That Council approve the following Capital Scheme to be included in the Capital Programme, funded by the deletion of the scheme below: Scheme 2019/20 Budget 2020/21 Budget Narrative Sports Facilities – Wimbledon Park Lake De-Silting (1,393,160) 0 Money being vired to cover priority scheme on the lake Sports Facilities – Wimbledon Park Lake Reservoir Safety 75,000 1,318,160 Money required to cover statutory obligations Total (1,318,160) 1,318,160
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
That Council approve the following Capital Scheme to be included in the Capital Programme, funded by the deletion of the scheme below: 2019/20 2020/21 Scheme Budget Budget Narrative
Sports Facilities - Wimbledon Park Lake De-Silting (1,393,160) 0 Money being vired to cover priority scheme on the lake
Sports Facilities - Wimbledon Park Lake Reservoir Safety 75,000 1,318,160 Money required to cover statutory obligations
Total (1,318,160) 1,318,160
1. PURPOSE OF THE REPORT AND EXECUTIVE SUMMARY
1.1The purpose of this report is to approve the funding required to progress the Wimbledon Park Lake Reservoir Safety scheme.
1.2In accordance with the Authority’s Financial Regulations, any addition of £500,000 or more to the Capital Programme for a new scheme must be authorised by decision of Council. This is a distinct separate project to the Wimbledon Park De-Silting Project and requires such approval.
Page 93 2. DETAILS
2.1Wimbledon Park Lake
2.1.1 The approved capital programme 2019-23 contains £1,393,160 for Wimbledon Park Lake De-Silting. The capital fund set aside for Wimbledon Park Lake De- silting project should be reallocated to be Wimbledon Park Lake – Reservoir Safety. 2.1.2 It was originally envisaged that if the council invested in de-silting the lake that it would result in reservoir safety improvements that would assist the council in meeting its statutory obligations under The Reservoir Act 1975, but reports from studies recently commissioned identify that de-silting will not have this desired effect. The council is required to carry out Reservoir Safety improvements to Wimbledon Park Lake to comply with the Act by January 2022 and therefore request this fund be reallocated for this purpose. 2.1.3 In carrying out the Reservoir Safety requirements that the depth of water in the lake will be lowered and thus works in forthcoming years to de-silt would still be necessary if recreational pursuits wish to be maintained on this lake. 2.1.4 Proposals for de-silting as a stage 2 part to this project are intended to be developed as part of this first stage reservoir safety so that the council can progress in the future should funding be available and be deemed a priority post 2024. 3 FINANCIAL,RESOURCE AND PROPERTY IMPLICATIONS
3.1Progression of these schemes requires the following amendments to the Capital Programme: 2019/20 2020/21 Scheme Budget Budget Narrative
Sports Facilities - Wimbledon Park Lake De-Silting (1,393,160) 0 Money being vired to cover priority scheme on the lake
Sports Facilities - Wimbledon Park Lake Reservoir Safety 75,000 1,318,160 Money required to cover statutory obligations
Total (1,318,160) 1,318,160
3.2There is no revenue impact on the funding of the capital programme as the cost and source of funding remains the same.
3.3It is envisaged that an accurate spend profile will be established within the Capital Programme once the Quantity Surveyor and Design and Build Company are established.
Page 94 4 LEGAL AND STATUTORY IMPLICATIONS
4.1Detailed in the body of the report. 5 HUMAN RIGHTS, EQUALITIES AND COMMUNITY COHESION IMPLICATIONS 5.1 None for the purposes of this report
6 CRIME AND DISORDER IMPLICATIONS 6.1 None for the purposes of this report 7 RISK MANAGEMENT AND SAFETY IMPLICATIONS 7.1 None for the purposes of this report 8 RISK MANAGEMENT AND SAFETY IMPLICATIONS 8.1 None for the purposes of this report 9. APPENDICES 9.1 None 10 BACKGROUND PAPERS 10.1 Papers held by Resources.
Page 95 This page is intentionally left blank
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Notice of Motion - Labour MotionCouncil notes • With concern reports that St George's, Epsom and St Helier University Trust are considering proposals...
Appointment of Independent PersonsCouncil is asked to: A. Appoint Sabrina Winter and Anastasia Serdari for a three year period, both as Independent Per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.