrastructure Planning Commission (IPC) and not by means of a planning application.

2.0THE INFRASTRUCTURE PLANNING COMMISSION APPLICATION PROCESS

2.1The 2008 Planning Act (the Act) has transformed the arrangements for obtaining development consent for nationally significant infrastructure projects. The stated advantages of this new process include improved opportunities for the public, local authorities, consultees and objectors to become involved in the process at pre application stage. Importantly, all participants now have the opportunity to make their views known.

The IPC is an independent body, charged with making decisions on nationally significant infrastructure projects.

The IPC can refuse to accept an application if the applicant (the Promoter) has not demonstrated there has been adequate or proper consultation.

2.2Whereas the normal planning application process is “end loaded” (that is a detailed report and recommendation are presented to Committee or Council after a period of consultation and consideration), the IPC process comprises a series of separate submissions by the Promoter. Each requires input and responses within a defined, limited timescale from consultees, including Council. The required response times are (typically) 28 or 42 days.

2.3For clarity, under this process Council is not the determining authority, but an important consultee albeit a significant one. The Act recognises that local authorities are key to the process, but are not the only participants to it.

2.4The IPC process is a clear, iterative consultation process. Therefore between now and the formal submission of an application to the IPC for a Development Consent Order (DCO), Council will receive a series of submissions, each of which will require a formal response from Council within the defined timescales referred to at 2.2.

2.5The submissions will include:-

2.5.1 Draft Statement of Community Consultation; 2.5.2 Consultation under Section 42 of the Act or Preliminary Environmental Information (PEI); 2.5.3 Statement of Common Ground; 2.5.4 Draft Development Consent Order; and 2.5.5 Section 106 Agreement/s.

Upon submission of the DCO application to the IPC, the following input is required by Council:-

• Council’s representations to the IPC on the adequacy of consultation; and • Council’s Local Impact Report (LIR).

2.6The LIR will allow Council to identify areas of concern. It will weigh which matters are most significant, in its consideration, to the local impact of the proposal. It will allow Council to indicate which of those issues have been weighed most and those which have been weighed least in Council’s LIR.

2.7The IPC must have regard to the LIR report in making its determination. 3.0 WORKING ARRANGEMENTS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Energy From Waste Plant (Covanta Limited), Brig-Y-Cwm, Cwmbargoed: Application ProcessReport 4 pages DownloadRead as text

At this meeting

Whole meeting
735aMinutes of meeting Monday, 1st February, 2010 of CabinetOn the agenda 735bMinutes of meeting Wednesday, 3rd February, 2010 of CabinetOn the agenda 735cMinutes of meeting Wednesday, 3rd February, 2010 of Full CouncilOn the agenda 735dMinutes of meeting Wednesday, 10th February, 2010 of CabinetOn the agenda 735eMinutes of meeting Wednesday, 10th February, 2010 of Planning and Regulatory CommitteeOn the agenda 735fMinutes of meeting Monday, 15th February, 2010 of Rights of Way CommitteeOn the agenda 735gMinutes of meeting Wednesday, 17th February, 2010 of CabinetOn the agenda 735hMinutes of meeting Monday, 22nd February, 2010 of Rights of Way CommitteeOn the agenda 736Notice of QuestionsOn the agenda 737Petition - Against Table and Chair PermitDecided 738Firing Line - Cardiff Castle Museum of the Welsh SoldierDecided 739WWF's Earth Hour InitiativeDecided
740Proposed Energy From Waste Plant (Covanta Limited), Brig-Y-Cwm, Cwmbargoed - Application ProcessThis decision
741Community Asset Transfer Strategy DocumentApproved 742Change of Political Management Structure from Alternative Arrangements to Executive Arrangements - Receipt of WAG ConsentNoted 743Council Responses To E Coli Inquiry RecommendationsNoted 744Proposed New Provisions For The Controlling And Regulating Of Street Trading Throughout The County BoroughNoted 745Waiving Repayment of "Right To Buy" DiscountDecided 746Integrated Children's Services School Support Services Service Delivery Plan 2009-2010Approved 747BIFFA Profit Sharing SchemeApproved 25RESOLVED thatOn the agenda 748Council Introduction of Reclaim Policy for Disabled Facilities GrantsPrivate 750EXTRA ITEM Unit 5 Triangle Business Park Merthyr TydfilPrivate

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open
30 Sep 2026 Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies