Merthyr Tydfil County Borough Council
Cabinet, Wednesday 25 November 2026 at 4.00pm

Nant Yr Odyn Coal Tip - Reclamation and Stabilisation

Approved Executive 3 papers

AI summaryMerthyr Tydfil County Borough Council Cabinet approved reprofiling and stabilisation of Nant Yr Odyn Coal Tip, including selective spoil removal, drainage work and ecological improvements, at an estimated construction cost of approximately £4-5 million [D, 1.3, 4.4].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOption four includes selective spoil removal [4.4].
Moneyapproximately £4-5 million [4.4]Estimated construction cost [4.4].
What happens nextDelivery target: next 3 years [5.2]Seven immediate steps were approved [P26].
Who it affectsPentrebach and nearby areas [3.2]Groundwater, flooding, stability and ecology are in scope [3.6, 4.4].

What was decided

Option four, reprofiling and stabilisation with selective removal of spoil, was approved [D, 4.4]. Report 4.4

The scheme removes approximately 100,000 to 140,000 m³ from critical upper and mid slope areas, regrades slopes, upgrades drainage and undertakes ecological and landscape enhancements [4.4]. Report 4.4

The immediate next steps in section 5.2 were approved [D, 2.2, 5.2]. Report 2.2, 5.2

Why

The tip's classification, extreme weather, drainage issues and flooding led to a need for proactive, long term risk management [3.2]. Report 3.2

Ground investigation and assessment of six options identified option four as the best balance of safety, flood and stability risk reduction, environmental protection, cost and deliverability [1.2, 4.4]. Report 1.2, 4.4

Doing nothing and limited intervention would not adequately address long term stability and flood risk, while complete removal is less favourable because of cost, environmental impact, planning complexity and programme duration [4.3]. Report 4.3

What happens next

Progress preliminary engineering design, complete drainage and flood risk assessments, and undertake EIA screening and ecological surveys [P26]. Report P26

Start early engagement with Natural Resources Wales, landowners, statutory undertakers and local communities, and select and secure a receptor site [P26]. Report P26

Develop a planning, permitting and stakeholder engagement strategy, plus a phased delivery programme with long term monitoring [P26]. Report P26

The money

  • approximately £4-5 million Estimated construction cost for reprofiling and stabilisation Report 4.4

Options considered

  • Chosen: Option four: Reprofiling and stabilisation with selective removal of spoil. It provides the best balance of public safety, flood and stability risk reduction, environmental protection, cost and deliverability [4.4]. Report 4.4
  • Rejected: Option six: Complete removal and relocation to a receptor site. Complete removal gives the highest risk reduction but is less favourable because of significant cost, environmental impact, planning complexity and programme duration [4.3]. Report 4.3
  • Rejected: Option one: Do nothing. It would not adequately address long term geotechnical stability and flood risk [4.3]. Report 4.3
  • Rejected: Option two: Maintain the tip with enhanced drainage and monitoring. Limited intervention would not adequately address long term geotechnical stability and flood risk [4.3]. Report 4.3
  • Rejected: Option three: Install directionally drilled under drains. Limited intervention would not adequately address long term geotechnical stability and flood risk [4.3]. Report 4.3
  • Rejected: Option five: Temporary removal and engineered replacement of spoil Report P18

Implications

  • Financial: Funding has been secured for three years to support scheme development, construction and stabilisation works [5.3]. Report 5.3
  • Risk: The tip's classification, extreme weather, drainage issues and flooding led to a need for proactive, long term risk management [3.2]. Report 3.2
  • Risk: The scheme seeks to reduce ground, drainage and flood risks and safeguard the local community [4.4, 5.3]. Report 4.4, 5.3
  • Risk: Some spoil is combustible, so precautions are required during earthworks, and some water samples contained elevated metals, hydrocarbons and polyaromatic hydrocarbons [3.6]. Report 3.6
  • Legal: Planning, ecological and regulatory challenges remain, and further planning and permitting work is required [4.7, 5.2, P26]. Report 4.7, 5.2, P26
  • Climate: The assessment records one positive decarbonisation impact and five neutral or not applicable impacts, and says biodiversity will be enhanced [P33, P37]. Report P33, P37
  • Equalities: Protected characteristics and socio economic disadvantage are recorded as neutral or not applicable, and the assessment identifies no negative impacts [P30, P32, P38]. Report P30, P32, P38
  • Other: The tip is a Site of Importance for Nature Conservation with habitats that may support protected species, and public notices are to incorporate Welsh language [3.6, P35]. Report 3.6, P35

Who and where

  • Pentrebach and nearby communities Report 3.2, 4.7, P26
  • Residential and public areas near the tip Report 3.2
  • Habitats and protected species at the Site of Importance for Nature Conservation Report 3.6
  • Natural Resources Wales Report P26
  • Mining Remediation Authority Report 3.4
  • Landowners Report P26
  • Statutory undertakers Report P26
  • Welsh Government Report 5.3

Timeline

  • 2020: Flooding in Pentrebach occurred during Storm Dennis [3.2]. Report 3.2
  • 2024: Further flooding in Pentrebach occurred during Storm Bert [3.2]. Report 3.2
  • January 2025: Engagement with the Mining Remediation Authority identified evidence that the tip formed over three natural watercourses [3.3]. Report 3.3
  • April 2026: The ground investigation concluded and produced geological, hydrogeological and geotechnical models [3.6]. Report 3.6
  • July 2026: The WSP feasibility study concluded [4.2]. Report 4.2
  • 7th September 2026: The Cabinet report was written [P2]. Report P2
  • 25th November 2026: Cabinet approved the preferred option and its immediate next steps [D, P2]. Report P2
  • within the next 3 years: Delivery of the approved option is the stated target [5.2]. Report 5.2

