Acquisition of 146 homes at the former Mitcham Gas Works (CR4 3ED) from St William (Berkeley Homes) to provide new Council homes at social rent

Approved Committee 1 paper

AI summaryCouncil asked to approve capital programme allocation of 60,000 £000s to buy 146 homes at former Mitcham Gas Works from St William for social rent.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital programme allocation to buy 146 homes
Money60,000 £000sTotal scheme cost over four years
What happens nextExchange mid-February 2026Following Council approval on 4 February 2026
Who it affectsHousing register and homeless householdsAround 2,000 in acute need, 751 in temporary accommodation

What was decided

Council asked to approve the capital funding allocation for the purchase of 146 homes at the former Mitcham Gas Works from St William, a subsidiary of the Berkeley Homes Group, for use as social rented council homes. Report 2.12, 4.1

The homes will be acquired on a 999 year lease, financed initially through the General Fund and later appropriated to the Housing Revenue Account, contingent on GLA grant funding being confirmed. Report 4.1, 4.7

Cabinet previously approved the proposal on 19 January 2026, and the Council is now asked to confirm the capital programme allocation set out in the decision. Report 4.1

Why

Merton has over 10,000 households on the housing register, around 2,000 in acute need, and 751 households in temporary accommodation, a 260% increase since 2020. Report 2.4, 2.5

Affordability has worsened across all wards and tenures except social rent, with the average house price in Merton at £622,000 in April 2025. Report 2.3

The scheme gained planning permission on 27 November 2025 with no affordable housing on viability grounds, and the acquisition will deliver 24% of the site as affordable homes by habitable room. Report 4.2, 4.3

What happens next

GLA grant funding settlement to be agreed, as the actual capital required will only be confirmed once this is in place, with a Red Book Valuation to be issued prior to contract execution.

Exchange of contracts is anticipated mid-February 2026, with start on site in Q1 2026, and the Council will enter into a Development Agreement followed by an Agreement for Lease. Report 6.5

A separate report will follow on the financial implications of transferring the asset to the HRA and the impact on the 30 year HRA business plan. Report 4.7

The money

  • 60,000 £000s Total scheme capital programme allocation across 2026-27 to 2029-30
  • 29,360 £000s Capital allocation for 2026-27
  • 10,280 £000s Capital allocation for 2027-28
  • 10,280 £000s Capital allocation for 2028-29
  • 10,080 £000s Capital allocation for 2029-30
  • £25.982m Estimated addition to the Capital Financing Requirement
  • £514,640 Per annum for 50 years minimum revenue provision, charged to the General Fund
  • £2.6m Small negative 50-year NPV after discounting, with break-even at year 20
  • £150k Capitalised project management budget during construction Report P80

Options considered

  • Rejected: Do not approve the acquisition of 146 homes. Slower stock growth, scheme may be mothballed, continued reliance on temporary accommodation Report P47, P48, P49, P50, P51, P52
  • Chosen: Approve the acquisition of 146 homes. Preferred option: delivers new energy efficient social rented homes, fixed price, contributes to 400 home target Report P53, P54, P55, P56, P57, P58, 9.1

Implications

  • Financial: Adds £25.982m to the Capital Financing Requirement with a £514,640 annual minimum revenue provision for 50 years, wholly impacting the General Fund.
  • Financial: Scheme breaks even in revenue terms at year 20 over 50 years assuming rents at Formula rent +5%, with a small negative 50-year NPV of £2.6m.
  • Legal: Acquisition powers derive from Section 120 Local Government Act 1972, Section 9 Housing Act 1985, Section 1 Localism Act 2011, and homelessness duties under the Housing Act 1996 and Homelessness Reduction Act 2017. Report P73, P74
  • Equalities: Public Sector Equality Duty considered; scheme intended to reduce inequalities for disadvantaged households, including overrepresented black and minority ethnic communities in temporary accommodation. Report P76, P77, P78
  • Climate: New homes will meet building standards and be energy efficient, with positive impact on carbon reduction and addressing fuel poverty. Report P79
  • Risk: Key risks are failure to secure GLA grant funding and inability to agree terms with the vendor, mitigated through ongoing GLA discussions and legal advice. Report P80
  • Staffing: Additional staffing and capacity required to deliver the development, with a £150k capitalised project management budget during construction. Report P80

Who and where

  • Around 2,000 households in acute housing need in Merton, including homeless households and those with old age, special, or medical needs Report 2.4
  • 751 homeless households currently in temporary accommodation Report 2.5
  • Over 10,000 households on Merton's housing register Report 2.4
  • St William, a subsidiary of the Berkeley Homes Group, as vendor Report 2.12, 4.1
  • Greater London Authority as potential grant funder through the Affordable Homes Programme 21-26 Report 2.12

