CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Merthyr Tydfil County Borough Council
Planning, Regulatory and Licensing, Wednesday 7 January 2026 at 5.00pm

P/23/0065 - Land To The South West Of The A470/A4102, Roundabout At Rhydycar West, Merthyr Tydfil

Approved Planning 1 paper

AI summaryMerthyr Tydfil County Borough Council approved the Rhydycar West mixed leisure development, subject to detailed conditions, a Section 106 agreement and an amendment to Condition 24. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRequires Section 106 agreement and amendment to Condition 24. [D]
MoneyNot stated
What happens nextSecure Section 106 agreementNo agreement in reasonable time means committee reconsideration. [P144]
Who it affectsResidents, visitors, workers and habitatsTransport, ecology, heritage, safety and local benefits. [P140] [P143]

What was decided

The council approved outline application P/23/0065 for a mixed leisure development south west of the A470/A4102 roundabout at Rhydycar West. [D] [P4] Report P4

Approval is conditional on the report's conditions, a Section 106 agreement and an amendment to Condition 24. [D]

The outline allows an indoor snow centre up to 39,200 sq m, water park up to 7,500 sq m, activity centre up to 9,000 sq m, hotel up to 418 bedrooms, lodges up to 30 units and up to 830 parking spaces. [P4] Report P4

Why

Welsh Ministers cancelled the direction that had required their prior authorisation before the council could grant permission. [P6] [P13] Report P6, P13

Welsh Government acknowledged conflicts with national planning policy, but the Cabinet Secretary considered the issues suitable for the council to consider. [P11] [P16] Report P11, P16

Members had not supported the officer recommendation to refuse in March 2025, so the application returned for a conditional approval decision. [P5] [P16] Report P5, P16

What happens next

Before any decision notice, the applicant and interested parties must enter into a Section 106 agreement securing the listed terms. [P137] If no agreement is reached within a reasonable timescale, the application must return to committee. [P144] Report P137, P144

Access, appearance, landscaping, layout and scale details must be approved as reserved matters, with an application made not later than five years from the date of permission. [P18] [P19] Report P18, P19

At the stages set in the conditions, the applicant must submit environmental, transport, contamination, mining and heritage plans. Condition 24 requires a car parking strategy before development starts. [P26] [P57] [P78] [P87] [P101] [P117] Report P26, P57, P78, P87, P101, P117

Options considered

  • Chosen: Approve subject to conditions and a Section 106 agreement. The approval uses detailed conditions and a legal agreement to secure mitigation and local measures. [D] [P137] [P138] [P139] [P140] [P143] Report P137, P138, P139, P140, P143
  • Rejected: Refuse the application. This was the officer recommendation, but members did not support it. [P5] [P16] Report P5, P16
  • Rejected: Refer the application to Welsh Ministers for determination. Welsh Ministers concluded that the issues were suitable for the local planning authority to consider. [P8] [P11] Report P8, P11

Implications

  • Legal: A Section 106 agreement must be secured before a decision notice issues, covering the listed community, ecology, travel and energy terms. [D] [P137] [P138] [P139] [P140] [P142] Report P137, P138, P139, P140, P142
  • Environment: Conditions require approved plans to protect the SSSI, habitats and protected species, with monitoring and dark areas and routes for wildlife. [P30] [P34] [P36] [P40] [P42] [P47] Report P30, P34, P36, P40, P42, P47
  • Transport: The A470 junction, coach access, emergency access, shuttle bus, walking and cycling routes and electric vehicle charging are secured by conditions. [P75] [P77] [P80] [P83] [P94] [P98] [P99] Report P75, P77, P80, P83, P94, P98, P99
  • Risk: Contamination, drainage, groundwater and former coal mining risks require investigation, remediation, monitoring and confirmation that the site is safe and stable. [P57] [P70] [P71] [P117] [P121] [P123] Report P57, P70, P71, P117, P121, P123
  • Legal: Four named historic assets require conservation management and protection in perpetuity. [P102] [P103] Report P102, P103
  • Other: The agreement covers local labour, responsible supply chains, joint marketing, and preferential rates and tariffs for local residents. [P138] [P143] Report P138, P143
  • Financial: Long term conservation management requires identified funding that allows for costs to rise. [P36] [P39] Report P36, P39
  • Legal: Separate permissions may still be needed for drainage, highway works, rights of way and protected species licences. [P146] [P147] [P149] Report P146, P147, P149

Who and where

  • Local residents Report P127, P143
  • Visitors Report P141, P143
  • Operational and construction staff Report P138, P141
  • Suppliers to the development Report P138
  • Public rights of way users Report P15, P147
  • Walking and cycling users Report P83, P94, P99
  • Emergency services Report P80, P85, P96
  • Protected species and habitats Report P35, P40, P42

Timeline

  • 9th March 2023: Application dated, with MTCBC as determining authority. Report P2
  • 15th March 2024: Direction issued under Article 18, requiring prior Welsh authorisation. Report P6, P13
  • 12th March 2025: Members did not support the officer recommendation to refuse. Report P5
  • 21st November 2025: Welsh Government confirmed that the application would not be called in. Report P8
  • 7th January 2026: The council approved the application subject to conditions, a Section 106 agreement and an amendment to Condition 24. Report P1
  • Prior to the issuance of any decision notice: The applicant and interested parties must enter into a Section 106 agreement. Report P137
  • Not later than five years from the date of this permission: An application for approval of reserved matters must be made. Report P19
  • Before the expiration of seven years from permission or two years after the last reserved matter is approved, whichever is later: Development must begin. Report P21

