River Taff Corridor Phase 4 - Rhydycar Cascade Link

Noted Executive 1 paper

Cabinet noted this item on Wednesday 16 March 2011. Below is the council's own wording, with the papers it was decided on.

Item872

Resolved

RESOLVED that The contents of this report be noted and that Alun Griffiths Ltd is appointed in the sum of £182,486.04 to undertake the River Taff Corridor Phase 4 works.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 3 pages

Purpose of the report

To inform Cabinet of the proposed implementation of Phase 4 of the River Taff Corridor Enhancement scheme and to seek approval of a contractor to undertake the works.

1.0INTRODUCTION AND BACKGROUND

1.1A report was presented to Cabinet on 28th January 2010 informing members of the implementation of the River Taff Corridor Phase Three Scheme. The report concluded that funding would be sought to additionally implement a further Fourth Phase. This was included in the Town Centre Regeneration Programme approved by WEFO in November 2010.

2.0PROJECT OVERVIEW 2.1 The River Taff Corridor is an important asset and forms an attractive feature in the Town Centre with links on the Taff Trail, to the remains of the Glamorganshire Canal and other features. In January 2006, the River Corridor Masterplan was prepared by Austin Smith Lord Consultants, which was subsequently approved by Cabinet and three phases were implemented through the Heads of the Valleys Programme. The scheme phases have been developed and consulted in conjunction with the Town Centre Partnership. 2.2 The first three phases of works comprised of major environmental improvements from Dixon Street through to the Weir and installation of a fish pass which public realm enhancements as far as the Leisure Village. 2.3 A fourth phase has now been developed which aims to extend the first three phases, achieve continuity and improve links between the Taff Trail, Orbit Business Centre and Welsh Assembly Government Building to the town centre.

2.4As part of the Town Centre Regeneration Programme which is funded through the Heads of the Valley’s Programme and ERDF Convergence Fund, this scheme has been granted £350,000 for associated works for the financial year 20010/11. The project has funds available to carry over into the financial year 2011-12 if required.

2.5The phase 4 scheme has been designed in-house and involves the installation of a new bridge over the Rhydycar cascade, creating a new path, installation of way finding, lighting, artwork and landscaping. 2.6 This phase will extend the features and attractions on the Taff Trail and provide a more attractive route to the town centre for users from the WAG building, ORBIT and future developments. Innovative project design will provide a stronger identity for the Taff Trail and corridor enhancing its tourism potential.

2.7Tenders were invited from six contractors for the above scheme, five tenders were returned, by the due time and date of 1600 on Thursday 3rd March 2011. 2.8 Tenders were opened at 10.00am on Friday 4th March 2011 and the values were as follows:

1 £ 216,150.00 2 £ 221,980.03 3 £ 200,523.03 4 £ 182,486.04 5 £ 183,319.58

2.9Arithmetical checking was carried out on all five tenders and no arithmetical error was noted. The three lowest tenders were then given a detailed analysis and the rates contained therein were found to be consistent with provisional estimates. Alun Griffiths Ltd is the lowest tender in the sum of £182,486.04. 3.0 FINANCIAL IMPLICATIONS 3.1 There are no direct financial implications to the Authority, as funding has been approved as part of the Town Centre Regeneration Programme. Officer time will be required, in managing the contractors. Scheme design and specification has purposely been identified to be low maintenance to the Authority, in particular landscaping features were designed to assist low maintenance. In addition, the proposed lighting utilises modern LED technology.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
River Taff Corridor Phase 4: Rhydycar Cascade LinkReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. River Taff Corridor Phase 4 - Rhydycar Cascade LinkThis decision
  2. River Taff Central Link and Penderyn Square ContractDecided
  3. Town Centre Regeneration Programme: The naming of key elements of the River Taff Central LinkApproved
  4. Penderyn Square and River Taff Central Link Regeneration Projects - Proposed Permanent Traffic Regulation OrdersDecided
  5. Town Centre Regeneration Programme: Project Management Services for the River Taff Central Link and Penderyn Square SchemesApproved
  6. River Taff Central Link and Penderyn Square - Appointment of Contractor AmendmentApproved

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies