It was AGREED that this information would be presented to the May meeting of this Committee. Discussion took place regarding: · IT systems being implemented and the perceived lack of follow up support for users; · Levels of sickness and reporting methods; · The number of empty homes in the district and the reasons why they could be empty; · Improvements from last year to performance regarding food premises inspections but further improvements were still needed; · The Leisure Service not meeting income performance targets; · Work that was being undertaken with the Town Centre Manager to look at empty premises above shops and whether they could be brought into use for housing; · The need for a named Head of Service to be identified as responsible for each risk. Note : - Report previously circulated and attached to Minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
PERFORMANCE AND RISK REPORT FOR THE THIRD QUARTER OF 2015-16
Cabinet Member Cllr Peter Hare-Scott Responsible Officer Head of Communities & Governance, Amy Tregellas
Reason for Report: To provide Members with an update on performance against the corporate plan and local service targets for 2015-16 as well as providing an update on the key business risks.
RECOMMENDATION: That the Committee reviews the Performance Indicators and Risks that are outlined in this report and feeds back any areas of concern to Cabinet.
Relationship to Corporate Plan: Corporate Plan priorities and targets are effectively maintained through the use of appropriate performance indicators and regular monitoring.
Financial Implications: None identified
Legal Implications: None
Risk Assessment: If performance is not monitored we may fail to meet our corporate and local service plan targets or to take appropriate corrective action where necessary. If key business risks are not identified and monitored they cannot be mitigated effectively.
1.0Introduction
1.1Appendices 1-6 provide Members with details of performance against the Corporate Plan and local service targets for the 2015-16 financial year.
1.2Appendix 7 shows the higher impact risks from the Corporate Risk Register. This includes operational and Health and Safety risks where the score meets the criteria for inclusion
1.3All appendices are produced from SPAR, the Corporate Service Performance and Risk Management system.
1.4When benchmarking information is available it is included.
2.0Performance
Managing the Environment Portfolio - Appendix 1
2.1The roll out for the chargeable garden waste scheme commenced on 1 September 2015 but was not completed until the end of quarter 3. So far 6,097 bin permits have been sold; the uptake is expected to increase in the Spring because garden waste is seasonal.
MDDC Report [title] 1 v Decent and affordable Homes Portfolio - Appendix 2
2.2The Ratio between planned and responsive repairs – starts to make more sense by quarter 3 and is only just below target.
2.3Decent Council Homes - We currently only have 14 properties that are non- decent with access, works are scheduled to ensure these are addressed before year end.
2.4For Gas safety – there were 2 properties with expired certificates, as at the end of January there is only 1 remaining.
Community Well Being Portfolio - Appendix 3
2.5The number of empty shops in all 3 towns is above target, only the number in Tiverton is higher than the previous year-end.
2.6The % of food premises inspected is much improved from last year but still below target.
2.7The “Scores on the Doors” for the year is included as Appendix 8 92% of premises are broadly compliant.
Planning and Regeneration Portfolio - Appendix 4
2.8As previously, the performance for quarter 3 of 2015/16 shows that in the majority of instances targets are being met or exceeded. However building regulations applications remain below target for the third quarter running.
2.9The Government has indicated its intention to tighten planning performance requirements so that local authorities making 50% or fewer decisions on time or those processing minor applications too slowly are at risk of designation. The Government’s planning guarantee requires that authorities determine all planning applications within 26 weeks unless an extension of time is agreed with the applicant. If not, the planning fee is returned. Planning performance continues to be closely monitored.
2.10The report which went to Planning Committee on 21 October is included as Appendix 4; this includes comments on performance and further information about enforcement.
Working Environment Portfolio - Appendix 5
2.11The sickness figures continue to be monitored closely but have been favourable against target for all 3 quarters to date this year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.