Plain English for the jargon

  • Reprofiling: Regrading slopes to improve stability [4.4].
  • Selective removal: Removing material from critical upper and mid slope areas [4.4].
  • Stabilisation: Engineered works to improve slope stability and reduce failure risk [4.4, 5.3].
  • Receptor site: A location where removed spoil can be relocated [4.4, P21].
  • Site of Importance for Nature Conservation: A designated site with habitats that may support protected species [3.6].
  • Environmental Impact Assessment: A screening process used with ecological surveys for the approved scheme [P26].
  • Groundwater: Water within and around the tip, where drainage conditions are complex [3.2, 3.3].
  • Geotechnical: Relating to ground and slope stability work at the tip [3.6, 4.4].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item62

Resolved

Resolved that; 2.1 The option to re-profile and stabilise the Nant Yr Odyn Tip proceeds in accordance with recommendations contained in the WSP Reclamation and Stabilisation Options Report, be approved. 2.2 The next steps as highlighted in Section 5.2, be approved.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet

Civic Centre, Castle Street, Merthyr Tydfil CF47 8AN Main Tel: 01685 725000 www.merthyr.gov.uk

CABINET REPORT Date Written 7th September 2026** Report Author Carwyn Morris Service Area Engineering Committee Division Portfolio Exempt/Non Exempt Non Exempt Committee Date 25th November 2026

Nant Yr Odyn Coal Tip – Reclamation and Stabilisation

1.0SUMMARY OF THE REPORT 1.1 The Nant Yr Odyn Tip, formerly known as North Dyffryn Incline Tip No. 498, is a historic coal spoil tip located above Pentrebach, south of Merthyr Tydfil. The Tip is classified as a High Risk Category D coal tip and contains approximately 1 million m³ (1.85 million tonnes) of colliery spoil. Recent extreme weather events, ongoing groundwater drainage issues, and flooding incidents have highlighted the need for a long-term management strategy to reduce geotechnical, environmental, and community risks.

1.2The report outlines the work undertaken to date including the completion of an extensive ground investigation, monitoring and a feasibility options report where 6 options were assessed against safety, environmental, social and economic criteria.

1.3The report seeks Cabinet approval to proceed with the preferred option of Re- profiling and Stabilisation of the Tip to deliver a robust and sustainable solution by addressing both geotechnical and environmental risks to ensure long-term safety.

2.0RECOMMENDATIONS that

2.1The option to re-profile and stabilise the Nant Yr Odyn Tip proceeds in accordance with recommendations contained in the WSP Reclamation and Stabilisation Options Report, be approved.

2.2The next steps as highlighted in Section 5.2, be approved. 3.0 INTRODUCTION AND BACKGROUND 3.1 The Nant Yr Odyn Tip, formerly known as North Dyffryn Incline Tip No. 498, is a historic coal spoil tip located above Pentrebach, south of Merthyr Tydfil. The Tip is classified as a High Risk Category D coal tip and contains approximately 1 million m³ (1.85 million tonnes) of colliery spoil and slag deposited during historic coal mining operations at the Bwllfa level. Formation of the Tip is understood to have commenced in 1915 and continued until its completion in 1940. The tip has remained largely unchanged since that time.

3.2However, recent flooding incidents in Pentrebach particularly during Storm Dennis in 2020 and Storm Bert in 2024 has resulted in a significant amount of groundwater issuing from beneath the Tip. The recent extreme weather events, drainage issues, and flooding incidents combined with its classification and proximity to residential and public areas highlighted the need for proactive intervention with a long-term management strategy to reduce geotechnical, environmental, and community risks.

3.3Following engagement with the Mining Remediation Authority (formerly the Coal Authority) in January 2025, historical evidence was identified which indicates that the Tip was formed over three natural watercourses. In addition, due to the extensive mining activity in the area and changing weather patterns with increased rainfall events this has created complex drainage conditions both within and around the Tip.

3.4After the identification of this historic evidence, an immediate decision was taken to increase the frequency of inspections at Nant yr Odyn. These enhanced inspections remain ongoing and are being undertaken jointly by the Mining Remediation Authority and geotechnical engineers from consultant WSP. In parallel, Merthyr Tydfil County Borough Council (MTCBC) progressed considerable flood alleviation works in the vicinity of the Tip. The installation of an advanced monitoring system is also operating 24 hours per day and will alert of any movement within the Tip.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 13 MB Download
PDF
Nant Yr Odyn Coal Tip: Reclamation and StabilisationReport 304 KB DownloadRead as text
PDF
iiaReport 751 KB Download

At this meeting

Whole meeting

Who was there

0 of 7 attended
BC
Councillor Brent CarterChair, expected
DJ
Councillor David JonesVice-Chair, expected
GL
Councillor Gareth LewisCommittee Member, expected
LM
Councillor Louise Minett-VokesCommittee Member, expected
JS
Councillor Jamie ScrivenCommittee Member, expected
AW
Councillor Anna Williams- PriceCommittee Member, expected
SJ
Simon JonesOfficer, expected

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
25 Nov 2026 Minutes of meeting Thursday, 22 October 2026 of CabinetResolved that; The minutes be approved as an accurate record Approved Open
25 Nov 2026 Community Infrastructure Levy (CIL) - Funding ApplicationsResolved that; 2.1 The recommendations of the MTCBC CIL Steering Group, to award funding to the three applications li... Approved Open
25 Nov 2026 Revenue Budget 2027/28 OutlookResolved that; 2.1 An update on the Council’s budget position for the 2027/28 financial year in advance of future con... Noted Open
25 Nov 2026 Switch TogetherResolved that; 2.1 The participation in the 2027 collective purchasing scheme be approved, subject to completion and ... Approved Open
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies