RESOLVED that delegated authority be given to the Head of Planning and Regeneration and the Project Team in consultation with the Cabinet Member for Planning and Regeneration to finalise details of the agreement and method of delivery for final Cabinet approval in November/December 2016. (Proposed by Cllr R J Chesterton and seconded by Cllr R L Stanley) Note: *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
BUILDING CONTROL PARTNERSHIP BETWEEN MID DEVON DISTRICT COUNCIL AND NORTH DEVON COUNCIL
Cabinet Member: Councillor Richard Chesterton Responsible Officer: Jenny Clifford, Head of Planning & Regeneration
REASON FOR REPORT: The purpose of this report is to update Members of the proposed arrangements and progress made towards delivering the Building Control Service through a Partnership between Mid Devon and North Devon Councils.
RECOMMENDATION: The Project team in consultation with the Cabinet Member for Planning and Regeneration is delegated responsibility to finalise details of the agreement and method of delivery for final Cabinet approval in November / December 2016.
RELATIONSHIP TO CORPORATE PLAN: The effective operation of the Building Control Service directly links with all four of the corporate priorities of economy, homes, community and the environment. It is principally a service to ensure health and safety standards apply to building work, energy saving provisions are attained and premises are fully accessible for use through the application of the Building Regulations. The service also deals with dangerous structures and demolition notices.
Financial Implications: Mid Devon are providing ICT resource to support the implementation of systems for the partnership but there are no capital costs. The project costs are within the allocated budget identified by North Devon.
Legal Implications: A legal agreement is required and the impact on constitution of the Council is being identified
Risk Assessment: There is risk associated with all changes to the way we work. The Partnership business case considered by Cabinet on 10th March 2016 contained a risk analysis that shows that after mitigation the risk profile is low.
1.0BACKGROUND 1.1 Cabinet recommended to Council on 10 March 2016 that the Councils form a Joint Committee in respect of their Building Control functions to enable joint working and it was agreed that the matter would be brought back to Cabinet, once the draft agreement (along with all other aspects of joint working on building control) with Mid Devon District Council has been finalised, so that decisions can be made on the following in respect of a new Joint Committee: 1.1.1 its membership and formation; 1.1.2 the proposed variations to the constitution; and 1.1.3 finalise all other details.
This was subsequently endorsed by Council.
2.0THE PROPOSED MODEL 2.1 The Building Control Service will be provided through a joint committee composed of a total of four members consisting of two members appointed by each Council.
2.2It is proposed that MDDC will supply and support the Building Control administrative system to support the operational activity of Building Control using the iDox Uniform database and associated software.
2.3In order to ensure a balance of power and resources required to support the service between the Partners it is proposed that North Devon is the Lead Authority providing governance and financial support services.
2.4On formation of the partnership human resource support and employment contracts will remain with the existing employing Authority. The implications of this will be reviewed within 12 months and in the event of the need to recruit new staff.
2.5Legal services support in relation to enforcement will be provided by the relevant partner authority.
2.6A single address using Woodlands, South Molton is proposed to emphasis the single nature of the service.
2.7A minimalist approach to branding of the Partnership is proposed emphasising that North and Mid Devon are working in Partnership to deliver the service.
3.0PROPOSED ICT INFRASTRUCTURE 3.1 One of the drivers for the Partnership was to minimise overheads charged to the service of which a significant part is ICT charges.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.