CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Merthyr Tydfil County Borough Council
Governance and Audit Committee, Monday 26 September 2011 at 3.30pm

Annual Risk Management Progress Report and Updated Corporate Risk Register for 2011/12

Approved Finance 3 papers

Governance and Audit Committee approved this item on Monday 26 September 2011. Below is the council's own wording, with the papers it was decided on.

Item338

Resolved

RESOLVED that Councillors receive and approve this report, including the Corporate Risk Register for 2011-2012 and note the progress made in developing Risk Management. Audit Committee invites Directors to attend periodically on a rolling programme basis to report on progress in managing their Corporate Risks. This report be forwarded to Cabinet for approval.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Governance and Audit Committee, 11 pages

Purpose of the report

For Councillors to receive a progress report on implementing Risk Management and the updated Corporate Risk Register for 2011-12.

1.0INTRODUCTION

1.1It was previously agreed by Council that Councillors, via Cabinet and Audit Committee should receive Risk Management Progress Reports. This is the fourth Annual Risk Management Progress Report.

1.2Ultimate responsibility for Risk Management within the Local Authority rests with Council, whilst Cabinet is allocated responsibility for overseeing Risk Management.

1.3In summary, Councillors’ role is to:

• Oversee the effective management of risk by Officers. • Take a full part in the Risk Management process as members of the Service Management Boards and Executive Board.

1.4The role of the Audit Committee in relation to Risk Management is to:

• Consider the effectiveness of the Council’s Risk Management arrangements. • Seek assurances that action is being taken on risk-related issues. 2.0 PROGRESS ON RISK MANAGEMENT

Council Restructure

2.1Following the Council restructure in April 2010 it was decided to combine the Performance and Risk Management Team in order to better integrate Performance and Risk Management across the Council.

2.2One of the main aims of this change was to adopt and implement an effective Business Planning and Performance and Risk Management Framework that enables monitoring and delivery of the Community Plan, Partnership Plans, the Council’s Corporate Plan, Strategic Service plans and Operational Team plans.

Role of the Risk Management Service

2.3The Specific Outcome (What do we want to achieve?) for the Risk Management Service is the provision of a Risk Management Service which promotes and integrates Risk Management across the Local Authority so that risks and opportunities are identified, evaluated, monitored and managed to enable the Council to achieve its Corporate Priorities for Improvement. The Tasks (How will we deliver this?) for the Service are:

Tasks Contribute towards the adoption and implementation of an effective Performance and Risk Management Framework for the Community Plan, Partnership Plans, the Council’s Corporate Plan, Strategic Service Plans and Operational Team Plans. Tasks To develop a Corporate Risk Register and Operational Risk Registers which are actively used by the Council and each service in order to prioritise the risks to be managed and the actions required to manage those risks. Tasks Explore opportunities to provide a Risk Management Service to neighbouring Local Authorities. Tasks To update the Council's current Risk Management Strategy to reflect the new Local Government (Wales) Measure 2009, other best practice and statutory requirements and ensure implementation. Tasks In consultation with key partners develop a partnership Risk Management methodology/approach to support delivery of the Community Plan, Partnership Plans, the Council’s Corporate Plan and Outcome Agreement. Tasks Ensure that Risk Management forms a key part of financial planning and the Medium Term Financial Plan. Tasks To play a key role in the production of the Annual Governance Statement. Tasks To develop a clear understanding and knowledge of Risk Management so that Councillors and employees recognise and incorporate Risk Management as part of their role. 2.4 The Corporate Risk Manager is responsible for overseeing the day to day management of the Risk Management Service within the Council under the leadership of the Assistant Director – Chief Executives.

Risk Assessment Model

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Risk Management Progress Report and Updated Corporate Risk Register for 2011-12 Appendix 1Appendix 3 pages Download
PDF
Annual Risk Management Progress Report and Updated Corporate Risk Register for 2011-12 Appendix 2Appendix 18 pages Download
PDF
Annual Risk Management Progress Report and Updated Corporate Risk Register for 2011/12Report 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Annual Risk Management Progress Report and Updated Corporate Risk Register for 2011/12This decision
  2. Corporate Risk Management Quarter 3Approved
  3. Corporate Risk ManagementApproved
  4. MTCBC Local Flood Risk Management Strategy 2024Approved
  5. Annual Risk Management Report - Corporate Risk Register 2022-23Approved
  6. Risk Management Strategy/PolicyApproved

More from Merthyr Tydfil Governance and Audit Committee

All decisions
MeetingDecisionOutcome
28 Sep 2026 Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. Noted Open
28 Sep 2026 Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. Approved Open
28 Sep 2026 Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... Noted Open
22 Jun 2026 Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... Decided Open
1 Sep 2025 Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies