Resolved
RESOLVED that the recommendations be NOTED and further considered during discussions on the budget later in the meeting. (Proposed by the Chairman) Note : Report previously circulated, copy attached to signed minutes.
Cabinet noted this item on Thursday 5 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the recommendations be NOTED and further considered during discussions on the budget later in the meeting. (Proposed by the Chairman) Note : Report previously circulated, copy attached to signed minutes.
DECENT & AFFORDABLE HOMES PDG 20 JANUARY 2015
HRA BUDGET 2015/16
Cabinet Member Cllr Peter Hare-Scott, Cllr Ray Stanley Responsible Officer Head of Finance, Head of Housing
Reason for Report: This report provides an estimate of the budget required for the operation of the Housing Revenue Account (HRA) in 2015/16. It includes a proposal on the rent increase and a schedule of other fees and charges.
RECOMMENDATION: That the PDG agree the rent increase proposed, along with the rest of the budget proposals and agree for MDDC to investigate the feasibility of creating a Special Purpose Vehicle, as described in paragraph 3.5.
Relationship to Corporate Plan: The financial resources of the Council directly impact on its ability to deliver its Corporate Plan objectives/pledges.
Financial Implications: A balanced and realistic budget must be set for 2015/16 in order to maintain a sustainable Housing Revenue Account with adequate investment for necessary maintenance. The rent convergence target of 2015/16 will need to be met in order that the 30 year business plan and debt repayments are achieved.
Legal Implications: It is a statutory requirement for the Council to set a balanced budget.
Risk Assessment: Service managers and Finance staff have assessed volatility in income and large contractor budgets. In addition, reserves will continue to be maintained at prudent levels and grown in some cases to meet future pressures.
1.0Introduction
1.1Finance and Housing officers have now collated a final budget for 2015/16 which proposes a balanced budget position, shown here in Appendix 1. We are able to predict with relative certainty the majority of the HRA budget areas, since uncertainties reduce as we get closer to the new financial year.
2.0Draft Budget
2.1We are required to set an HRA budget where expenditure is balanced by income. The income is made up primarily of dwelling rents whereas the expenditure consists of day-to-day operations, corporate overheads and capital expenditure. The largest expenditure in the HRA is an annual debt repayment of £2,645k that is made to the Public Works Loan Board. 2.2 Our rent income (both dwelling and non-dwelling) is expected to generate in excess of £13m in 2015/16.
2.3The major challenge for managers in setting next year’s budget is to meet the significant demand for investment in property maintenance in the long term. It is proposed that £2,323k be budgeted as an annual contribution to the Housing Maintenance Fund to provide for any spikes in demand in future years. This will allow for properties to be maintained to an appropriate standard as well as enabling Mid Devon to support the provision of new social housing.
2.4Recharges between the General Fund and HRA are yet to be finalised, but overall the position between the HRA and the General Fund has been assumed as increasing in line with estimated salary growth.
Rent convergence
2.5MDDC rents currently lag behind Formula Rent (the target that we are tasked with meeting by 2015/16). DCLG are increasing Formula Rent by 2.8%. This means that MDDC need to increase rent even more if the gap is to be closed in time.
2.6By increasing the rents by an average of 3.4%, we will ensure that the vast majority of properties have reached the Formula Rent and those that lag further behind are moved towards Formula Rent as quickly as is possible.
Other Fees & Charges
2.7It is proposed that garage plot ground rents are increased from £165 to £185 per annum. This move is designed to align them more closely with residential parking permits, which will cost £375 in the coming year. In addition, it is proposed that garage rents increase by 2.3% to £11.25 per week.
HRA Reserve
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA budget 2015/16 (00-14-36)Report | 122 KB | DownloadRead as text |
Follow Cabinet at Mid Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... | Approved | Open |
| 4 Aug 2026 | Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... | Approved | Open |
| 4 Aug 2026 | 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... | Noted | Open |
| 4 Aug 2026 | Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... | Decided | Open |
| 4 Aug 2026 | Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies