Resolved
RESOLVED that The report be received.
Cabinet decided this item on Wednesday 14 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that The report be received.
The purpose of the paper is to update Cabinet on the progress and keys issues for the Future Jobs Fund project.
1.0INTRODUCTION AND BACKGROUND
1.1On 2nd July 2009, Cabinet approved the recommendation to lead a consortium tender on behalf of the six South East Wales local authorities to deliver the Department for Work and Pensions (DWP) Future Jobs Fund Programme (FJF).
1.2Cabinet will be aware that as lead sponsor, Merthyr Tydfil County Borough Council (MTCBC) is required to act as the regional coordinator for the Programme contract with DWP, as well as providing a range of job opportunities within the council, and across a range of local partner organisations.
1.3The FJF programme initially focussed on engaging young people 18 – 24 year olds. However, the DWP have agreed that the Merthyr Tydfil contract should offer job opportunities to a wider group and include not only eligible 18-24 year olds but those 24+ who are classed as living in a disadvantage area. If an individual electoral ward is 1.5% above the national average of JSA Claimants then it can be classed as a disadvantaged area. The criteria set for a disadvantage area has resulted in all electoral wards in Merthyr Tydfil being eligible.
1.4In December 2009, MTCBC were invited to request an extension to the current contract for an additional 12 months. An extension request was submitted to the DWP with a proposal to create 1656 job opportunities across the HOV region, which will equate to 418 jobs for Merthyr Tydfil. 1.5 On the 2nd February 2010, DWP notified the local authority that the extension request was successful with a potential financial value of £10,746,000 for the HOV region. This equates to £2,717,000 for Merthyr Tydfil.
2.0CONTENT - PERFORMANCE TO DATE 2.1 The DWP have agreed a job creation profile of 872 for the HOV region for the period October 2009 – March 2010. This equates to 209 job opportunities for Merthyr Tydfil in this period. A break down of the agreed profile is shown in Appendix 1.
2.2To minimise the financial risk to MTCBC, The development of the FJF programme has been incorporated into the operational structures for the Bridges into work and Job Match Programme supported by additional capacity as summarised below:
• Development officer responsible for developing, implementing and coordinating the regional and local data systems. • Financial support to manage and verify all financial transactions with internal and external organisations • HR support to manage the process of recruitment and inductions, within the local authority job opportunities
2.3Progress against agreed targets detailed in the contract with DWP are:
2.4Locally
• 199 job opportunities have been created and advertised in the Merthyr Tydfil County Borough area for the period October 2009 – March 2010. This is in line with the agreed contract profile. • 103 individuals have been employed to date. This is 37% below the contract profile up to the end of February 2010. Delays in CRB checks, inappropriate referrals from Job Centre Plus (JCP), delay in interviews following the adverse weather and departments struggling to appoint within their agreed timeframe are all issues that have impacted on current outputs. • 100% of those employed have gained a qualification through the pre-employment programme associated to the FJF opportunities.
2.5Regionally
• 872 jobs opportunities have been created and advertised across the HOV region which is in line with the profile submitted to DWP for up to March 2010. • 511 jobs have been filled. This is 24% below the contract profile up to the end of February 2010.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Future Jobs Fund Programme UpdateReport | 5 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.