Full Council, Wednesday 15 July 2026 at 5.30pm

Cyfarthfa Castle Redevelopment

Approved Committee 2 papers

AI summaryMerthyr Tydfil Full Council approved the recommendations in the Cyfarthfa Castle Redevelopment report, moving forward future project phases with council match-funding and external funding bids.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull Council approved the report's recommendations
MoneyNo figure stated in papersAllocation sits within Capital Programme 2026/27 to 2029/30
What happens nextFuture phases of the projectCouncil will pursue external funding and fundraising
Who it affectsCyfarthfa Castle and heritage areaNationally significant heritage asset in Merthyr Tydfil

What was decided

Full Council approved the recommendations contained within the officer report on the Cyfarthfa Castle Redevelopment.

The Council accepted it will need to contribute funding towards future phases of the project, with a match-funding allocation already included in the approved Capital Programme. Report 7.1

The Council noted that the planned works will have both capital and revenue financial implications that must remain affordable within the Medium-Term Financial Plan. Report 7.2

Why

The report sets out safeguarding a nationally significant heritage asset, supporting economic regeneration and tourism, and creating opportunities for learning, culture and community engagement. Report P11, P12, P15

It also cites preventing deterioration through conservation, roof protection and drainage works, and supporting future job creation and investment. Report P13, P14

The Integrated Impact Assessment found no significant negative impacts, though future phases will need ongoing consideration of funding, accessibility, traffic, operational and construction impacts. Report P16, P17

What happens next

The Council will continue to explore and pursue alternative external funding sources, including successor streams to the UK Shared Prosperity Fund and other grant programmes. Report 7.3

Fundraising activity will be undertaken to support delivery of future phases, with progress monitored through the Council's established governance and project management arrangements. Report 7.4

Ongoing revenue costs of borrowing, Minimum Revenue Provision, asset maintenance and operational costs must be met within the Medium-Term Financial Plan. Report 7.2

The money

  • Capital Programme 2026/27 to 2029/30 Approved allocation to meet the Council's anticipated match-funding requirements for the Cyfarthfa Heritage Area project Report 7.1

Implications

  • Financial: Future phases will have both capital and revenue implications, including borrowing costs, Minimum Revenue Provision, asset maintenance and operational costs that must remain affordable and sustainable within the Medium-Term Financial Plan. Report 7.2
  • Risk: Funding risk will be monitored through the Council's established governance and project management arrangements, including progress against fundraising targets. Report 7.4
  • Equalities: The Integrated Impact Assessment recorded 6 of 9 negative impacts under Protected Characteristics, and 2 of 6 reduced impacts under Decarbonisation; no significant negative impacts were overall identified. Report P8, P10, P16
  • Other: Future redevelopment phases will require ongoing consideration of accessibility, traffic, operational and construction impacts. Report P17

Who and where

  • Cyfarthfa Castle, a nationally significant heritage asset Report P11
  • Visitors, tourists and the local economy in Merthyr Tydfil Report P11, P12
  • Residents and community groups engaging with learning and culture activities Report P12

Timeline

  • 14th January 2026: Capital Programme 2026/27 to 2029/30, including match-funding allocation for the Cyfarthfa Heritage Area project, approved by Full Council Report 7.1
  • 2026-07-15: Full Council considered and approved the recommendations in the Cyfarthfa Castle Redevelopment report

Plain English for the jargon

  • UKSPF: UK Shared Prosperity Fund, a previous external funding source secured for the project
  • MRP: Minimum Revenue Provision, the council's statutory charge for repaying debt on capital assets
  • Medium-Term Financial Plan: The Council's multi-year financial planning document covering revenue and capital affordability
  • Cyfarthfa Heritage Area: The wider project name referenced for match-funding purposes within the Capital Programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Resolved that; The recommendations as contained within the report be approved.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 10 pages

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

FULL COUNCIL REPORT Date Written 24th June 2026 Report Author Laura Willcox / Zoe Thomas Service Area Regeneration, Housing and Investment Exempt/Non-Exempt Non-Exempt Committee Date 15th July 2026

Cyfarthfa Castle Redevelopment 1.0 SUMMARY OF THE REPORT

1.1This report provides Council with an update on the progress made in relation to the conservation and redevelopment of Cyfarthfa Castle, a key project within The Cyfarthfa Plan.

1.2The report outlines the work undertaken to date, including the completion of condition surveys, emergency conservation works and the progression of key work programmes and the immediate next steps.

1.3The report requests Council notes the progress made to date and the next steps required to deliver the long-term vision for Cyfarthfa Castle as a heritage, cultural and visitor destination of national significance.

2.0RECOMMENDATION that:

2.1The continuation of the phased approach, including the re-submisison of the National Lottery Heritage Fund application when ready, be approved.

3.0INTRODUCTION AND BACKGROUND

3.1Merthyr Tydfil County Borough Council (MTCBC), working in partnership with The Cyfarthfa Foundation (TCF), continues to progress the long-term restoration and redevelopment of Cyfarthfa Castle and its wider estate in line with the vision set out within The Cyfarthfa Plan.

3.2In January 2025, a report to Full Council proposed the new approach progressing with a phased approach to the re-development of the Castle. The recommendation was approved, and this report will outline the progress made in relation to the phased approach with the ‘former house’ side where the Museum operates from as the priority phase.

3.3Prior to the Council report in January 2025, in November 2023, Council had approved the recommendation to proceed with the next stage design work and associated investigations in line with the Option 1 proposal (full coverage to the entire structure within a purpose-built temporary roof using scaffolding).

3.4Within the January 2025 report it was identified that due to the many constraints identified in relation to the re-development of the building, discussions had commenced regarding an alternative approach. Where the tenting solution would enable the building to dry out it also became a very costly solution and would result in no physical works being undertaken on the building for a number of years.

3.5To enable the tenting proposal to progress, funding would need to be secured and once delivered, a further fundraising programme would need to be undertaken in order for the works phase to commence. This would have resulted in the scaffold remaining erected for potentially three to five years.

3.6As the building was continuing to deteriorate and would deteriorate further if the tent was due to cover the building for a three to five year period, it was identified that a phased approach would be a more appropriate solution and would result in physical works to preserve the fabric of the building, would ensure that part of the building becomes watertight and would create outputs for the community.

3.7There would still be a requirement to erect scaffolding around the ‘former house’ side but this would be at a much lesser scale than tenting the entire building as per the original proposal and would be for a reduced period of time as works would be undertaken and scaffold removed accordingly.

3.8Discussions were held with TCF, CADW and Welsh Government regarding the phased approach and this was welcomed by all organisations.

4.0PROGRESS TO DATE

4.1Following the Council Report in January 2025, significant progress has now been made in advancing the approved proposed phased works. Shortly after securing approval from Council, discussions were held with CADW regarding funding for ‘transformational conservation works’ to the Grade I Listed building.

4.2Work was undertaken to develop three key areas of work:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cyfarthfa Castle RedevelopmentReport 10 pages DownloadRead as text
PDF
iiaReport 18 pages Download

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Cyfarthfa Castle RedevelopmentThis decision
  2. Cyfarthfa Castle and Art Gallery AccreditationApproved
  3. Cyfarthfa Castle RedevelopmentApproved
  4. Cyfarthfa Castle Roof Repairs Contract AwardDecided
  5. Cyfarthfa Castle: Heritage Lottery Fund Stage One ApprovalDecided
  6. Cyfarthfa Castle Phase 1 Redevelopment - Design Team AppointmentDecided

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open