AI summaryLondon Borough of Merton's Governance Standards and Audit Committee reviewed the Q1 2025-26 Key Strategic Risk Register, noting seven red-rated risks including housing supply, cyber security and the annual savings programme.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedQ1 2025-26, with 7 red risks or issues
MoneyNot stated
What happens nextZurich recommendations to feed into KSRRFrom Q2 2025-26, revised strategy due February 2026
Who it affectsCouncil-wide risk management and operationsIncludes housing, schools, IT, climate and budget
What was decided
The Committee reviewed the adequacy of the risk management framework and the associated control environment. Report P1, P4
Members considered the Key Strategic Risks and Issues faced by the council and whether these are being actively managed. Report P1, P4
The Committee reviewed the Key Strategic Risk Register as of Q1 2025-26, which contains 9 Key Strategic Risks and 3 Key Strategic Issues. Report P30
Why
As part of the remit of the Governance Standards and Audit Committee, members are required to review the adequacy of the risk management framework. Report 7.1
It is best practice to review Key Strategic Risks and Issues periodically to ensure effective action is being taken to mitigate them. Report 5.1
Good corporate governance requires mechanisms to be in place for the identification and management of risk. Report 5.2
What happens next
Officers will compile an action plan in response to Zurich's recommendations, with changes feeding into the KSRR from Q2 2025-26. Report P45
A revised Risk Management Strategy will be presented via the Budget Process in February 2026. Report P45
From October 2025, the Leader's Strategy Group will receive quarterly updates on the KSRR, and CLT is being asked to consider adding a Health and Safety risk to it. Report 2.4, P64
Options considered
Chosen: Review the Key Strategic Risks and Issues periodically. Best practice and a requirement of good corporate governance. Report 5.1, 5.2, 6.1
Implications
Legal: Risk management is an essential part of sound corporate governance and good management within any organisation. Report P62
Financial: Financial Risks are contained in the body of the report; resourcing of the response to Zurich's recommendations is also covered there. Report P62
Equalities: One Key Strategic Issue on the KSRR concerns Equalities duties (CPI41 / KSR53). Report P62
Climate: One Key Strategic Risk on the KSRR concerns implementation of the Climate Action Plan (CC01 / KSR84). Report P62
Risk: Seven entries on the KSRR are red-rated, including Housing Supply (scored 20), Annual Savings Programme (18), and Cyber Attack (16). Report P37, P38, P39, P40, P41
Risk: The Cyber Attack risk score has increased from 12 (Amber) to 16 (Red) since the last quarterly review. Report P42
Staffing: Staffing implications are noted as being contained in the body of the report. Report P63
Schools, given DSG Safety Valve and School Budget Deficit risks (LL0003 / KSR95 and LL0004 / KSR96) Report P40, P41
Council IT users and service users, given the elevated Cyber Attack risk (DIG0002 / KSR83) Report P40, P42
Council-wide budget holders, given the Annual Savings Programme and Corporate Business Plan and Balanced Budget risks Report P39, P41
Timeline
March 2025: Risk Management Strategy approved by Council and closed session held on Cyber Security risk. Report 2.1, 2.2
October 2025: Leader's Strategy Group to start receiving quarterly KSRR updates. Report 2.4
Q1 2025-26: Current Key Strategic Risk Register snapshot considered by the Committee. Report P1, P30
Q2 2025-26: Changes responding to Zurich's recommendations start to feed into the KSRR. Report P45
February 2026: Revised Risk Management Strategy to be presented via the Budget Process. Report P45
Plain English for the jargon
KSRR: Key Strategic Risk Register, the council's register of its most significant strategic risks and issues.
KSR: Key Strategic Risk, an individual high-level risk on the KSRR.
CRMG: Corporate Risk Management Group, which meets quarterly to scrutinise risk registers.
CLT: Corporate Leadership Team, which reviews the KSRR each quarter.
DLT: Departmental Leadership Team, which reviews departmental risks each quarter.
DSG Safety Valve: A government programme to help councils manage deficits in the Dedicated Schools Grant.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
It was RESOLVED that the Committee - Reviewed the adequacy of the risk management framework and the associated control environment. - Considered the Key Strategic Risks and Issues faced by the council, and determine whether these are being actively managed. Review the Key Strategic Risk Register as of Q1 2025-26.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Report to Governance Standards and Audit Committee
Recommendations
Governance, Standards and Audit Committee is asked to: A. Review the adequacy of the risk management framework and the associated control environment. B. Consider the Key Strategic Risks and Issues faced by the council, and determine whether these are being actively managed. Review the Key Strategic Risk Register as of Q1 2025-26.
Page 123 Recommendations, report summary and relevance to strategic priorities
1. Recommendations (repeated from page 1)
Governance, Standards and Audit Committee is asked to: A. Review the adequacy of the risk management framework and the associated control environment. B. Consider the Key Strategic Risks and Issues faced by the council, and determine whether these are being actively managed. Review the Key Strategic Risk Register as of Q1 2025-26.
Executive summary
2.1The purpose of this report is to provide a progress report on risk management within Merton, including details of the Key Strategic Risks (KSRs) faced by the council since the report presented on 7 November 2024. In March 2025, there was a closed session to discuss Merton’s risk management of Cyber Security (DIG0002/ KSR83 Risk of Cyber attack on the Council’s IT Infrastructure and Systems).
2.2The attached risk management strategy was approved by Council in March 2025 (Appendix A).
2.3All departments review their risks each quarter at their respective DLTs, followed by a review of all risks by the Corporate Risk Management Group (CRMG). The final report in the quarterly cycle is presented to CLT to review the risks that are on the Key Strategic Risk Register (KSRR); these are significant risks/issues, which may have a strategic impact on the council as a whole. (Attached as Appendix B- Q1 2025/26)
2.4From October 2025, the Leader’s Strategy Group will receive quarterly updates on the KSRR.
2.5Strategic oversight is provided annually by Cabinet, and assessment of governance arrangements are considered as part of the annual report to the Governance Standards and Audit Committee.
3. Relevance to strategic priorities, including Council Plan priorities
Strategic priority Relevant? Brief explanation of relevance
Borough of Sport Officers are required to consider the risks in relation to day-to-day operations ✓ and developmental projects and escalate and mitigate accordingly
Page 124 Strategic priority Relevant? Brief explanation of relevance
Building a Officers are required to consider the sustainable future risks in relation to day-to-day operations ✓ and developmental projects and escalate and mitigate accordingly
Nurturing civic pride Officers are required to consider the risks in relation to day-to-day operations ✓ and developmental projects and escalate and mitigate accordingly
Other service The Key Strategic Risk Register is delivery priority critical for ensuring that business is ✓ conducted in accordance with the law and proper standards and is critical for the progress of the three priorities
Organisational Officers are required to consider the development risks in relation to day-to-day operations ✓ and developmental projects and escalate and mitigate accordingly
Page 125 Background, options and next steps
4. Introduction and background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.