That the items in the Table below are added to the approved and indicative Capital Programme: Narrative Budget 2020-21 Budget 2021-22 Indicative Indicative Total Budget 2026/27 Budget 2028/29 Street Lighting Wimbledon 150,000 670,000 0 0 820,000
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Agenda Item 23 Committee: Council Date: 18 November 2020 Wards: Subject: Approval of Street Lighting to the Approved Capital Programme Lead officer: Caroline Holland, Director Corporate Services Lead member: Mark Allison, Deputy Leader and Cabinet Member for Finance Contact officer: Roger Kershaw, Assistant Director Resources Urgent report: Reason for urgency: The chair has approved the submission of this report as a matter of urgency as it relates to the latest available monitoring information for 2020/21. This requires consideration as it has implications for current and future years’ budget monitoring and management.
Recommendations: 1. That Council approve items in the Table below are added to the approved and indicative Capital Programme: Indicative Indicative Budget Budget Narrative 2020-21 2021-22 Budget Budget Total 2026/27 2028/29
Street Lighting Wimbledon 150,000 670,000 0 0 820,000
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This report is being progressed in accordance with the Council’s Financial Regulations which requires that new Schemes for £500,000 and above require Council approval prior to being formally added to the approved Capital Programme. 1.2. This report seeks formal approval to add Street Lighting Wimbledon to the approved capital programme.
1. DETAILS OF THE STREET LIGHTING WIMBLEDON SCHEME
1.1No budgetary provision currently exists within the capital programme to cover the costs of Street Lighting Wimbledon.
1.2Greater demand is being placed on the existing Wimbledon Town Centre Lamp Columns to support a wider range of attachments – hanging baskets, banners, CCTV cameras, Wi-Fi equipment, 4G small cells etc. The columns were not originally designed to support a significant number of attachments and as the columns age and lose steel wall thickness due to rusting, they become less able to carry the load that the additional attachments place on the columns.
Page 41 1.3 Many of the electronic attachments require separate control gear which needs to be installed in the base compartment of the column. The existing columns do not have sufficient capacity in their base compartment to store the controls of this additional equipment. The proposed scheme would see approximately 135 columns in Wimbledon Town Centre and in Wimbledon Village replaced with new medium duty columns with double door compartments which will support both the additional weight and wind load of the many future attachments which are proposed for the columns as part of Smart Cities and Internet of Things roll-out, as well as provide the internal capacity within the column for the electronic controls of this equipment.
1.4The scheme would also see the existing SON lanterns (lamps which use high pressure sodium gases to cause illumination) replaced with new "white light" LED lanterns which have greater energy efficiency, longer life and provide better colour rendering and better overall lighting levels than the existing lanterns.
1.5This scheme is being funded by Strategic Community Infrastructure Levy (SCIL). The Council has been collecting SCIL funding since April 2014 when the Merton CIL Charging Schedule came into effect. The Community Infrastructure Levy Regulations 2010 (as amended) restricts expenditure of SCIL by a local authority to funding infrastructure to support the development (such as new homes and commercial buildings) of its area. As part of new amendment Regulations and Government guidance that came into effect on 1st September 2019 introducing transparency requirements a formal bidding process has been introduced for SCIL bids which is overseen by the Capital Programme Board. Although, SCIL allows greater flexibility than Section 106 in order to address demands of development (such as demands of new housing developments) it must deliver a component of infrastructure designed to provide new or better infrastructure/functionality/service or service new customers. SCIL funding can be used on both capital and revenue items
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Notice of Motion - Labour MotionCouncil notes • With concern reports that St George's, Epsom and St Helier University Trust are considering proposals...
Appointment of Independent PersonsCouncil is asked to: A. Appoint Sabrina Winter and Anastasia Serdari for a three year period, both as Independent Per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.