RESOLVED the JCT Intermediate Building Contract with Contractors Design 2016 building contracts for essential planned maintenance works to two pool filters and the repair and upgrade to the fabric of both swimming pools at Lords Meadow Leisure Centre be awarded to supplier C for Lot 1 and supplier B for Lot 2. (Proposed by the Chairman) Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
LORDS MEADOW LEISURE CENTRE – FILTER PROJECT TENDER
Cabinet Member: Cllr Simon Clist, Cabinet Member for Housing and Property Services.
Responsible Officer: Andrew Busby, Group Manager for Corporate Property and Commercial Assets.
Reason for Report: For Cabinet to review the results of the tender exercise for essential maintenance work at Lords Meadow Leisure Centre (LMLC) and to award the JCT Intermediate Building Contract with Contractors Design 2016 to two contractors.
RECOMMENDATION: To award the JCT Intermediate Building Contract with Contractors Design 2016 building contracts for essential planned maintenance works to two pool filters and the repair and upgrade to the fabric of both swimming pools at Lords Meadow Leisure Centre, supplier C for Lot 1 and supplier B for Lot 2.
Relationship to Corporate Plan: Property assets are linked to the delivery, vision and priorities of the Council. The way that the Council manages its land and property assets has a direct impact on the quality of services delivered, as well as maximising the value derived from our property holdings for the on-going contribution in balancing the Councils budget. It is, therefore, important that efficient and effective use is made of our asset portfolio to support corporate and service objectives.
Financial Implications: The tendered Lots were established to incorporate essential maintenance works as detailed in this report. The financial results of the tender exercise can be met from the budget available in the 2019/20 financial year.
Legal Implications: The contracts will be let via a JCT Intermediate Building Contract with Contractors Design 2016 to the successful suppliers for Lots 1 and 2.
Risk Assessment: As part of the contract the contractor will need to provide a Risk Assessment taking into consideration the site. All works will be compliant with the latest version of the Construction Design and Management (CDM) regulations.
Equality Impact: There is no negative impact to equality.
Impact on Climate Change: To carry out these essential works will temporarily increase our Carbon Footprint, however once complete the works will assist the Council to achieve Carbon footprint reductions by improving water and electricity efficiency.
1.1A project team was created with the aim of completing essential maintenance tasks during a planned shut down during the month of December 2019.
1.2The tasks and tender include the replacement of end of life pool filters, the relining of both the main/learner pools, the pool surround and planned maintenance work to the pool hall roof structure. The pool filters and associated heat exchangers are approaching end of life and will require an onsite retro fit repair that will offer the same longevity as a full asset replacement.
1.3The existing pool tiles on the side of the pool and inside the Learner pool have become damaged, dated and stained which has proved difficult to clean. Consulting Engineers conducted a survey of the Lords Meadow Leisure Centre during May 2019 with the Facilities Manager for Corporate Property and Commercial Assets. The objective of the survey was to review the status of the existing pool filters, the site infrastructure and to highlight opportunities for energy efficiency improvement. The survey focused primarily on the plant room, pool hall and associated areas that had energy opportunities to focus on. All pool water onsite is filtered by means of sand filtration using two bobbin wound glass fibre filters; the fibreglass resin in filter 1 is extruding through the outer shell of the filter, deterioration is largely cosmetic but over time with further resin extrusion, the structure of the filter may be compromised, the filters are therefore proposed to be replaced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.