It was AGREED that the Director of Corporate Affairs and Business Transformation would discuss community engagement, and how volunteers could be encouraged to help the authority in areas such as recycling, at Leadership Team, and report back. Note : - Report * previously circulated and attached to Minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member Cllr Clive Eginton Responsible Officer Director of Corporate Affairs & Business Transformation, Jill May
Reason for Report: To provide Members with an update on performance against the corporate plan and local service targets for 2017-18 as well as providing an update on the key business risks.
RECOMMENDATION: That the Committee reviews the Performance Indicators and Risks that are outlined in this report and feeds back any areas of concern.
Relationship to Corporate Plan: Corporate Plan priorities and targets are effectively maintained through the use of appropriate performance indicators and regular monitoring.
Financial Implications: None identified
Legal Implications: None
Risk Assessment: If performance is not monitored we may fail to meet our corporate and local service plan targets or to take appropriate corrective action where necessary. If key business risks are not identified and monitored they cannot be mitigated effectively.
Equality Impact Assessment: No equality issues identified for this report.
1.0Introduction
1.1Appendices 1-5 provide Members with details of performance against the Corporate Plan and local service targets for the 2017-18 financial year.
1.2When benchmarking information is available it is included.
1.3Appendix 6 shows the higher impact risks from the Corporate Risk Register. This includes Operational and Health & Safety risks where the score meets the criteria for inclusion. See 3.0 below.
1.4Appendix 7 shows the risk matrix for the Council.
1.5All appendices are produced from the Corporate Service Performance And Risk Management system (SPAR).
MDDC Report [title] 1 v 2.0 Performance
Environment Portfolio - Appendix 1
2.1Regarding the Corporate Plan Aim: Increase recycling and reduce the amount of waste: The Council is broadly on track with Residual household waste per household (measured in Kilograms) until the end of October was 224kg. We are still a little below target for % of household waste reused, recycled and composted but at 53.6% still did well compared to the mean for all English authorities on LG Inform which was 48.09% for Q2 2017/18.
2.290% of trade waste customers are now covered by the recycling service.
2.3Number of Households on Chargeable Garden Waste; sales/renewals exceeded the target of 9,000 by the end of June. The number of customers peaked in September at 9,537 but has slightly decreased since due to the drop in garden waste produced during the winter. We now have 9,268 customers against 8,298 as at 30 November 2016.
2.4Regarding the Corporate Plan Aim: Reduce our carbon footprint: We continue to put energy saving measures in place wherever we can; recent additions are low energy air handling and LED lighting in the EVLC extension.
2.5The energy switching scheme went live on MDDC website on 1 December 2017. The Waste transfer station at Carlu Close was officially opened on 8 December.
2.6Regarding the Corporate Plan Aim: Protect the natural environment: 12 of the 27 recommendations from the Street Cleansing review have now been implemented; some have been put on hold and will be considered with the proposed merger of the service with Grounds Maintenance.
Homes Portfolio - Appendix 2
2.7Regarding the Corporate Plan Aim: Build more council houses: No new Council Houses were completed in 2016/17 nor so far in 2017/18 however work is progressing on Birchen Lane and Palmerston Park, both due for completion in 2018.
2.8Regarding the Corporate Plan Aims: Facilitate the housing growth that Mid Devon needs, including affordable housing: and Planning and enhancing the built environment: The Local Plan is of course key; having taken legal advice and reviewed the statements of participants who would take part in the hearings a deferment has been requested to allow an independent review of the major modifications stage sustainability appraisal. This has been commissioned but a delay in the order of 6 months is expected.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.