Plain English for the jargon

  • Local Planning Authority: The council responsible for deciding the application and approving plans under the conditions. [P18] [P137]
  • Section 106 agreement: A legal agreement required before the decision notice, securing community, biodiversity, travel, energy and resident benefit measures. [P137] [P138] [P139] [P140] [P142] [P143]
  • Reserved matters: Access, appearance, landscaping, layout and scale details requiring the council's written approval. [P18]
  • Construction Environment Management Plan: The plan required before site clearance and construction to manage environmental risks and controls. [P26] [P28]
  • Green Infrastructure Statement: The detailed statement required before ground works or vegetation clearance. [P30]
  • Construction Traffic Management Plan: The plan required before development starts to manage construction vehicles, traffic and parking. [P87]
  • DMPWO: Town and Country Planning (Development Management Procedure) (Wales) Order 2012. [P13]
  • SSSI: A site for which the conditions require protection during development. [P40] [P41]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31

Resolved

Resolved that: The application be approved subject to the conditions outlined in the report, a Section 106 agreement and the amendment to Condition 24.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Planning, Regulatory and Licensing, 88 pages

DATE WRITTEN 19th December 2025 REPORT AUTHOR Judith Jones CASE OFFICER Gareth Davies COMMITTEE Planning and Regulatory COMMITTEE DATE 7th January 2026

Application No. Date Determining Authority P/23/0065 9th March 2023 MTCBC

Proposed Development Location Name & Address of Applicant/Agent

Outline application for erection of Land To The South West Marvel Ltd a mixed leisure development Of The A470/A4102 c/o CarneySweeney comprising Indoor Snow Centre Roundabout At Rhydycar F.a.o. [name removed] (up to 39,200 sq m), Water park West Brunel House (up to 7,500 sq m), Indoor Merthyr Tydfil 2 Fitzalan Road Activity Centre (up to 9,000 sq Cardiff m), Outdoor Activity Centre, Hotel Accommodation (up to 418 bedrooms), Woodland Lodge accommodation (up to 30 units), car parking (up to 830 spaces) and associated earthworks, access, drainage, servicing and utilities connections/infrastructure PURPOSE OF REPORT To further consider planning application P/23/0065

At the Planning, Regulatory and Licensing Committee meeting held on the 12 th March 2025, Members did not support the officer recommendation to refuse the application.

Members will be aware that on 15th March 2024, Welsh Government’s Minister for Climate Change issued a Direction under Article 18 of the Town and Country Planning (Development Management Procedure) (Wales) Order 2012, Directing the Council not to grant planning permission for this application without the prior authorisation of the Welsh Ministers.

The direction was issued to enable WG to give further consideration to whether or not the application should be referred to the Welsh Ministers for their determination.

On the 21st November 2025 the Council received confirmation from Welsh Government that the application will not be called in for consideration by the Welsh Ministers. The letter advised that:-

“Consideration has been given to the concerns expressed in the call-in requests, the contents of the LPA’s planning officer’s report to the planning committee, the committee’s decision (being minded to grant planning permission) and any other relevant information.

Decision

The Cabinet Secretary for Economy, Energy and Planning has concluded that while issues of conflict with national policy exist, in this case they are of a scale and complexity which she is content for the LPA to consider. The application will not be called in for determination by the Welsh Ministers.

The decision not to call in the application should not in any way be taken as a reflection of the planning merits of the development.

In exercise of my powers under Article 31 of the Town and Country Planning (Development Management Procedure) (Wales) Order 2012 (“DMPWO”), the direction issued by Welsh Ministers under Article 18(1) of the DMPWO on 15 March 2024 for planning application P/23/0065 is hereby cancelled.”

Since the original report was presented to Committee in March 2025 one email of support, endorsing the skiing opportunities it would give to the next generation, has been received. One email raising objection with 20 attachments has also been received. The 20 documents cover a range of topic areas that includes a series of notes cataloguing the variety of species in the area that identifies Gelligaer and Merthyr Common as the most biodiverse area of the UK. The objections made reiterate the concerns that Members had regard to when this application was first considered on 12th March 2025 and can be summarised as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/23/0065: Land To The South West Of The A470/A4102, Roundabout At Rhydycar West, Merthyr TydfilReport 88 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. P/23/0065 - Land To The South West Of The A470/A4102, Roundabout At Rhydycar West, Merthyr TydfilThis decision
  2. P/23/0065 - Land to The South West Of THe A470/A4102 Roundabout At Rhydycar West, Merthyr TydfilApproved
  3. P/22/0284 - Land to the South West of 152 Heolgerrig, Heolgerrig, Merthyr TydfilApproved
  4. P/23/0197 - Land adjoining (South of) Swansea Road to the East of Waunbant Court and North West of Old Winchfawr Road Swansea Road, Merthyr TydfilApproved
  5. P/18/0316 - Land Adjoining (south of) Swansea Road to the east of Waunbant Court and north west of Old Winchfawr Road, Merthyr TydfilApproved
  6. P/18/0316 - Land Adjoining (south of) Swansea Road to the east of Waunbant Court and north west of Old Winchfawr Road, Swansea Road, Merthyr TydfilDecided

More from Merthyr Tydfil Planning, Regulatory and Licensing

All decisions
MeetingDecisionOutcome
2 Sep 2026 Minutes of meeting Friday, 1 May 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 17 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Tuesday, 30 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Planning, Regulatory and LicensingResolved that: The minutes be approved as an accurate record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies