Resolved
That the report was noted.
South London Waste Partnership Joint Committee noted this item on Tuesday 18 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report was noted.
1.1The Partnership sets it budget in December for the forthcoming financial year.
1.2The budget is monitored regularly by Management Group to allow the budgets to be flexed where appropriate in order to respond to any budget pressures.
2. Financial Position 2018/19
2.1The table below refers to the Partnership’s outturn position for its Strategic Management activities for the 2018/19 financial year. It relates to expenditure in the following areas; procurement, project management, administration, contract management and communications.
Page 21 1 Approved Final Variance Item Budget Outturn £ £ £
Internal and External Advisors 175,000 112,665 (62,335)
Project & Contract 500,000 533,198 33,198 Management
Document and Data 24,000 22,702 (1,298) Management
Communications 25,000 22,555 (2,445)
TOTAL 724,000 691,120 (32,880)
COST PER BOROUGH 181,000 172,780 (8,220)
2.2The Partnership’s budget for core functions forecasts an under spend for the year of £32,880 (£8,220 per borough), an increase of £10,480 from the month 11 position of £22,400 reported to this committee on the 2 April 2019. The difference between month 11 and outturn is attributable to the final outturn being based on actuals and not rounded to the nearest £100, and due to de- minimus levels allowed for year-end accruals. The major variances are detailed below:
2.3External advisors underspend of £62k mainly due to the ERF contract not requiring the additional external advice budgeted as contingency.
2.4Project and contract management overspend by £33k due to additional cost of maternity cover, the evaluated grades of new posts through the changed structure last year being higher than budgeted and the impact of increments.
3. Recommendations: 3.1 To note the content of this report.
4. Impacts and Implications:
Finance
4.1Contained within report.
Page 22 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
South London Waste Partnership Budget Outturn 2018/19Report | 85 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Merton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2023 | Minutes of the Previous MeetingThat minutes of the meeting held on 25 April 2023 were agreed and signed as an accurate record. | Agreed | Open |
| 15 Jun 2023 | Contract Performance ReportThat the Joint Committee; · noted the contents of the report, and · commented on any aspects of the performance of th... | Noted | Open |
| 15 Jun 2023 | Partnership Budget Update 22/23 - Final Out-turnThat the report was noted. | Noted | Open |
| 25 Apr 2023 | Minutes of the Previous MeetingThat the minutes of the meeting held on 12 January were agreed as an accurate record. Item 8 on the agenda would be b... | Agreed | Open |
| 25 Apr 2023 | Partnership Budget Update - Month 11That the Committee noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.