Bedlinog 72 Diversion

Approved Committee 2 papers

AI summaryMerthyr Tydfil County Borough Council's Way Committee decided to make a diversion order for part of Bedlinog 72 [D]. Confirmation requires no unresolved objections or representations, and the rights of way department will meet costs [D][5.0].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConfirmation needs no unresolved objections or representations [D]
MoneyCouncil funded [5.0]Rights of way department will meet order and inquiry costs [5.0]
What happens nextRefer unresolved orders [D]Planning Inspectorate determines the affected order [D]
Who it affectsBedlinog 72 users and council [3.5][P13]Both routes are on council owned land [3.5][P13]

What was decided

The Way Committee decided to make an order under section 119 of the Highways Act 1980 to divert a section of public footpath Bedlinog 72 [D].

The order will be confirmed if no objections or representations are made during the prescribed period, or if any made are withdrawn [D].

If objections or representations made during the prescribed period are not withdrawn, the order will be referred to the Planning Inspectorate for determination [D].

Why

The existing path has suffered severe erosion, repeated closures and severe storm damage, making it difficult to traverse [3.5][3.6]. Report 3.5, 3.6

Engineers and the parks department found that a diversion to the opposite side had better terrain, would keep the same start and end points, and would not be less convenient for the public [3.7]. The proposed route would also have a better surface [P11]. Report 3.7, P11

The original path would gain improved drainage, and no compensation would be payable because the existing land and proposed path are both council owned [P12][P13]. Report P12, P13

What happens next

Undertake the formal consultation if the diversion is confirmed [P23]. Report P23

Confirm the order if there are no objections or representations during the prescribed period, or if all objections or representations are withdrawn [D].

Refer the order to the Planning Inspectorate for determination if objections or representations are not withdrawn [D].

Options considered

  • Chosen: Divert the path to the opposite side of the park. Engineers and the parks department agreed that the opposite side had better terrain, would not change the start or end point, and would not be less convenient for the public [3.7]. Report 3.7
  • Rejected: Keep the existing route without diversion. The existing route had severe erosion, repeated closures and was becoming a drainage swale [3.5][P11]. Report 3.5, P11
  • Rejected: Wait to divert until the repair outcome is known. A pre order representation said this was premature because it was unclear whether the damage and erosion had been overcome [P20]. Report P20

Implications

  • Legal: If objections or representations are not withdrawn, the order will be referred to the Planning Inspectorate for determination [D]. The report also notes a possible public inquiry and says the Secretary of State must be satisfied that the diversion does not change where the path ends and is substantially as convenient for the public [3.4][5.0]. Report 3.4, 5.0
  • Financial: The rights of way department will meet the costs of making the order and any public inquiry [5.0]. Report 5.0
  • Financial: No compensation is payable because the existing land and proposed path are both council owned [P13]. Report P13
  • Risk: Storm Bert caused the most significant damage to date [3.6]. A pre order representation said erosion might recur and that vehicles using the proposed route at speed created a clear conflict with genuine footpath users [P19][P24]. Report 3.6, P19, P24
  • Other: The existing path is being improved with a drainage swale, new attenuation ponds and desilting of existing ponds, following Welsh Government storm funding secured for the site [3.6][3.8]. Report 3.6
  • Other: The existing route is approximately 752 metres long [4.1]. The proposed route shares the start point, crosses a newly installed footbridge after approximately 425 M, then rejoins the original path for 244m to Grid Reference ST 1010 0198 [4.2][4.3][4.4]. The new footbridge would be the responsibility of the rights of way section [4.3]. Report 4.1, 4.2, 4.3, 4.4
  • Equalities: The protected characteristics assessment, including Welsh Language, recorded 1 of 10 positive, 0 of 10 negative and 9 of 10 not applicable [P33]. Report P33
  • Other: The assessment recorded 2 of 4 positive, 0 of 4 negative and 2 of 4 not applicable wellbeing objectives; 5 of 5 positive, 0 of 5 negative and 0 of 5 not applicable sustainable development principles; and 1 of 1 positive, 0 of 1 negative and 0 of 1 not applicable biodiversity impacts [P31][P32][P34]. Report P31, P32, P34

Who and where

  • People who use the existing Bedlinog 72 footpath Report 3.5, 3.7
  • People who would use the proposed route, including sports personnel accessing playing fields Report 3.7, P24
  • The sports club using the playing fields Report P24
  • Merthyr Tydfil County Borough Council and its rights of way department Report 3.5, P13, 5.0
  • The Planning Inspectorate if objections or representations are not withdrawn
  • The friends on Nant Lwynog, who made a pre order representation Report 3.9, P20

Timeline

  • November 2024: Storm Bert caused the most significant damage to date to the existing path [3.6]. Report 3.6
  • April 2025: A pre order representation said the repair works were not due for completion before this date [P19]. Report P19
  • Before the order: Pre order consultation was carried out, no formal objections were received, and an email was received from the friends on Nant Llynog [3.9]. Report 3.9
  • 7th January 2026: The rights of way report was written [P2]. Report P2
  • 4th February 2026: The Way Committee decided the diversion order [P2][D]. Report P2
  • After the order, if confirmed: Another formal consultation will take place before confirmation [P23]. Report P23
  • During the prescribed period: Objections or representations may be made about confirmation of the order [D].

