CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Merthyr Tydfil County Borough Council

Quarterly Update on Corporate Risk Quarter 3 2025/26

Approved Finance 2 papers

AI summaryMerthyr Tydfil County Borough Council's governance committee approved the corporate risk report recommendations for Quarter 3 2025/26, including the January 2026 risk register [D] [P1].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThe committee approved the recommendations contained in the report [D].
MoneyNot stated
What happens nextNot stated
Who it affectsCorporate risk register [P1]Appendix 1 covers Quarter 3, January 2026 [P1].

What was decided

The Combined Governance & Audit Committee / Joint Scrutiny Committee approved the recommendations contained in the report [D].

Why

The Corporate Management Team had been consulted about each proposal and recommendation [P3]. Report P3

Implications

  • Risk: The report concerns the Council's Corporate Risk Register for Quarter 3, January 2026 [P1]. Report P1
  • Legal: The report raises the question of whether any issue may affect the Council's Constitution [P2]. Report P2
  • Other: The Corporate Management Team was consulted on each proposal and recommendation [P3]. Report P3

Who and where

  • Merthyr Tydfil County Borough Council Report P2, P3
  • Corporate Management Team Report P3

Timeline

  • Quarter 3 2025/26: Corporate risk reporting period [P1] Report P1
  • January 2026: Corporate Risk Register appendix [P1] Report P1

Plain English for the jargon

  • Corporate Risk Register: Quarter 3 corporate risk appendix, January 2026 [P1].
  • Corporate Management Team: Management body consulted on each proposal and recommendation [P3].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item634

Resolved

Resolved that; The recommendations as contained within the report be approved.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Combined Governance & Audit Committee / Joint Scrutiny Committee, 6 pages

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

JOINT SCRUTINY & GOVERNANCE AND AUDIT COMMITTEE

Date Written 29th January 2026 Report Author A Mogford Service Area Policy & Performance Exempt/Non Exempt Non Exempt Committee Date 9th February 2026

QUARTERLY UPDATE ON CORPORATE RISKS QUARTER 3 2025/26

1.0SUMMARY OF THE REPORT

1.1The purpose of this report is to provide assurance regarding updates on progress against the Council’s Corporate Risk Register (CRR) at the end of quarter 3 2025- 26.

1.2This report builds on actions implemented to address recommendations of an internal audit.

1.3A review of quarter 3 took place including as part of the Corporate Management Team meeting on the 28th January 2026. The corporate risk register (as at the end of quarter 3) can be found in appendix 1.

2.0RECOMMENDATIONS that

2.1the contents of this report be noted and debated.

3.0INTRODUCTION AND BACKGROUND 3.1 The purpose of this report is to provide assurance regarding updates on progress against the Council’s Corporate Risk Register (CRR) at the end of quarter 3 2025- 26. 3.2 The Council has updated its Corporate Risk Register (CRR) using the existing policy and strategy. Corporate risks have been reviewed against the following:

 Significant threats to the achievement of the Council’s Priorities.  Potential opportunities that may better enable delivery of the Council’s Priorities.  Other significant risks that would have an impact beyond any one service area and/or are of such significance that they need to be monitored corporately that have not been identified as Priorities.

(MTCBC Risk Management Strategy and Policy, January 2025)

4.0WHERE WE WERE 4.1 At the end of quarter 2 2025/26 the Council had identified 12 corporate risks. You can find a breakdown of risk scores and further information in Appendix 1.

4.2We highlighted in previous reports to the Governance and Audit Committee (GAC) that Internal Audit are conducted an audit regarding Corporate Risk and our processes. This is now complete and further information can be found below.

4.3It was agreed at a previous GAC meeting that awareness workshops were to be held with the GAC and Scrutiny Committees regarding Corporate Risk Management and that Scrutiny consider the Corporate Risk Register (CRR) in forward programmes.

5.0WHERE WE ARE NOW 5.1 The Corporate Risk Register (CRR) has been reviewed by the CMT at a meeting held on the 29th January 2026. This was done using the risk management policy and strategy and following analysis of the CRR following input from risk owners.

5.2There are 2 proposed changes to the risk scores at quarter 3, both risks to be increased. This is summarised in the table and chart below with more information available in appendix 1. Progress against mitigations has slowed in quarter 3, so there will be a focus on increasing progress in quarter 4. 5.3 The following table sets out the rationale for changing risk scores.

Corporate Risk Rationale to change the risk score CRR4 The main reason for increased risk score is the lower than anticipated completion of on-line training. This has been reported to the Corporate Management Team with it being a focus in quarter 4. CRR12 This is based on the current position regarding SPF funding. Mitigation is being considered. 5.4 The Policy and Performance Manager has continued to engage with Scrutiny Support Officers to inform them of changes to the CRR so they can brief Scrutiny Chairs. As such, the risks on the CRR are being included for consideration in future scrutiny forward work programmes.

5.5Corporate risk awareness workshops have been held with all Scrutiny Committees and the Governance and Audit Committee. Feedback has been positive with information being used to shape how we manage risk going forward.

5.6The internal audit referred to above has been completed with an outcome of ‘substantial assurance’ was achieved and two minor recommendations given. These are detailed in the table below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2 pages Download
PDF
Quarterly Update on Corporate Risk Quarter 3 2025/26Report 6 pages DownloadRead as text

At this meeting

Whole meeting
634Quarterly Update on Corporate Risk Quarter 3 2025/26This decision
635Draft Revenue Budget 2026/27Approved

More from Merthyr Tydfil Combined Governance & Audit Committee / Joint Scrutiny Committee

All decisions
MeetingDecisionOutcome
9 Feb 2026 Draft Revenue Budget 2026/27Resolved that: The recommendations as contained within the report be approved. Approved Open
17 Apr 2023 ExemptResolved that: The public be excluded from the Meeting on the grounds that it involves the likely disclosure of exemp... Decided Open
13 Feb 2023 ExemptResolved that: The public be excluded from the Meeting on the grounds that it involves the likely disclosure of exemp... Decided Open
26 Jan 2023 ExemptResolved that: The public be excluded from the Meeting on the grounds that it involves the likely disclosure of exemp... Decided Open
26 Jan 2022 Revenue Budget 2022/23 and Medium Term Financial Plan UpdateResolved that : The content of the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies