Resolved
That members reviewed and commented upon the 2021/22 Draft , Strategy and Charter.
Governance Standards and Audit Committee decided this item on Thursday 11 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That members reviewed and commented upon the 2021/22 Draft , Strategy and Charter.
A. That members review and comment upon the 2021/22 Draft Internal Audit Plan, Strategy and Charter.
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The Draft Internal Audit Plan, Strategy and Charter 2021/22 are included in Appendix 1.
2 DETAILS
2.1A risk-based audit plan has been set based on the approach set out in the audit strategy (Annex 1). In preparing the plan, the Head of Audit has taken account of the adequacy and outcomes of the organisation’s risk management, performance management and other assurance processes.
2.2The Head of Audit provides copies of the draft plan to department directors and attends the departmental management teams where they may request audits to be added to provide assurance on their areas of risk. Comments are also obtained from their Heads of Services and key managers, departmental finance advisors.
2.3The 2021/22 Audit Plan detailed in Appendix 1 may be subject to review during the year, due to changes in risk and priorities for the Council as result of COVID 19.
Page 97 Information Technology audits
2.4Where IT audits are of a specialist nature, they require the detailed technical knowledge and expertise of a skilled IT practitioner; the framework contract with Mazars is used. An IT needs Assessment was undertaken by Mazars in 2020/21 and audits identified for the 2021/22 audit plan.
Proactive Fraud Team
2.5In 2021/22 a temporary Proactive team is being established across 4 of the 5 partnership Council, including Merton, to undertake analysis of vendor spend across the partnership, identifying areas at high risk of fraud and feeding this into a programme of deep dive end to end testing. This team will be in place for 2 years.
2.6The service will be responsible for undertaking the following for each of the partners: Analysis of financial and other information as part of a robust assessment of risk, to identify possible fraud, error and/or mismanagement. This will include detailed analysis of vendor spend against contract registers and review of budgetary control information.
Targeted end to end testing on procurement activity directed by the risk assessment process (above). This will include ensuring that contract procedure rules and associated legislation have been followed at the point of commissioning, assessing the adequacy of the procurement process and decision to award to the chosen contractor, analysing and reconciling orders and invoice payments through to service delivery and/or receipt of goods.
Any fraud or error identified will be investigated by the proactive team in liaison with the South West London Fraud Partnership (SWLFP).
Provision of written reports making recommendations for action which may include improving controls/processes, taking disciplinary action against staff or seeking recompense from contractors/suppliers.
3.1None for the purpose of this report.
4 CONSULTATION UNDERTAKEN OR PROPOSED
4.1The draft Audit Plan has been sent to all Chief Officers who have consulted with their management teams. The Head of Audit attends Departmental Management Teams to discuss the audit coverage. 5 TIMETABLE
5.1The Internal Audit Plan will be the basis of Internal Audit’s programme of work 2
Page 98 throughout the 2021/22 financial year. The timing of individual audits is considered in consultation with the Departments where possible.
6 FINANCIAL, RESOURCE AND PROPERTY IMPLICATIONS
6.1The audit plan is completed within the provision of existing resources. The Proactive Fraud team cost of £68,945 over 2 years is covered from reserves.
7 LEGAL AND STATUTORY IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit PlanReport | 235 KB | DownloadRead as text |
Follow Governance Standards and Audit Committee at Merton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | External Audit UpdateIt was resolved that the Committee noted and commented on the report | Noted | Open |
| 3 Sep 2026 | Update on the progress of the audit on the 2025/26 Statement of AccountsIt was resolved that the Committee noted and commented on the report. | Noted | Open |
| 3 Sep 2026 | Internal Audit Progress ReportIt was RESOLVED that the Committee noted and commented on the report. | Noted | Open |
| 3 Sep 2026 | Corporate Complaints ReportIt was RESOLVED that the Committee noted and commented on the report | Noted | Open |
| 3 Sep 2026 | Complaints against MembersIt was RESOLVED that the Committee noted and commented on the reprot | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.