Timeline

  • 27 November 2025: Planning permission granted for the Mitcham Gas Works scheme with no affordable housing on viability grounds Report 4.2
  • 19 January 2026: Cabinet approved the proposal to purchase 146 homes including Exempt Appendix 1 Report 4.1
  • mid-February 2026: Anticipated exchange of contracts
  • Q1 2026: Anticipated start on site by St William, required to start prior to end of March 2026 for GLA grant bid
  • 04 February 2026: Full Council meeting to consider capital programme allocation
  • April 2027: Cabinet previously agreed to re-establish the Housing Revenue Account from this date Report 4.7

Plain English for the jargon

  • HRA: Housing Revenue Account, a local authority account ring-fenced for income and spending on council housing
  • EUVSH: Existing Use Value Social Housing, a valuation method for social housing stock
  • S106: Section 106 planning obligation requiring developers to contribute to affordable housing or infrastructure
  • GLA: Greater London Authority
  • NPV: Net Present Value, a financial measure comparing future cash flows to today's money
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

Council is asked to: A Approve the allocation funding set out Exempt Appendix 1 B Approve the following allocation to the Capital Programme for the purchase of property as part of the Mitcham Gas Works Redevelopment: Total 2026- 2027- 2028- 2029- £000s 27 28 29 30 £000s £000s £000s £000s Total Scheme 60,000 29,360 10,280 10,280 10,080
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Council

Executive summary

2.1The Council’s corporate plan “Building a Better Merton Together 2023-26” sets out the Council’s ambition for the borough. The Plan has three priorities of which one is building a sustainable future. The Plan acknowledges good quality affordable homes are essential and accelerating the supply of affordable and sustainable homes is a key priority for the Council.

2.2There is a significant shortage of affordable housing in London, and this is particularly acute in Merton. Many residents of the Borough are experiencing hardship because of a malfunctioning housing market. The reasons are multiple and complex, but the result is the same.

2.3Levels of affordability in Merton (measured as a proportion of income) have worsened across all wards and across tenures, excepting social rent. The average house price in Merton in April 2025 is £622,000, an 11% increase from 2022. For London it is £567,000 in April 2025, a 7% increase from 2022.

2.4The Council has over 10,000 households on the housing register, which represents a 10% increase in the last 5 years of which approximately 2000 are in acute need. These include households who are experiencing homelessness, and those who are vulnerable due to old age, special needs, medical needs or overcrowding, and young people in need.

2.5There has been a significant increase in homelessness demand, coupled with a drop in private sector renting affordability, driving the fact that there are now 751 homeless households in temporary accommodation, a 260% increase since 2020.

2.6Temporary Accommodation supply is increasingly scarce and procuring sufficient temporary accommodation and ensuring the demand for permanent

Page 102 accommodation is met are two of the largest challenges facing LB Merton. Many landlords are leaving the private rented sector market, which is reducing the volume of Private rented sector (PRS) supply, forcing LB Merton to increase the use of expensive nightly paid accommodation for emergency accommodation to meet statutory duties.

2.7Despite the Council’s best efforts through its approach to inward investment and as the local planning authority which has granted consent for a number of significant housing schemes these are not being built. The Council recognises that the bulk of new housing supply needs to come from the private sector, and the Council will continue to work with partners to facilitate private sector development of sites.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Acquisition of 146 homes at the former Mitcham Gas Works (CR4 3ED) from St William (Berkeley Homes) to provide new Council homes at social rentReport 275 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

53 of 58 attended
SE
Sharon EvansCouncil Staff, expected
KL
Keir LewisCouncil Staff, expected
SK
Sally KennyCommittee Member, present
AM
Agatha Mary Akyigyina OBECommittee Member, present
SA
Stephen Alambritis MBECommittee Member, present
LA
Laxmi AttawarCommittee Member, present
TB
Thomas BarlowCommittee Member, present
HB
Hina Bokhari OBECommittee Member, present
MB
Mike BruntCommittee Member, present
BC
Billy ChristieCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
AF
Anthony FaircloughCommittee Member, present

All 58 on the meeting page

On this subject at Merton

Search all
  1. Acquisition of 146 homes at the former Mitcham Gas Works (CR4 3ED) from St William (Berkeley Homes) to provide new Council homes at social rentThis decision
  2. Acquisition of Homes for use as affordable housingAgreed

More from Merton Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the previous meetingThat the minutes of the meeting held on 20 May 2026 are agreed as an accurate record. Agreed Open
15 Jul 2026 Notice of Motion - Labour MotionCouncil notes • With concern reports that St George's, Epsom and St Helier University Trust are considering proposals... Decided Open
15 Jul 2026 Appointment of Independent PersonsCouncil is asked to: A. Appoint Sabrina Winter and Anastasia Serdari for a three year period, both as Independent Per... Agreed Open
15 Jul 2026 Update on Motions 2025/26Council is asked to: A. Note the updates within the report on motions passed at Council during the previous municipal... Noted Open
15 Jul 2026 Changes to membership of committees and related mattersA. Note the changes to the membership of Committees that were approved under delegated authority since the last meeti... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies