P/25/0199 - Furnace Row/Ash Road, Troedyrhiw, Merthyr Tydfil, CF48 4TR

Approved Planning 1 paper

AI summaryMerthyr Tydfil County Borough Council approved a permanent 1.5m fence along the Taff Trail at Furnace Row, subject to the planning conditions in the report. [D] [P30] [P31] [P46]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIt replaces temporary safety fencing and provides fall protection. [P28] [P31]
MoneyNot stated
What happens nextBiodiversity scheme required before installation [P52]Council must approve the scheme and implementation timescale in writing. [P52]
Who it affectsNot stated

What was decided

The council approved the application for a permanent fence along the Taff Trail, subject to the conditions in the report. [D] [P26] [P31] [P46] Report P26, P31, P46

Development must begin no later than five years from the decision and must be carried out in accordance with the approved plans and documents. [P47] [P49] [P50] [P51] Report P47, P49, P50, P51

Before installation, a biodiversity enhancement scheme and implementation timescale must be submitted for the council's written agreement. The scheme must then be implemented and retained in perpetuity, and reflective strips must be fitted to the corner posts at either end of the railing. [P52] [P53] [P54] [P55] Report P52, P53, P54, P55

Why

The proposal is acceptable in principle because it forms part of the Taff Trail, an existing tourism, recreation and leisure asset, and replaces temporary fencing required for safety. [P28] Report P28

The 1.5m open metal hooped design with a muted green finish reduces overbearing effects, suits the local context and maintains residents' interaction with trail users. [P30] [P32] [P34] Report P30, P32, P34

The Head of Engineering and Highways, Estates, the Council Ecologist, Rights of Way and South Wales Fire & Rescue Service raised no objection. [P1] [P2] [P3] [P4] [P5] Highways raised no safety concerns, the heritage effect was not considered adverse in any meaningful way, and the ecologist raised no issue in principle with the bird and bat boxes. The gates are considered suitable for pedestrian access. [P36] [P38] [P39] [P42] Report P1, P2, P3, P4, P5, P36, P38, P39, P42

What happens next

Submit a biodiversity enhancement scheme, including an implementation timescale, for written council agreement before installing the railing. Implement the agreed scheme and retain the enhancements in perpetuity. [P52] Report P52

Begin development no later than five years from the decision and carry it out in accordance with the approved plans. [P47] [P49] [P50] Report P47, P49, P50

Install reflective strips on the corner posts at either end of the railing. [P54] Report P54

Options considered

  • Chosen: Permanent 1.5m fence with an open metal hooped design and muted green finish. It replaces temporary safety fencing and was found acceptable in location, character and appearance, residential amenity, highway safety and ecology. [D] [P28] [P30] [P45] Report P28, P30, P45
  • Rejected: Alternative fence types or heights suggested by residents. The application must be determined on the acceptability of the scheme proposed. [P42] Report P42
  • Rejected: Restoration of the wall and embankment. The application must be determined on the submitted detail rather than alternative solutions. [P42] Report P42

Implications

  • Legal: The approval is conditional on development beginning no later than five years from the decision, compliance with approved plans, a biodiversity agreement before installation and reflective strips at either end. [P47] [P49] [P52] [P54] Report P47, P49, P52, P54
  • Risk: The fence is intended to provide fall protection. A supporting submission says it will also deter anti-social behaviour. [P31] [P12] Report P31, P12
  • Risk: The highways officer raised no safety concerns, and the gates were considered suitable for pedestrian access. [P36] [P42] Report P36, P42
  • Other: The fence will reinforce the boundary between public and private space. [P31] Report P31
  • Equalities: The consultation received 10 letters of objection and one supporting letter. Concerns covered enclosure, height, views, interaction, visibility, access, heritage, wellbeing and ecological feature placement. The report did not consider the residential amenity impact unacceptable, and did not treat property values or private views as material planning considerations. [P8] [P10] [P34] [P42] Report P8, P10, P34, P42
  • Other: The proposal was not considered to adversely affect historic character in any meaningful way or harm the conservation of historic assets. [P38] Report P38
  • Other: Pole mounted bird and bat boxes are proposed to deliver net biodiversity benefits. Further details, location and maintenance must be agreed through a condition. [P39] [P52] Report P39, P52
  • Other: The proposal is intended to support and enhance the Taff Trail as a sustainable transport route, part of the National Cycle Network and a bridleway. [P31] [P36] Report P31, P36

Who and where

  • Taff Trail users Report P31
  • Nearby residents and neighbouring occupiers Report P8, P34
  • National Cycle Network users Report P31
  • Bridleway users Report P31

Timeline

  • 22nd July 2025: Letters were sent to neighbouring properties. [P7] Report P7
  • 23rd July 2025: Site notices were displayed in the vicinity of the site. [P7] Report P7
  • 1st October 2025: Reconsultation letters were sent after the proposed fence height was reduced to 1.5m. A further 4 objections were received after the October 2025 reconsultation. [P8] Report P8
  • 11th March 2026: Reconsultation letters were sent and site notices were displayed after the fence type was revised. An additional 4 objections were received after the March 2026 reconsultation. [P8] Report P8
  • No later than five years after the decision: Development must begin. [P47] Report P47
  • 2026-06-03: The application was approved subject to the conditions in the report. [D]

