RESOLVED that the revisions to the pre-application advice service as set out in this report be agreed and come into force from 1 st January 2016 and that the guidance document be updated accordingly. (Proposed by the Chairman) Note: *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
That the revisions to the pre-application advice service as set out in this report be agreed and st come into force from 1 January 2016 and that the guidance document be updated accordingly.
Relationship to Corporate Plan: Planning decision making is relevant to key objectives within the Corporate Plan of thriving economy, better homes, empowering our communities and caring for our environment.
Financial Implications: The provision of pre application advice is a discretionary customer service that also acts as an income stream for the Planning Service. The cost of providing the service in terms of staff time and resources must be balanced against value of providing a service to customers and the income received.
Legal Implications: As with existing pre-application advice, the scheme will need to continue to make it clear that the advice given is made in good faith, is not a guarantee that a particular decision will be made and is not binding on the Local Planning Authority in the event of an application being made.
Risk Assessment: The scheme sets out clear timescales for the receipt of a reply and what form that reply will take. It also clarifies the extent of advice and number of meetings offered. The Planning Service needs to be able to resource this level of service in order to ensure the success of the scheme. If service levels are not met, applicant expectations will not be met and it will have a detrimental effect on the working relationship with agents and applicants.
1.0INTRODUCTION
1.1A system for prospective developers to gain pre-application planning advice incorporating a charge was introduced in May 2010, together with the detail of standards of service. It was reviewed in March 2014, at which time changes were made to categories of development and associated charging. This report seeks to update the approach to charges for heritage advice based on the experience of operating a chargeable service for some of this area of work since June 2014.
1.2Some other agencies that feed into the consideration of planning related applications also now charge for pre-application advice. The costs referred to in this document relate only to advice provided by Mid Devon District Council Planning and Conservation officers. Statutory consultees may wish to make a separate and additional charge for pre-application advice.
2.0BACKGROUND: ADVANTAGES OF THE SERVICE.
2.1The Planning Service provides advice to our customers at an early stage in the development process and before a planning application is submitted. Such advice is considered vital and is encouraged wherever possible. The advantages of providing this service are as follows:
i) Our customers have the ability to discuss their proposals early on and before the details have been established. The input of planning guidance at this stage gives customers more certainty about how their proposal is likely to be received and allows for schemes to be amended in accordance with advice in order to overcome difficulties and ensure the application deals with important planning issues. A proportion of proposals do not progress beyond this stage as a result of advice gained.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.