Resolved
RESOLVED that Cabinet receives this report
Cabinet decided this item on Wednesday 27 October 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet receives this report
To update members on the progress of the Heritage Lottery Fund’s Townscape Heritage Initiative in Pontmorlais
1.0INTRODUCTION AND BACKGROUND
1.1It was reported to Cabinet on the 23rd June 2010 that the Authority had successfully secured funding from the Heritage Lottery Fund (HLF) from the Townscape Heritage Initiative (THI) programme for the Pontmorlais Heritage Quarter project. In conjunction, match funding commitments to the initiative have been made from the Heads of the Valleys Programme, CADW and MTCBC capital programme.
1.2Currently, a development grant of £97,000 has been awarded to progress the THI to a stage 2 application, which will allow access to the £1.58m which has currently been ring fenced to deliver the scheme in late 2011. There is no competitive round for this application but all the criteria set out by HLF must be met within the one year time frame. An extension past an 18 month period or failure to meet the HLF criteria would result in the total loss of the grant. 2.0 Development Phase
2.1To access the HLF funding a series of studies, that includes a conservation area management plan and consultations are required to be undertaken before submission of the Stage 2 application. A THI Officer has recently been appointed who will be responsible to ensure all terms and conditions imposed by the HLF for a Stage 2 approval are met, this will include working closely with property owners and business in the area to promote and develop the scheme.
2.2A key document required by HLF is a Conservation Area Management Plan. This document will provide a comprehensive management plan for the area, prioritise schemes and provide costs which will be submitted. A brief for the plan was drafted in conjunction with HLF and advertised through Sell2Wales. Three tenders were returned and two consultants were interviewed. The successful candidates were Donald Insall Associates, who have significant experience in undertaking Conservation Area Management Plans.
3.0FINANCIAL IMPLICATION(S)
3.1The development phase of the THI is being funded through the HLF development grant (£50,000) and HoV programme (£47,000). This funding will cover the costs of the THI Officer post (for 12 months) and the Conservation Area Management Plan commission.
3.2The implementation phase total project cost is expected to be in excess of £2.5 million. MTCBC’s contribution will total £150,000 over the 5 year programme (£30,000 per year) from the former Regeneration Department Capital Programme, which has been agreed with Director of Finance. This will match £1.58 million from HLF, it is expected to secure £752,000 from the HoV Programme and £60,000 from CADW plus private sector leverage.
GARETH CHAPMAN DEPUTY CHIEF EXECUTIVE AND EXECUTIVE DIRECTOR OF SCHOOLS, GOVERNANCE AND TECHNICAL SERVICES BACKGROUND PAPERS Title of Document(s) Document(s) Date Document Location
Built Heritage Strategy December 2008 Physical Regeneration & Action Plan Department
HLF THI Stage 1 November 2009 Physical Regeneration Application Department
Town Centre April 2009 Physical Regeneration Partnership Department Performance Report & Action Plan 2009-2010
Consultation has been undertaken with Executive Board in respect of each proposal(s) and recommendation(s) set out in this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Townscape Heritage Initiative: Pontmorlais Heritage QuarterReport | 3 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.