Merthyr Tydfil County Borough Council
Cabinet, Wednesday 13 October 2010 at 2.30pm

Danube Footbridge Reconstruction

Approved Executive 1 paper

Cabinet approved this item on Wednesday 13 October 2010. Below is the council's own wording, with the papers it was decided on.

Item361

Resolved

RESOLVED that Cabinet notes the progress made in permanently restoring the footbridge link between Abercanaid and Pentrebach . Cabinet approve the expenditure incurred to date, in particular the additional expenditure required under Contract ‘A’.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 5 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL Civic Centre, Castle Street, Merthyr Tydfil, CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

CABINET REPORT Date Written 29th September 2010 Report Author Keith Watkins Service Area Engineering, Highways and Transport Committee Division Portfolio Committee Date 13th October 2010

To: Chairman, Ladies and Gentlemen

Danube Footbridge Reconstruction

PURPOSE OF THE REPORT: To inform Councillors of the various costs incurred to date in respect of the above scheme and to request approval for payment of the anticipated final costs now that the scheme is nearing completion.

1.0INTRODUCTION AND BACKGROUND 1.1 Councillors will recall my previous report describing the events of 30th October to 1st November last year when the original Danube Footbridge collapsed into the River Taff as a result of a fire on the gas main carried by the bridge.

1.2Councillors approved the reinstatement of the footbridge, a vital link between the communities of Abercanaid and Pentrebach, with funding of up to £400,000 to be found from balances (Minute No. 474 refers).

2.0THE RECONSTRUCTION PROCESS

2.1In the interests of expediency it was decided to place direct orders with contractors for the provision of a temporary footbridge crossing in view of the relatively long lead-in time (minimum six months) required for the provision of a permanent replacement structure.

2.2An order was placed with one of our regular contractors, Marton Civil Engineering Ltd., who were available at short notice to prepare a new temporary support structure on the west bank of the river and organise the installation of a temporary footbridge crossing the river. 2.3 A separate order was placed with RMD Kwikform Ltd., the supplier of the materials making up the temporary footbridge, for the subsequent hire of the bridge over the period required for the construction of a new permanent abutment on the west side of the river and the fabrication of the new permanent replacement footbridge superstructure. It should be noted that the original stonework west abutment had been severely damaged by the fire and could not safely be reused.

2.4Installation of the temporary footbridge could not take place until Wales & West Utilities Ltd. had completed their works to lay a new gas main below the river bed. Following the fire, a temporary gas supply had been supported by the collapsed footbridge and as soon as this was no longer required our Contractors proceeded as quickly as possible to install the temporary footbridge. The temporary footbridge was opened to the public on Tuesday, 16th February and at this point the twice daily shuttle bus commissioned to transport school children from Pentrebach to the Abercanaid Community School was taken out of service.

2.5With regard to procurement of the works for the permanent replacement footbridge it was decided to undertake this under two different contracts. Competitive tenders were invited from specialist steelwork fabricators for the superstructure element of the project and competitive tenders were separately invited from general civil engineering contractors for the substructure elements of the project and subsequent site reinstatement works.

2.6The successful tender for the provision of the new superstructure was submitted by Nusteel Structures Ltd. in the amount of £68,405.00 and a contract (Contract ‘B’) was placed with them in mid April for installation of the new footbridge to take place on site in early August.

2.7The successful tender for the substructure works was submitted by Marton Civil Engineering Ltd. in the amount of £17,978.48. A contract (Contract ‘A’) for these works was awarded to Marton in early May so that the new west abutment and the modifications required to the existing east abutment would be completed in time for the delivery of the new footbridge superstructure in early August. Dismantling of the temporary footbridge and site reinstatement would then be carried out.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Danube Footbridge ReconstructionReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Danube Footbridge ReconstructionThis decision
  2. Danube Footbridge ReconstructionApproved

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies