CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Merton
General Purposes Committee, Wednesday 16 September 2015 at 7.15pm

Vehicle Maintenance Follow-up Audit Review

Decided Committee 1 paper

General Purposes Committee decided this item on Wednesday 16 September 2015. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED That the General Purposes Committee notes the progress made in response to the recommendations on the Vehicle Maintenance report
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to General Purposes Committee

Recommendation

1. To note progress made in response to the recommendations on the Vehicle Maintenance report

1. Purpose of report and executive summary

1.1This report sets out the results of Internal Audit’s follow up review of Vehicle Maintenance. 1.2 The purpose of this review was to follow up progress made by management in implementing previous audit recommendations made in the audit originally carried out in September 2014.

2. Details

2.1An Internal Audit review was carried out in September 2014, with a final audit report issued in February 2015 which concluded a limited assurance. There were 30 recommendations of which 12 were high, 16 medium and 2 low priority.

2.2The main concerns highlighted were:-

 Non -Compliance with CSO  Contractor using workshop area for maintenance of own private vehicle.  Security of workshop and lack of stock control

Page 267  Declaration of interest forms not completed  Paper and electronic records incomplete or did not contain necessary information to identify the vehicle worked on, with little or no audit trail  Testing found that some services were not carried out until up to six weeks after the scheduled service date and brake testing not always evident.  The same faults were found to have been repaired by one particular contractor multiple times in a very short time period. In each case, the contractor recharged the Authority for the work.  Disposal of Vehicles Procedure not followed

2.3The Management Summary and summary of agreed actions were reported to General Purposes Committee on the 12th March 2015 at this time there were 26 of the 30 audit actions outstanding as the final report had only previously been issued in February 2015. The committee sought assurance that progress had commenced on the audit actions.

3. Follow up review

3.1The purpose of this follow up is to provide assurance to members that that all recommendations previously made have been adequately implemented.

3.2The officers responsible for the implementation of recommendations were interviewed to determine the status of agreed actions. Where appropriate, audit testing has been completed to assess the level of compliance and the controls in place.

3.3In the opinion of Internal Audit, management has demonstrated satisfactory progress in implementing actions to address Internal Audit recommendations. The audit opinion has therefore been upgraded to Satisfactory Assurance.

3.4In summary, of the recommendations contained in the original audit report:

• 23 have been fully implemented • 7 are in progress (2 high and 5 medium risk) 3.5 Details of the 7 audit recommendations carried forward are in section 2 of the attached report along with the management response. These recommendations relate to the completion of the commissioning process, a clear audit trail for parts ordered and a stock recording system.

Alternative options

4.1None for the purposes of this report.

London Borough of Merton

Page 268 5. Consultation undertaken or proposed

5.1The Strategic Plan, Internal Audit Plan and Audit Charter have been agreed with Chief Officers who have consulted with their Management teams. Business Partners and Financial Advisors for each department have also been consulted. Customer Agreements are in place. The Head of Audit & Investigations has monthly meetings with the Director of Corporate Services to report upon progress against the Plan.

5.2Audit briefs outlining the scope and objectives of each audit are agreed with the relevant manager prior to the audit commencing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Vehicle Maintenance Follow-up Audit ReviewReport 154 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
TO
Test OfficerCouncil Staff, expected
PM
Peter McCabeChair, present
JH
Janice HowardVice-Chair, present
LA
Laxmi AttawarCommittee Member, present
AB
Adam BushCommittee Member, apologies
TB
Tobin ByersCommittee Member, present
SC
Stephen CroweCommittee Member, apologies
MC
Mary CurtinCommittee Member, apologies
IM
Ian Munn BSc, MRTPI(Rtd)Committee Member, present
DW
David WilliamsCommittee Member, apologies
AM
Agatha Mary AkyigyinaCommittee Member, present

More from Merton General Purposes Committee

All decisions
MeetingDecisionOutcome
10 Mar 2016 Certification of Claims and Returns Annual Report 2014-15RESOLVED Members noted the report Noted Open
10 Mar 2016 External Audit: Audit PlanRESOLVED Members noted the report Noted Open
10 Mar 2016 External Audit:Audit BriefingRESOLVED The Committee noted the Briefing Document Noted Open
10 Mar 2016 Internal Audit: Progress ReportRESOLVED That the General Purposes Committee: A. noted the Internal Audit Progress Report and comment upon matters ar... Noted Open
10 Mar 2016 Internal Audit: Plan,Strategy and CertificateRESOLVED The General Purposes Committee reviewed the 2016/17 Draft Internal Audit Strategy, Plan and Charter. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies