RESOLVED that the new three-year Roofing Replacement Contract be awarded to Contractor 4 with a forecast annual cost £600,000.00. (Proposed by Cllr S J Clist and seconded by Cllr G Barnell) Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Cabinet Member: Cllr Simon Clist Responsible Officer: Andrew Pritchard, Director of Operations
Reason for Report: To advise Members on the results for the tendering of the Replacement Roofing Programme 2020 – 2023 to Council houses and confirm the award of the contract.
RECOMMENDATION: It is recommended Members agree that the new three- year Roofing Replacement Contract is awarded to Contractor 4 with a forecast annual cost £600,000.00. The contract has been awarded to the contractor with the highest combined price/quality score with 60% of the total score based on price and 40% quality.
Financial Implications: The budget for the works is £600,000.00 per annum. Capital investment in the MDDC stock will result in a lower revenue cost in the coming years, which will enable the Repairs Service to operate more effectively and manage future maintenance costs.
Legal Implications: We have a legal duty to maintain the stock and meet the Decent Homes Standard. The conditions of engagement are based on a JCT Intermediate Building Contract with Contractors Design 2016, combined with the contractual requirements. This provides a robust framework for managing and controlling the performance of the contractor to meet our legal obligations.
Risk Assessment: The principal risk is failing to limit costs due to additional works and delivery of the programme. The performance of the contract shall be monitored monthly; corrective action will be taken where performance falls below Key Performance Indicator Targets. These include: 1) Customer satisfaction; 2) Variations and extras; 3) Delivery of programme; 4) Number of defects; 5) Managing Health and Safety
Equality Impact Assessment: All staff have received Equality and Diversity awareness training. MDDC discuss equality and diversity at the progress meetings and encourage the contractor to carry out awareness training.
Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.
Impact on Climate Change: Investment in the MDDC stock will lower the amount of fossil fuels used to run and maintain the homes.
1.0Introduction
1.1The term of this contract is three years with the option to terminate the contract at the end of each year subject to performance.
MDDC Report: Replacement Roofing Programme 1 2020 – 2023 award 1.2 Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This means that anyone who expressed an interest in the contract would be invited to tender.
1.3To ensure quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these would be disqualified.
2.0Procurement Process
2.1Expressions of interest were invited via a notice in the Supplying the Southwest Procurement Portal published on the 30 September 2019.
2.2Evaluation criteria set out in the ITT:
2.3Quality 40% Membership of the National Federation of Roofing Contractors Pass/Fail Mobilisation of the works 15% Communication 15% Waste and recycling 10%
Price 60%
2.4Responses were required by midday on 1 November 2019.
2.5There were a total of 33 expressions of interest of which 8 submitted their tenders on time, 5 opted out and 20 did not respond.
2.6Evaluations were carried out during November and early December 2019, by representatives from Mid Devon District Council’s Planned Maintenance and Procurement service, as well as a representative from Teignbridge District Council’s Procurement Service.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.