Report to Governance Standards and Audit Committee
Agenda Item 12 Committee: Standards and General Purposes Committee Date: 9 November 2017 Wards: All Subject: Progress Report on Risk Management Lead officer: Caroline Holland, Director of Corporate Services Lead member: Councillor Mark Allison, Deputy Leader of the Council and Cabinet Member for Finance Contact officer: Zoe Church, Head of Business Planning, 020 8545 3451
Recommendations: A. That the Standards and General Purposes Committee reviews the adequacy of the risk management framework and the associated control environment B. To consider the Key Strategic Risks and Issues faced by the council, and determine whether these are being actively managed
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 The purpose of this report is to provide a progress report on risk management within Merton, including details of the Key Strategic Risks (KSRs) faced by the council.
1.2The risk management strategy was revised by the Business Planning Team in early January 2017 taking account of recommendations made by the Corporate Risk Management Group on 11 January 2017. The strategy was then approved by Cabinet on 13 February 2017 and approved by Council on 1 March 2017 as part of the 2017-21 Business Plan. The current Risk Management Strategy is at Appendix I.
1.3The procedure for identifying and monitoring risks is that each department manages their risks through their risk registers, and these are reviewed quarterly by DMTs. Any significant risks which may have a strategic impact are escalated by the Corporate Risk Management Group (CRMG) to CMT for inclusion on the Key Strategic Risk Register (KSRR) to ensure that risks which affect the council are being effectively monitored and managed.
1.4Strategic oversight is provided by Cabinet and the Standards and General Purposes Committee.
2 DETAILS 2.1. The risk management strategy emphasises the benefits of effective risk management, particularly in the context of budget savings. The strategy includes clear guidance for defining the likelihood and impact of risks, and the appropriate matrices for assessing these. This results in consistency across the council when it comes to scoring and monitoring risk. Where risks
Page 115 which might affect the Council as a whole are concerned, the strategy clearly sets out the process for escalating risks onto the KSRR. 2.2. The procedure for managing risk is laid out clearly in the strategy. Departmental risks are reviewed quarterly by the relevant risk champions and DMTs, to ensure that they have been assessed accurately and in a manner consistent with risk assessment across the organisation. 2.3. Risks rated as High (Red) risks must be supported by an action plan to mitigate against the risk. Where possible, the risks are linked to an existing action plan such as a service or project plan, and up-to-date management commentary is supplied to demonstrate progress with mitigation actions. 2.4. CRMG meets quarterly within two weeks of the DMT risk review meetings, and subjects the departmental risk registers and the KSRR to thorough scrutiny and challenge. Proposed amendments to KSRs, including the addition or deletion of risks, are escalated to CMT via a quarterly risk report. Any urgent decisions regarding KSRs can be escalated to CMT via the monthly finance and performance report. 2.5. In accordance with the risk reporting cycle, the last quarterly review of the KSRR by DMTs took place during September 2017. These reviews were scrutinised at CRMG on 4 October 2017, and a report on the status of the KSRR was subsequently presented to CMT on 24 October 2017. 2.6. There are currently 18 Key Strategic Risks and Issues on the KSRR. • A Risk is defined as an event which may happen in the future • An Issue is something that is happening now.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.