Plain English for the jargon

  • LDP: The council's Replacement Local Development Plan, containing the settlement, design, transport, historic environment and ecology policies used in the assessment. [P21] [P22]
  • PPW: Planning Policy Wales Edition 12, February 2024, which sets land use policies for the Welsh Government. [P17]
  • TAN: Technical Advice Note. TAN 12 advises on design in the built and natural environment. [P18] [P19]
  • Taff Trail: An existing tourism, recreation and leisure asset, and part of the National Cycle Network and a bridleway. [P28] [P31]
  • Hooped top: A fence form intended to give a domestic appearance and blend with nearby homes. [P30]
  • Net Biodiversity Benefits: Biodiversity gains proposed through pole mounted bird and bat boxes. [P39]
  • WBFG Act: The 2015 future generations Act, under which the sustainable development principle was considered. [P44]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item72

Resolved

Resolved that: The application be approved subject to the conditions outlined in the report.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Planning, Regulatory and Licensing, 9 pages

DATE WRITTEN 22nd May 2026 REPORT AUTHOR Judith Jones CASE OFFICER Gareth Davies COMMITTEE Planning and Regulatory COMMITTEE DATE 3rd June 2026

Application No. Date Determining Authority P/25/0199 18th July 2025 MTCBC

Proposed Development Location Name & Address of Applicant/Agent

Erection of permanent fencing Furnace Row/Ash Road Dwr Cymru Welsh Water Troedyrhiw c/o [name removed] Tydfil Asbri Planning Ltd. CF48 4TR Unit 9 Oak Tree Court Cardiff Gate Business Park PURPOSE OF REPORT To further consider planning application P/25/0199

At the Planning, Regulatory and Licencing Committee meeting held on 22nd April 2026, Members raised the following concerns with the proposed development:

• The height of the railing and its potential impact on the adjacent properties. • The presence of gates incorporated into the railing could have highway safety implications and impede the access for residents stepping directly on to the road. • The green colour of the railing is inappropriate.

In response to these concerns it was noted during the meeting by the Agent, representing the applicant, that further changes to the proposal could be reviewed to assist in addressing the concerns raised. As such, Members deferred the determination of the application to further consider revisions to the proposal.

Amended plans have now been submitted with the following amendments to the proposed railing:

• The railing has been reduced in height from 1.5m to 1.2m. • The gated accesses have been removed. • The colour of the railing would be black. • The railing now includes a small return at both ends around the gabion structure.

A further consultation exercise has been undertaken with the Head of Engineering and Highways on the revised plans. No objection has been raised, subject to reflective strips being fitted to the end posts of the railing to make the structure clearly identifiable at night.

It is considered that the proposed amendments to the overall design of the railing is acceptable. It would not have an adverse impact on the character of the area, it would not give rise to an unacceptable impact on residential amenity, nor does it result in a highway safety concern.

Accordingly, it is recommended that the application be granted planning permission subject to the following revised conditions that reflect the changes made to the proposal:

1. The development shall begin not later than five years from the date of this decision. Reason - To comply with Section 91 of the Town and Country Planning Act 1990. 2. The development shall be carried out in accordance with the following approved plans and documents:

General arrangement drawing no. B50730-121316-13-BG-DR-CA-CI1001 Rev C5.0. Fencing detail 03 drawing no. B50730-121316-13-BG-DR-CA-CI1052 Rev C3.0. Fencing detail 02 drawing no. B50730-121316-13-BG-DR-CA-CI1052 Rev C3.0. Fencing detail 01 drawing no. B50730-121316-13-BG-DR-CA-Cl1050 Rev C3.0.

Reason -To ensure compliance with the approved plans and clearly define the scope of the permission.

3. Prior to the installation of the approved railing, a scheme for biodiversity enhancements, including a timescale for implementation, shall be submitted to and agreed in writing by the local planning authority. Development shall be carried out in accordance with the approved details and retained in perpetuity thereafter.

Reason - Future Wales and Planning Policy Wales (Edition 12 February 2024) requires all development to maintain and enhance biodiversity, and to accord with Policy EnW1 of the Merthyr Tydfil County Borough Council Replacement Local Development Plan.

4. The installation of the railing shall incorporate reflective strips fitted on the corner posts at either end of the railing.

Reason - In the interests of highway safety and to comply with the requirements Policy SW11 of the Merthyr Tydfil County Borough Council Replacement Local Development Plan.

COMMITTEE’S DECISION IS REQUIRED.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/25/0199: Furnace Row/Ash Road, Troedyrhiw, Merthyr Tydfil, CF48 4TRReport 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. P/25/0199 - Furnace Row/Ash Road, Troedyrhiw, Merthyr Tydfil, CF48 4TRThis decision
  2. P/25/0199 - Furnace Row / Ash Road, Troedyrhiw, Merthyr Tydfil, CF48 4TRDeferred

More from Merthyr Tydfil Planning, Regulatory and Licensing

All decisions
MeetingDecisionOutcome
2 Sep 2026 Minutes of meeting Friday, 1 May 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 17 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Tuesday, 30 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. Approved Open
2 Sep 2026 Minutes of meeting Wednesday, 8 July 2026 of Planning, Regulatory and LicensingResolved that: The minutes be approved as an accurate record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies