RESOLVED that the introduction of a planning obligation monitoring fee be approved and that delegated authority be given to the Head of Planning and Regeneration in conjunction with the Cabinet Member for Planning and Economic Regeneration to set the fees and any future review of fees. (Proposed by Cllr R J Chesterton and seconded by Cllr R L Stanley) Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member Cllr Richard Chesterton Responsible Officer Stephen Walford, Chief Executive
Reason for Report: To consider the introduction of a monitoring fee within future legal agreements made pursuant to S106 of the Town and Country Planning Act 1990.
RECOMMENDATIONS: That the Cabinet agrees to introduce a planning obligation monitoring fee as set out in the schedule attached at Appendix 1 and delegates the future review of these fees to the Head of Planning and Regeneration in conjunction with the Cabinet Member for Planning and Economic Regeneration.
Relationship to Corporate Plan: The Planning Service is a statutory service, the effective operation of which is central to the delivery of Corporate Plan priorities of community, housing, economy and environment. The effective monitoring of planning obligations (also known as S106 agreements) will ensure that legally binding requirements are adhered to.
Financial Implications: If introduced, this decision will generate additional revenue to recover the cost of the council’s monitoring activity. At present the full cost of the monitoring activity carried out is not recovered from the developer and hence is being subsidised.
Legal Implications: Limitations exist on charging standard, non-differentiated, fees for monitoring activity (see report). However, the introduction of a fee will help ensure the Planning Service is able to monitor the various obligations, trigger points and complexities within an increasing number of Planning Agreements entered into under s106 of the Town and Country Planning Act 1990.
Risk Assessment: The fee must relate to the cost of undertaking the monitoring activity rather than being a standard charge such as a percentage of the overall cost of financial contributions secured through the Agreement.
1.0INTRODUCTION.
1.1Planning obligations or agreements are entered into by developers under s106 of the Town and Country Planning Act 1990 in order to mitigate the impacts of a development proposal and are legally enforceable. They must be necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonable related to the development in scale and kind. These tests are set out in the Community Infrastructure Levy Regulations 2010 and as policy tests in the National Planning Policy Framework.
1 2.0 CONTEXT.
2.1It has long been the practice of this Authority to charge applicants entering into a planning obligation a fee to cover the council’s legal costs in preparing the obligation. The Local Government Act 2003 gave councils the ability to charge for discretionary, non-obligatory services, which in the planning context include services such as the provision of pre-application advice. It is requirement that the income from the charges should not exceed to cost of providing the service. In this context it is considered appropriate to seek to recover the cost of monitoring the provisions of planning agreements from applicants.
3.0BACKGROUND.
3.1The charging of monitoring/admin fees by Local Planning Authorities has been widespread due to the extra costs that such monitoring activity generates. However, a High Court case in 20151 has since meant that block fees or tariffs being applied in a standard manner are more likely to be challengeable as they don’t relate to an accurate assessment of the true cost.
3.2It is important that the fees charged reflect the actual cost (or as close as can be reasonably calculated) in order to justify the fee as a legitimate cost as opposed to ‘universal charge’ irrespective of the monitoring and administrative burden. In the Oxfordshire County Council case the monitoring sum was calculated as a percentage of the total contributions payable under the agreement and did not, in the view of the Inspector, reflect an accurate assessment of the true costs involved in the monitoring of the obligations in the section 106 agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.