Resolved
Resolved that; The recommendations as contained within the report be approved.
AI summaryMerthyr Tydfil Full Council approved the recommendations in the Cyfarthfa Castle Redevelopment report, moving forward future project phases with council match-funding and external funding bids.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved that; The recommendations as contained within the report be approved.
Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk
FULL COUNCIL REPORT Date Written 24th June 2026 Report Author Laura Willcox / Zoe Thomas Service Area Regeneration, Housing and Investment Exempt/Non-Exempt Non-Exempt Committee Date 15th July 2026
Cyfarthfa Castle Redevelopment 1.0 SUMMARY OF THE REPORT
1.1This report provides Council with an update on the progress made in relation to the conservation and redevelopment of Cyfarthfa Castle, a key project within The Cyfarthfa Plan.
1.2The report outlines the work undertaken to date, including the completion of condition surveys, emergency conservation works and the progression of key work programmes and the immediate next steps.
1.3The report requests Council notes the progress made to date and the next steps required to deliver the long-term vision for Cyfarthfa Castle as a heritage, cultural and visitor destination of national significance.
2.0RECOMMENDATION that:
2.1The continuation of the phased approach, including the re-submisison of the National Lottery Heritage Fund application when ready, be approved.
3.0INTRODUCTION AND BACKGROUND
3.1Merthyr Tydfil County Borough Council (MTCBC), working in partnership with The Cyfarthfa Foundation (TCF), continues to progress the long-term restoration and redevelopment of Cyfarthfa Castle and its wider estate in line with the vision set out within The Cyfarthfa Plan.
3.2In January 2025, a report to Full Council proposed the new approach progressing with a phased approach to the re-development of the Castle. The recommendation was approved, and this report will outline the progress made in relation to the phased approach with the ‘former house’ side where the Museum operates from as the priority phase.
3.3Prior to the Council report in January 2025, in November 2023, Council had approved the recommendation to proceed with the next stage design work and associated investigations in line with the Option 1 proposal (full coverage to the entire structure within a purpose-built temporary roof using scaffolding).
3.4Within the January 2025 report it was identified that due to the many constraints identified in relation to the re-development of the building, discussions had commenced regarding an alternative approach. Where the tenting solution would enable the building to dry out it also became a very costly solution and would result in no physical works being undertaken on the building for a number of years.
3.5To enable the tenting proposal to progress, funding would need to be secured and once delivered, a further fundraising programme would need to be undertaken in order for the works phase to commence. This would have resulted in the scaffold remaining erected for potentially three to five years.
3.6As the building was continuing to deteriorate and would deteriorate further if the tent was due to cover the building for a three to five year period, it was identified that a phased approach would be a more appropriate solution and would result in physical works to preserve the fabric of the building, would ensure that part of the building becomes watertight and would create outputs for the community.
3.7There would still be a requirement to erect scaffolding around the ‘former house’ side but this would be at a much lesser scale than tenting the entire building as per the original proposal and would be for a reduced period of time as works would be undertaken and scaffold removed accordingly.
3.8Discussions were held with TCF, CADW and Welsh Government regarding the phased approach and this was welcomed by all organisations.
4.0PROGRESS TO DATE
4.1Following the Council Report in January 2025, significant progress has now been made in advancing the approved proposed phased works. Shortly after securing approval from Council, discussions were held with CADW regarding funding for ‘transformational conservation works’ to the Grade I Listed building.
4.2Work was undertaken to develop three key areas of work:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cyfarthfa Castle RedevelopmentReport | 10 pages | DownloadRead as text |
PDF |
iiaReport | 18 pages | Download |
Follow Full Council at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved | Approved | Open |
| 22 Oct 2026 | MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved | Approved | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. | Approved | Open |
| 22 Oct 2026 | Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved | Approved | Open |
| 30 Sep 2026 | Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.