Plain English for the jargon

  • Diversion order: An order changing the route of a footpath or bridleway [3.2][3.4].
  • Section 119: The Highways Act 1980 power used by local authorities to make diversion orders [3.2][3.4].
  • Confirmation: Approval of the diversion order, subject to the prescribed objection process [D].
  • Prescribed period: The period for objections or representations about confirmation of the order [D].
  • Planning Inspectorate: The body that determines an order referred because objections or representations are not withdrawn [D].
  • Public right of way: The public footpath affected by the proposed Bedlinog 72 diversion [1.0].
  • Drainage swale: The existing path area being incorporated as drainage in the improvement scheme [3.8][P11].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item233

Resolved

Resolved that: 2.1 Taking into consideration all the evidence which has been provided, that an order be made under s119 Highways Act 1980 to divert a section of the public footpath. 2.2 To approve the confirmation of the Order made as a result of (a) above provided no objections or representations are made within the prescribed period or if any objections or representations made are so withdrawn. 2.3 If any objections or representations are made within the prescribed period are not subsequently withdrawn then to refer the relevant Order to the Planning Inspectorate for determination
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Way, 5 pages

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

Rights of Way Report Date Written 7th January 2026 Report Author Beth Jones/Geraint Morgan Service Area Economic Development Committee Division Place & Transformation Exempt/Non Exempt Non Exempt Committee Date 4th February 2026

Bedlinog 72 Diversion

1.0SUMMARY OF THE REPORT 1.1 To inform Councillors of the need to divert the Public Right of Way Bedlinog 72 under Section 119 of the Highways Act 1980.

2.0RECOMMENDATION(S) that 2.1 Taking into consideration all the evidence which has been provided, that an order be made under s119 Highways Act 1980 to divert a section of the public footpath.

2.2To approve the confirmation of the Order made as a result of (a) above provided no objections or representations are made within the prescribed period or if any objections or representations made are so withdrawn.

2.3If any objections or representations are made within the prescribed period are not subsequently withdrawn then to refer the relevant Order to the Planning Inspectorate for determination.

3.0INTRODUCTION AND BACKGROUND 3.1 Local Authorities have the power under Section 119 of the Highways Act 1980, to make orders for the diversion of footpaths or bridleways.

3.2The legal criteria for the diversion of a path under the Highways Act can be found at Agenda Item 3. 3.3 Welsh Office Circular 5/93 states that the power for local authorities to make orders for the diversion of footpaths or bridleways is contained within Section 119 of the Act. Orders may be made in the interests of the owner, lessee, or occupier of the land concerned, or authorities may initiate the order themselves in the interest of the public.

3.4When making an order local authorities must be prepared to show why they consider the diversion proposed is in the interests of the owner, lessee or occupier, or the public since the Secretary of State, when considering the confirmation of the order, must be satisfied that the diversion does not alter the point of termination of the path or way otherwise than to another point on the same highway, or one connected with it, and which is substantially as convenient to the public. Other considerations to be taken into account in relation to the question of confirmation are:

a) The effects the diversion would he on the public enjoyment of the path or way as a whole; The diverted route is a better surface for the users and the existing route is also becoming a drainage swale

b) The implementation of the order would have on the land served by the existing right of way; There would be a positive effect on the land as the original path will have increased drainage.

c) The new right of way would have on the land it crosses and other land held within that land. Before deciding to make an order local authorities may, under Section 119(5) of the Act, require an applicant to defray or contribute towards any compensation payable, or any expenses which they may incur in bringing the new path or way into a fit condition for use by the public. There would not be any compensation payable as the existing land and proposed path are both on land owned by the local authority.

3.5The footpath in question is located on Nant LLwynog park in Bedlinog, and is situated on Local Authority Owned land. The footpath is a well used path but over recent years when there is bad weather and storms the path has been subject to severe erosion, there has been significant money spent repairing the path but due to other factors with the site the path kept eroding. The path has had a number of closures on it due to the severe erosion making it very difficult to traverse along.

3.6In the recent storm Bert of November 2024 more damage was encountered to the path and this was the most significant to date. The engineering department visited the site and subsequently applied to Welsh Government under the storm Bert funding to improve the site and the path.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 1 pages Download
PDF
Bedlinog 72 DiversionReport 5 pages DownloadRead as text

At this meeting

Whole meeting
232Rights of Way GuidanceOn the agenda
233Bedlinog 72 DiversionThis decision

On this subject at Merthyr Tydfil

Search all
  1. Bedlinog 72 DiversionThis decision
  2. S.119 Highways Act 1980, Application for the Diversion of Part of Footpath 41 (Bedlinog)Approved

More from Merthyr Tydfil Way

All decisions
MeetingDecisionOutcome
8 Jul 2026 Troedyrhiw 120Resolved that: In respect of Troedyrhiw 120 a. On the balance of probabilities, there is sufficient evidence to suppo... Approved Open
8 Jul 2026 Troedyrhiw 206Resolved that: In respect of Troedyrhiw 206 a. On the balance of probabilities, there is sufficient evidence to suppo... Approved Open
9 Oct 2024 Guidance on the law relating to the continuous review of the Definitive Map and Statement of Public Rights of WayResolved that: The report for Information be received. Decided Open
9 Oct 2024 Treharris 38Resolved that: The application be rejected as on the balance of probability the normal period looked at for the purpo... Refused Open
28 Feb 2024 Vaynor 34Resolved that: In respect of Vaynor Plan 34 1. To approve the making of the Definitive Map Modification Order to rect... Approved Open