P/25/0317 - Brynhyfryd House, Cilsanws Lane, Cefn Coed, Merthyr Tydfil, CF48 2NU

Approved Planning 1 paper

AI summaryMerthyr Tydfil County Borough Council approved the application for a large side outbuilding at Brynhyfryd House, subject to three conditions covering completion, approved plans and bat and bird boxes. [D] [P12] [P18] [P19] [P21] [P26]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyNot stated
What happens nextMeet three conditions [P18]
Who it affectsNearby residents [P13] [P14]

What was decided

The application was approved subject to the conditions in the report. [D] [P18] Report P18

The development must begin no later than five years from the date of the decision. [P19] [P20] It must follow the approved plans and documents. [P21] [P25] Report P19, P20, P21, P25

Before beneficial use, one bat box and two bird boxes must be installed and kept permanently. [P16] [P26] [P27] Report P16, P26, P27

Why

The outbuilding would not appear out of place in its setting, and its design and appearance were considered acceptable. [P12] Report P12

Officers found no unacceptable overbearing effect, harmful loss of light, overshadowing or loss of privacy for nearby residents. [P13] [P14] No objections were received following the publicity exercise. [P3] [P14] Report P3, P13, P14

Vehicular access would remain unchanged. [P15] There was adequate space in the front garden for garage access and for vehicles to leave the site in a forward gear. [P15] The proposal was assessed against the duty to improve Wales's economic, social, environmental and cultural well-being. [P17] Report P15, P17

What happens next

Begin development no later than five years from the date of the decision. [P19] Report P19

Carry out the work in accordance with the approved plans GA003 Rev. A, GA004 Rev. A and GA005 Rev. A. [P21] [P22] [P23] [P24] [P25] Report P21, P22, P23, P24, P25

Install one bat box and two bird boxes in accordance with GA005 Rev. A before beneficial use, and keep them permanently. [P16] [P26] [P27] Report P16, P26, P27

Options considered

  • Chosen: Approve the application subject to conditions. The report found the proposal acceptable in design, neighbouring amenity, access and parking terms. [D] [P12] [P13] [P14] [P15] [P18] Report P12, P13, P14, P15, P18
  • Rejected: Undertake a consultation exercise. No separate consultation exercise was considered necessary. [P1] Report P1
  • Rejected: Require a Green Infrastructure Statement. A statement was considered disproportionate and unreasonable for a domestic outbuilding on maintained grass. [P16] Report P16
  • Chosen: Secure habitat enhancement through condition. One bat box and two bird boxes would contribute to green infrastructure objectives and would be secured by condition. [P16] [P26] Report P16, P26

Implications

  • Legal: The permission is conditional, with requirements on timing, approved plans and habitat boxes. [P18] [P19] [P21] [P26] Report P18, P19, P21, P26
  • Risk: Officers raised no concerns about visual impact, overbearing effects, light loss, overshadowing, privacy, parking or highway safety. [P12] [P13] [P14] [P15] Report P12, P13, P14, P15
  • Legal: The proposal was assessed under the sustainable development duty in the 2015 Act. [P17] Report P17
  • Other: A Green Infrastructure Statement was considered disproportionate and unreasonable. [P16] One bat box and two bird boxes would instead contribute to green infrastructure objectives and be secured by condition. [P16] [P26] Report P16, P26
  • Legal: The stated legal reason for the timing condition is Section 91 of the Town and Country Planning Act 1990. [P20] Report P20
  • Other: Future Wales and Planning Policy Wales provided the national planning context, with Policy SW11 applied locally. [P6] [P8] [P10] [P12] Report P6, P8, P10, P12

Who and where

  • The applicant Report P18, P19, P21, P26, P27
  • The resident to the west Report P13
  • The resident to the north Report P13, P14
  • The resident to the south Report P14
  • Vehicles using the site access Report P15

Timeline

  • 27th November 2025: Letters were sent to neighbouring properties. [P2] No objections were received following the publicity exercise. [P3] Report P2, P3
  • 2026-02-04: The committee approved the application subject to conditions. [D]
  • 25 November 2026: The drawings GA003 Rev. A, GA004 Rev. A and GA005 Rev. A were recorded as received. [P21] [P22] [P23] [P24] Report P21, P22, P23, P24
  • Not later than five years from the date of this decision: Development must begin. [P19] Report P19
  • Before the outbuilding is brought into beneficial use: The bat and bird boxes must be installed. [P26] Report P26

Plain English for the jargon

  • LDP: The Merthyr Tydfil County Borough Council Replacement Local Development Plan, containing Policy SW11. [P10]
  • SW11: A policy on sustainable design and place making used to assess the application. [P10] [P12]
  • GIS: Green Infrastructure Statement. [P16] Chapter 6 of Planning Policy Wales requests it for applications, but a submission was considered disproportionate and unreasonable here. [P16]
  • WBFG Act: The 2015 Act on the wellbeing of future generations in Wales, used to assess sustainable development. [P17]
  • EnW1 and EnW2: Local plan policies cited to protect the natural environment. [P27]
  • Beneficial use: Use of the approved outbuilding, before which the bat and bird boxes must be installed. [P26]
  • Overlooking: Looking towards or into a neighbouring property, assessed for privacy impacts. [P14]
  • Overshadowing: Shading affecting a neighbouring property, assessed with potential light loss. [P13]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42

Resolved

Resolved that: The application be approved subject to the conditions outlined in the report.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Planning, Regulatory and Licensing, 5 pages

Consultation

No consultation exercise was considered necessary in this instance. PUBLICITY

In accordance with the Town & Country Planning (Development Management Procedure) (Wales) Order 2012, letters were sent to neighbouring properties on the 27th November 2025.

No letters of objection were received following this publicity exercise.

POLICY CONTEXT

National Development Framework

Future Wales: the National Plan 2040 (February 2021) sets out a strategy for addressing key national priorities through the planning system, including sustaining and developing a vibrant economy, achieving decarbonisation and climate-resilience, developing strong ecosystems and improving the health and well-being of our communities.

National Planning Policies

Planning Policy Wales (Edition 12, February 2024)

Local Planning Policies

Policy SW11: Sustainable design and place making of the Merthyr Tydfil County Borough Council Replacement Local Development Plan 2016-2031 is relevant to the determination of this planning application. Furthermore, the application will be determined having regard to the advice contained within Supplementary Planning Guidance Note 6, A Design Guide for Householder Development.

PLANNING CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/25/0317: Brynhyfryd House, Cilsanws Lane, Cefn Coed, Merthyr Tydfil, CF48 2NUReport 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Merthyr Tydfil Planning, Regulatory and Licensing

All decisions
MeetingDecisionOutcome
2 Sep 2026 Minutes of meeting Friday, 1 May 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 17 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Tuesday, 30 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Planning, Regulatory and LicensingResolved that: The minutes be approved as an accurate record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies