Cabinet, Wednesday 11 February 2026 at 4.00pm

Aberdare Road, Merthyr Tydfil - Proposed Traffic Regulation Order

Approved Executive 4 papers

AI summaryMerthyr Tydfil Cabinet approved a conditional plan for permanent Traffic Regulation Orders on Aberdare Road. [D] Road user consultation and public notice are required, with process costs met from the 2025/26 Welsh Government 20mph grant award. [D] [4.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNo objections: make Orders; objections: committee report [D]
Money2025/26 Welsh Government 20mph grant award [4.1]Covers process costs, advertising and signage changes [4.1]
What happens nextConsult road users; give notice [D]Permanent Orders remain conditional on consultation and notice [D]
Who it affectsAffected road users [D]The Orders' effect is detailed in Appendix 1 [D]

What was decided

Approved the council's intention to make permanent Traffic Regulation Orders under the Road Traffic Regulation Act 1984. [D] This was subject to consultation with a representative list of road users and giving public notice. [D]

Approved making the permanent Orders if no objections are received. [D]

Approved presenting a report to the appropriate Committee for consideration as soon as practicable if objections are received. [D]

Why

Corporate Management Team had been consulted on each proposal and recommendation. [P7] Elected members had been engaged and a public consultation had been carried out, with further public representations possible after Cabinet approval. [5.0] Report P7, 5.0

The proposals were informed by Welsh Government guidance, traffic speed surveys and knowledge of the location. [P4] Report P4

No negative impacts were identified in the assessment. [P4] Report P4

What happens next

Consult a representative list of road users and give public notice of the intention to make permanent Orders. [D] The public can then make representations following Cabinet approval. [5.0] Report 5.0

If no objections are received, make the permanent Orders. [D]

If objections are received, present a report to the appropriate Committee as soon as practicable. [D]

The money

  • 2025/26 Welsh Government 20mph grant award Will meet costs of the traffic regulation order process, statutory advertising and required signage changes [4.1] Report 4.1

Options considered

  • Chosen: Make the permanent Orders if no objections are received. Consultation and public notice are approval conditions [D]
  • Chosen: Present a report to the appropriate Committee if objections are received. Objections trigger consideration by the appropriate Committee [D]

Implications

  • Financial: The 2025/26 Welsh Government 20mph grant award will meet traffic regulation order process costs, including statutory advertising and required signage changes. [4.1] Report 4.1
  • Legal: The report identified no issue that may impact the Council's Constitution. [P6] Any permanent Orders must be made under the Road Traffic Regulation Act 1984, with making conditional on consultation, public notice and no objections. [D] Report P6
  • Equalities: The assessment recorded 9 of 9 protected characteristic impacts as neutral or not applicable. [5.0] It also recorded 6 of 6 socioeconomic disadvantage impacts as neutral or not applicable. [5.0] Report 5.0
  • Climate: The assessment recorded 6 of 6 decarbonisation impacts as neutral or not applicable. [5.0] Report 5.0
  • Other: The assessment recorded 1 of 1 biodiversity and ecosystems impact as maintained. [5.0] Report 5.0
  • Other: The assessment recorded 4 of 4 wellbeing objectives as neutral or not applicable. [5.0] It recorded 5 of 5 sustainable development principles as positive. [5.0] Report 5.0
  • Other: The assessment recorded 2 of 4 Welsh language impacts as positive and 2 of 4 as neutral or not applicable. [5.0] Public notices will incorporate Welsh, and the language will continue to be promoted through the project. [P3] Report 5.0, P3
  • Risk: If objections are received, a report must go to the appropriate Committee as soon as practicable before the Orders are made. [D]

Who and where

  • Road users affected by the permanent Orders [D]
  • People able to make representations after Cabinet approval [5.0] Report 5.0
  • People with protected characteristics, with impacts recorded as neutral or not applicable [5.0] Report 5.0
  • People facing socioeconomic disadvantage, with impacts recorded as neutral or not applicable [5.0] Report 5.0

Timeline

  • 2026-02-11: Cabinet considered the proposed Traffic Regulation Order [D]
  • Following Cabinet approval: The public can make representations [5.0] Report 5.0
  • As soon as practicable: A report goes to the appropriate Committee if objections are received [D]

Plain English for the jargon

  • TRO: Short form for Traffic Regulation Order in this report [D]
  • Public Notice: Notice of the council's intention to make the permanent Orders [D]
  • 20mph grant: The 2025/26 Welsh Government grant award covering TRO process costs [4.1]
  • Integrated Impact Assessment: Assessment of positive, negative, and neutral or not applicable impacts [5.0]
  • Appropriate Committee: The Committee that would consider a report if objections are received [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76

