Council Approval for a Capital Scheme (Street Lighting Wimbledon)

Approved Committee 1 paper

Council approved this item on Wednesday 18 November 2020. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

That the items in the Table below are added to the approved and indicative Capital Programme: Narrative Budget 2020-21 Budget 2021-22 Indicative Indicative Total Budget 2026/27 Budget 2028/29 Street Lighting Wimbledon 150,000 670,000 0 0 820,000
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Council

Agenda Item 23 Committee: Council Date: 18 November 2020 Wards: Subject: Approval of Street Lighting to the Approved Capital Programme Lead officer: Caroline Holland, Director Corporate Services Lead member: Mark Allison, Deputy Leader and Cabinet Member for Finance Contact officer: Roger Kershaw, Assistant Director Resources Urgent report: Reason for urgency: The chair has approved the submission of this report as a matter of urgency as it relates to the latest available monitoring information for 2020/21. This requires consideration as it has implications for current and future years’ budget monitoring and management.

Recommendations: 1. That Council approve items in the Table below are added to the approved and indicative Capital Programme: Indicative Indicative Budget Budget Narrative 2020-21 2021-22 Budget Budget Total 2026/27 2028/29

Street Lighting Wimbledon 150,000 670,000 0 0 820,000

1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This report is being progressed in accordance with the Council’s Financial Regulations which requires that new Schemes for £500,000 and above require Council approval prior to being formally added to the approved Capital Programme. 1.2. This report seeks formal approval to add Street Lighting Wimbledon to the approved capital programme.

1. DETAILS OF THE STREET LIGHTING WIMBLEDON SCHEME

1.1No budgetary provision currently exists within the capital programme to cover the costs of Street Lighting Wimbledon.

1.2Greater demand is being placed on the existing Wimbledon Town Centre Lamp Columns to support a wider range of attachments – hanging baskets, banners, CCTV cameras, Wi-Fi equipment, 4G small cells etc. The columns were not originally designed to support a significant number of attachments and as the columns age and lose steel wall thickness due to rusting, they become less able to carry the load that the additional attachments place on the columns.

Page 41 1.3 Many of the electronic attachments require separate control gear which needs to be installed in the base compartment of the column. The existing columns do not have sufficient capacity in their base compartment to store the controls of this additional equipment. The proposed scheme would see approximately 135 columns in Wimbledon Town Centre and in Wimbledon Village replaced with new medium duty columns with double door compartments which will support both the additional weight and wind load of the many future attachments which are proposed for the columns as part of Smart Cities and Internet of Things roll-out, as well as provide the internal capacity within the column for the electronic controls of this equipment.

1.4The scheme would also see the existing SON lanterns (lamps which use high pressure sodium gases to cause illumination) replaced with new "white light" LED lanterns which have greater energy efficiency, longer life and provide better colour rendering and better overall lighting levels than the existing lanterns.

1.5This scheme is being funded by Strategic Community Infrastructure Levy (SCIL). The Council has been collecting SCIL funding since April 2014 when the Merton CIL Charging Schedule came into effect. The Community Infrastructure Levy Regulations 2010 (as amended) restricts expenditure of SCIL by a local authority to funding infrastructure to support the development (such as new homes and commercial buildings) of its area. As part of new amendment Regulations and Government guidance that came into effect on 1st September 2019 introducing transparency requirements a formal bidding process has been introduced for SCIL bids which is overseen by the Capital Programme Board. Although, SCIL allows greater flexibility than Section 106 in order to address demands of development (such as demands of new housing developments) it must deliver a component of infrastructure designed to provide new or better infrastructure/functionality/service or service new customers. SCIL funding can be used on both capital and revenue items

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Approval for a Capital Scheme (Street Lighting Wimbledon)Report 75 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

59 of 61 attended
SK
Sally KennyMayor, present
JD
John DehaneyDeputy Mayor, present
AM
Agatha Mary Akyigyina OBECommittee Member, present
SA
Stephen AlambritisCommittee Member, present
MA
Mark AllisonCommittee Member, present
SA
Stan AndersonCommittee Member, present
LA
Laxmi AttawarCommittee Member, present
EB
Eloise BaileyCommittee Member, present
TB
Thomas BarlowCommittee Member, present
NB
Nigel BenbowCommittee Member, present
HB
Hina BokhariCommittee Member, present
KB
Kelly BraundCommittee Member, present

All 61 on the meeting page

On this subject at Merton

Search all
  1. Council Approval for a Capital Scheme (Street Lighting Wimbledon)This decision
  2. Amendments to Revenue Budgets and the Capital Programme Requiring Cabinet Approval - Period 5Approved
  3. Financial Outturn Report 2024/25 - Capital Programme Amendments Requiring Council ApprovalApproved
  4. Approved Capital Programme Amendments Requiring Council ApprovalApproved

More from Merton Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the previous meetingThat the minutes of the meeting held on 20 May 2026 are agreed as an accurate record. Agreed Open
15 Jul 2026 Notice of Motion - Labour MotionCouncil notes • With concern reports that St George's, Epsom and St Helier University Trust are considering proposals... Decided Open
15 Jul 2026 Appointment of Independent PersonsCouncil is asked to: A. Appoint Sabrina Winter and Anastasia Serdari for a three year period, both as Independent Per... Agreed Open
15 Jul 2026 Update on Motions 2025/26Council is asked to: A. Note the updates within the report on motions passed at Council during the previous municipal... Noted Open
15 Jul 2026 Changes to membership of committees and related mattersA. Note the changes to the membership of Committees that were approved under delegated authority since the last meeti... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies