RESOLVED that all ground mounted solar PV applications seeking an extension of time (including small applications) be brought before the committee for determination. (Proposed by Cllr S G Flaws and seconded by Cllr R J Dolley) Notes : (i) Cllrs [name removed] and P J Heal requested that their vote against the decision be recorded; (ii) * Report previously circulated copy attached to signed minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
So that authority for the determination for such applications is clearly set out.
Risk Assessment:
None
Background
1.1Applications have been submitted under LPA ref: 15/01612/FULL at Ellicombe farm in Morchard Bishop, and under LPA ref: 15/01613/FULL at Palfreys Barton at Cove
AGITEM and related to solar PV schemes. Both schemes have been built and when planning permission was granted (LPA ref: 12/01306/MFUL and 12/01376/MFUL) each was granted for 25 years as specifically set at condition 1 of both permissions.
1.2The current applications seek to extend the life time of each development by a further 5 years.
1.315/01612/FULL at Ellicombe Farm: A Variation of condition 1 of planning permission 12/01306/MFUL is requested so that the solar PV facility shall cease to generate electricity on or before 28th March 2043
1.415/01613/FULL at Palfreys Barton: A variation of Condition 1 of Planning Permission 12/01376/MFUL is requested so that the solar PV facility shall cease to generate electricity in or before 30th June 2043.
2.0ASSESSMENT ISSUES
2.1Both schemes have already been assessed and approved by the Local Planning Authority under the original planning applications. No changes to the layout are proposed. The only change is to the duration of the lifetime of the development. The issues to be assessed in the consideration of these extension of time applications are therefore very limited.
2.2Both applications have been advertised and consulted on in accordance with the LPA’s statutory procedures. No response to either application have been received which raise any further, new planning issues for consideration.
2.3Although there are only two applications at present it is likely that similar applications will be received in the future for the other schemes that have been built out.
3.0CONCLUSION
3.1Where applications are submitted that seek to extend the life time of authorised solar farms by a further 5-10 year period over and above the permitted timeframe, that the decision for these types of applications should be delegated to the Head of Planning and Regeneration rather than automatically being considered by Planning Committee as is currently the case. This would not preclude a Ward Members, the Chair or Vice Chair of Committee requesting that the application be considered by Committee having given planning reasons for doing so.
Contact for any more information Simon Trafford (Area Planning Officer) 01823 234369
Background Papers Planning Committee 20th February 2013 and 21st October 2015
File Reference Circulation of the Report Cllr Richard Chesterton
AGITEM
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.