Resolved

Resolved that: 2.1 Subject to consultation with a representative list of roads users, the giving of Public Notice of the County Borough Council’s intention to make permanent Traffic Regulation Orders under the Road Traffic Regulation Act 1984, the effect of which is detailed in the schedules at Appendix 1, be approved. 2.2 In the event of no objections being received, the making of the said permanent Orders be approved. 2.3 If objections are received the presentation of a report to the appropriate Committee for consideration as soon as practicable, be approved.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 4 pages

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

CABINET REPORT Date Written 16th January 2026 Report Author Gareth Jones Service Area Engineering Committee Division Portfolio Exempt/Non-Exempt Non-Exempt Committee Date 11th February 2026

Aberdare Road, Merthyr Tydfil – Proposed Traffic Regulation Order

1.0SUMMARY OF THE REPORT 1.1 A Traffic Regulation Order (TRO) is required to be progressed for Aberdare Road in order to increase the Welsh Government (WG) default 20mph speed limit to 30mph. This follows the recent review undertaken in light of updated guidance issued by Welsh Government.

1.2For Councillors to authorise the intention that subject to satisfactory consultation with a representative list of roads users (Police, Fire, Ambulance Services, Bus operators etc.), Public Notice be given informing of the County Borough Council’s proposal to make permanent Traffic Regulation Orders under the Road Traffic Regulation Act 1984 and in the event of no objections, the Orders be made.

2.0RECOMMENDATION that

2.1Subject to consultation with a representative list of roads users, the giving of Public Notice of the County Borough Council’s intention to make permanent Traffic Regulation Orders under the Road Traffic Regulation Act 1984, the effect of which is detailed in the schedules at Appendix 1, be approved;

2.2In the event of no objections being received, the making of the said permanent Orders be approved;

2.3If objections are received the presentation of a report to the appropriate Committee for consideration as soon as practicable, be approved; 3.0 INTRODUCTION AND BACKGROUND 3.1 Aberdare Road - Proposed Traffic Regulation Order.

3.2The Welsh Government (WG) introduced a default 20mph speed limit on restricted roads across Wales on 17th September 2023. Local authorities were provided with guidance outlining the criteria under which exemptions to the default limit could be applied.

3.3Following practical implementation, WG issued revised guidance in late 2024 to support local authorities in reviewing locations where a 30mph speed limit may be more appropriate. This updated guidance provides greater clarity on road function, frontage density, strategic movement, and active‑travel considerations. In addition, members of the public were also invited to submit requests to local authorities for any roads they believed should be considered in relation to the revised guidance.

3.4In line with this revised guidance, a review has been undertaken for Aberdare Road by the Engineering department. The assessment of Aberdare Road against the WG revised criteria identifies that the road performs a strategic movement function connecting key parts of the network, the property frontage density is very low, footway provision is appropriate and traffic movement align more closely with 30mph than a 20mph setting.

3.5Elected Members within Park and Cyfarthfa Wards were consulted and a public consultation was undertaken on the proposal. The results of the consultation are shown below:

3. C3. C

2. Aberdare Road, Georgetown has been identified as potentially suitable for a speed limit change reverting back to 30mph.

Response Response Answer Choices Percent Total

Yes, I support the current 1 20mph speed limit reverting 77.40% 2541 back to 30mph No, I do not support the current 2 20mph speed limit reverting 22.60% 742 back to 30mph answered 3283 skipped 0 has been identified as potentially suitable for a speed limit change has been identified as potentially suitable for a speed limit change 3.6 It is therefore proposed that a Traffic Regulation Order (TRO) be progressed in order to increase the Welsh Government (WG) default 20mph speed limit to 30mph on Aberdare Road. The 30mph speed limit would apply from the junction of Ynysfach in a Westerly direction for a distance of 480 metres as shown in Appendix 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Aberdare Road, Merthyr Tydfil: Proposed Traffic Regulation OrderReport 4 pages DownloadRead as text
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
iiaReport 15 pages Download

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Aberdare Road, Merthyr Tydfil - Proposed Traffic Regulation OrderThis decision
  2. Aberdare Road, Merthyr Tydfil – Proposed Traffic Regulation OrderApproved
  3. P/13/0360 - Keir Hardie Health Park, Aberdare Road, Georgetown, Merthyr TydfilApproved
  4. Petition Requesting Further Parking Prohibitions, Aberdare Road, Merthyr TydfilDecided
  5. Petition - Aberdare Road Yellow LiningNoted
  6. Aberdare Road Area - Proposed Prohibition of Waiting Traffic Regulation OrderDecided

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open