RESOLVED that: Project 1: Refurbishment of Afon Taf High School site be approved to progress within Band A with a budget of £12m. Project 2: New Ysgol Y Graig Primary School be approved within Band A with a budget of 7m. Project 3: Refurbishment of Pen y Dre High School site and Project 4: Refurbishment of Troedyrhiw Primary School be moved to Band B as priority schemes with effect from 2019/20. The Authority takes forward the Outline and Full Business Cases with appropriate external support in order to be able to progress the Band A priority projects. A further report on progress be brought to Council at the appropriate time.