Resolved
RESOLVED that A variation order be issued to Flowline Civil Engineering Ltd to the value of £25,000.00 for the additional works required on the Ysgol Santes Tudful Safe Routes in Communities contract.
Cabinet decided this item on Wednesday 10 November 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that A variation order be issued to Flowline Civil Engineering Ltd to the value of £25,000.00 for the additional works required on the Ysgol Santes Tudful Safe Routes in Communities contract.
MERTHYR TYDFIL COUNTY BOROUGH COUNCIL Civic Centre, Castle Street, Merthyr Tydfil, CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk
CABINET REPORT Date Written 25th October 2010 Report Author Carwyn Morris Service Area Engineering, Highways & Transport Committee Division Portfolio Committee Date 10th November 2010
To: Chairman, Ladies and Gentlemen
Ysgol Santes Tudful Safe Routes in Communities, Merthyr Tydfil
PURPOSE OF THE REPORT: To inform Councillors of the requirement for additional works to the above scheme, to recommend the contractor be issued with a Variation Order to carry out the additional works and the financial implications of the additional works.
1.0INTRODUCTION AND BACKGROUND
1.1Tenders were invited from seven contractors for the above scheme, which is designed to provide safer routes to Ysgol Santes Tudful school.
1.2The project involves various traffic calming features including a zebra crossing on Panyffin Road and a new footpath on land adjacent to the school.
1.3Seven tenders were returned, by the due time and date of 1600 on Thursday 16th September 2010.
1.4Tenders were opened at 2.00pm on Friday 17th September 2010 and the values were as follows:
1. £69,915.21 2. £67,574.98 3. £59,096.29 4. £54,118.30 5. £72,600.00 6. £66,246.10 7. £56,597.99
1.5Arithmetical checking was carried out on all seven tenders and no arithmetical error was noted.
1.6The three lowest tenders were then given a detailed analysis and the rates contained therein were found to be consistent with provisional estimates.
1.7The recommendation that tenderer number 4, being Flowline Civil Engineering Ltd, in the sum of £54,118.30 as the lowest returned tender was approved by the Engineering, Highways and Transport Manager on 17th September 2010, in accordance with the financial regulations and awarded the contract for the Ysgol Santes Tudful Safe Routes in Communities contract.
1.8During the course of works, which started on 11th October 2010, additional requirements were identified to overcome unforeseen problems. Principally the need to carry out full construction on existing footways due to the poor condition of the sub grade of the existing footway and large boulders and concrete. Additional civil engineering works associated with BT and Western Power diversion are also required.
1.9I therefore seek authorisation to carry out the additional works required and extend the contract value by £25,000.00 to a total of £79,118.30.
2.0FINANCIAL IMPLICATION(S)
2.1Additional funding is available for the project from the 2010/2011 Local Road Safety grant which has been confirmed by WAG.
3.0RECOMMENDATION(S) that
3.1A Variation Order be issued to Flowline Civil Engineering Ltd to the value of £25,000.00 for the additional works required on the Ysgol Santes Tudful Safe Routes in Communities contract.
GARETH CHAPMAN CHIEF EXECUTIVE BACKGROUND PAPERS Title of Document(s) Document(s) Date Document Location Tender Documents for Engineering Files the Ysgol Santes Tudful H5.1/67 Safe Routes in Communities
Consultation has been undertaken with Executive Board in respect of each proposal(s) and recommendation(s) set out in this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ysgol Santes Tudful Safe Routes in Communities, Merthyr TydfilReport | 3 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.