Resolved
That the Minutes of the meeting held on 12 March 2015 be agreed as a correct record.
General Purposes Committee agreed this item on Thursday 25 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the meeting held on 12 March 2015 be agreed as a correct record.
Agenda Item 3 All minutes are draft until agreed at the next meeting of the committee/panel. To find out the date of the next meeting please check the calendar of events at your local library or online at www.merton.gov.uk/committee.
GENERAL PURPOSES COMMITTEE 12 MARCH 2015 (19.15 - 20.44) PRESENT Councillors Councillor Peter McCabe (in the Chair), Councillor Janice Howard, Councillor Adam Bush, Councillor Tobin Byers, Councillor Stephen Crowe, Councillor Mary Curtin, Councillor Abigail Jones, Councillor Ian Munn and Councillor David Williams
ALSO PRESENT Margaret Culleton (Head of Internal Audit & Investigations), Paul Dale (Assistant Director of Resources), David Keppler (Head of Revenues and Benefits), Paul King (External Auditor, Ernst and Young), Dean Shoesmith (Joint Head of Human Resources) and Chris Pedlow (Senior Democratic Services Officer)
1 DECLARATIONS OF INTEREST (Agenda Item 1)
No declarations of interests were received.
2 APOLOGIES FOR ABSENCE (Agenda Item 2)
An apology was received by Councillor Laxmi Attawar, with Councillor Stan Anderson standing in for her at the meeting.
3 MINUTES OF THE PREVIOUS MEETING (Agenda Item 3)
The Minutes of the Meeting of the General Purpose Committee held on the 6 November 2015 were approved as a correct record.
It was noted that Councillors Daniel Holden and Stan Anderson were present and should have been recorded as such at the meeting on the 6 November 2014 as they were standing in for the absent Councillors Stephen Crowe and Mary Curtin respectively.
4 EXTERNAL AUDITOR: CERTIFICATION OF CLAIMS AND RETURNS ANNUAL REPORT 2013-14 (Agenda Item 4)
The Council’s External Auditor, Paul King, presented the certification of claims and returns annual report. It was noted that the report only covers one claim that was required to be certified, which was on a housing benefit and council tax subsidy claim for £92,250,409 to the Department of Work and Pensions. Members were informed that fourteen extended tests occurred following the initial tests on the claim. From
Page1 1 those further tests, four main areas of identified errors and uncertainties were included within the qualification letter and were highlighted on page 11 of the report.
In response to a Member question, in relation to the summary of recommendations contained within section 4, and whether the council was on track to meet the 31 March 2015 deadline for three of the recommendations, it was confirmed that we were on track to meet them, but it was an ongoing process.
RESOLVED
Members noted the report.
5 EXTERNAL AUDITOR: AUDIT PROGRESS REPORT (Agenda Item 5)
The Council’s External Auditor, Paul King, introduced the Audit Progress report, which provided a position statement of the audit work carried out by Ernst and Young during 2014-15. Members were informed that, within paragraph 1.6, it details proposed ways for the audit process which, it is hoped, would be smoother and more efficient in future years.
It was noted that from 2017-18 the Council would be required to close and produce its accounts a month earlier than the current deadline. Also those accounts would be required to be audited by the external auditor and their subsequent audit report issued by the end of July, two months earlier than currently process.
RESOLVED
Members noted the report.
6 EXTERNAL AUDITOR: AUDIT PLANNING REPORT FOR THE COUNCIL (Agenda Item 6)
The Council’s External Auditor, Paul King, presented the Audit Planning report of the Council, which detailed the audits carried out by Ernst and Young during the year ending March 2015. Section 3 was highlighted to Members as it detailed the three areas of significant risks and the audit approach to them.
It was noted that the audit of the Council pensions scheme would be done separately and was not included in the report, but would be put to the committee in due course.
RESOLVED
Members noted the report
Page 2 2 7 INTERNAL AUDIT: PLAN, STRATEGY AND CHARTER 2015/16 (Agenda Item 7)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meetingMinutes | 47 KB | DownloadRead as text |
Follow General Purposes Committee at Merton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2016 | Certification of Claims and Returns Annual Report 2014-15RESOLVED Members noted the report | Noted | Open |
| 10 Mar 2016 | External Audit: Audit PlanRESOLVED Members noted the report | Noted | Open |
| 10 Mar 2016 | External Audit:Audit BriefingRESOLVED The Committee noted the Briefing Document | Noted | Open |
| 10 Mar 2016 | Internal Audit: Progress ReportRESOLVED That the General Purposes Committee: A. noted the Internal Audit Progress Report and comment upon matters ar... | Noted | Open |
| 10 Mar 2016 | Internal Audit: Plan,Strategy and CertificateRESOLVED The General Purposes Committee reviewed the 2016/17 Draft Internal Audit Strategy, Plan and Charter. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.