CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Mid Devon District Council
Cabinet, Thursday 10 May 2018 at 2.15pm

Supply of Boilers (00-44-44)

Decided Executive 1 paper

Cabinet decided this item on Thursday 10 May 2018. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that the Boiler Supply Contract be awarded to Supplier B with an approximate forecast annual cost of £144,000. (Proposed by Cllr R L Stanley and seconded by Cllr P H D Hare-Scott). Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

CABINET 10 MAY 2018

AGENDA ITEM: BOILER SUPPLY CONTRACT 2018 - 2022

Cabinet Member: Cllr Ray Stanley Responsible Officer: Andrew Pritchard, Director of Operations

Reason for Report: To advise Cabinet of the outcome of the recent procurement exercise for the direct award, via a procurement framework, for the supply of Boilers for the Capital Boiler replacement programme and confirmation of the intention to award the contract.

RECOMMENDATION: It is recommended that Cabinet award the Boiler Supply Contract to Supplier B with an approximate forecast annual cost of £144,000

Contracted Works: The contract will deliver the supply of boilers and essential associated items to Mid Devon District Council for the Capital Boiler Replacement Programme.

Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.

Financial Implications: The budget for the supply and installation of the boilers for is approximately £296,000 per annum. Capital investment in the MDDC stock will result in a lower on-going maintenance costs.

Legal Implications: We have a legal duty to maintain the stock and meet the Decent Homes Standard. The conditions of engagement are based on an existing framework with the YPO Procurement Consortium. This provides a robust framework for managing and controlling the performance of the contractor to meet our legal obligations.

Risk Assessment: The principal risk is failing to limit costs due to additional works and delivery of the programme. The performance of the contract will be monitored monthly and corrective action will be taken where performance falls below Key Performance Indicator Targets. These include:

1) Variations and extras 2) Delivery of programme 3) Cost

MDDC Cabinet Report 1 Boiler Supply Contract 2018 – 2022 1 Introduction

1.1The term of this contract is 4 years.

1.2The procurement procedure was a compliant direct award process via a framework managed by YPO Procurement Operations, 41 Industrial Park Wakefield WF2 0XE United Kingdom.

2 Framework Benefits

2.1About the framework provider:

The YPO Consortium (The Consortium) is a procurement consortium that supplies products and frameworks, providing procurement advice, guidance and expertise to public sector organisations. The Consortium is the largest formally constituted public sector buying organisation in the UK, owned and governed by local authorities. Customers include local authorities, schools, academies, colleges, universities, charities, care homes and the emergency services.

3 Use of YPO Frameworks

3.1Available to all contracting authorities across England, Scotland and Wales.

3.2Free to use for buying organisations, with no fees charged for Consortium membership or using the framework.

3.3Keep the flexibility and ownership of managing the contract and specification as you choose.

3.4No requirement to tender via OJEU directly as the pre-tendered framework is already fully compliant.

3.5All suppliers have been fully assessed for their experience, technical and professional ability.

4 Procurement Process

4.1The Boiler Supply Framework selected 4 boiler suppliers and manufacturers who were chosen via a tender issued in the Official Journal of the European Union (OJEU). The framework was undertaken as an EU compliant open tender procedure, as detailed in Regulation 27 of the UK statutory instrument Public Contracts Regulations 2015 #102.

4.2The YPO framework 691, Plumbing Heating Materials, Lot 2 framework was used to identify the suppliers. Those suppliers were ranked from 1st to 4th based on their tender evaluation carried out by YPO. The recommendation of this report is to make a direct award to the highest ranked supplier within this framework, which can meet the Service Level Criteria of MDDC outlined in 4.7.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Supply of Boilers (00-44-44)Report 74 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
SW
Stephen WalfordOfficer, in attendance
JC
Jenny CliffordOfficer, expected
AJ
Andrew JarrettOfficer, in attendance
JM
Jill MayOfficer, in attendance
KT
Kathryn TebbeyOfficer, in attendance
AP
Andrew PritchardOfficer, in attendance
JC
Jane CottrellOfficer, expected
CE
Councillor Clive EgintonAssociate Member, present
RC
Councillor Richard ChestertonCommittee Member, present
PH
Councillor Peter Hare-ScottCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present
MS
Councillor Margaret SquiresCommittee Member, present

All 20 on the meeting page

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies