Cullompton and Wellington New Railway Stations Project - Governance, Process, Project Funding and Next Steps (1-00-03)

Agreed Executive 2 papers

Cabinet agreed this item on Thursday 23 April 2020. Below is the council's own wording, with the papers it was decided on.

Item167

Resolved

RESOLVED that: a) The Governance arrangements as set out in appendix 1 be agreed. b) The overview of the process be noted. (Proposed by Cllr G Barnell and seconded by Cllr Mrs N Woollatt) Note : * Report previously circulated copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

Recommendation

1. That the governance arrangements set out in Appendix 1 be agreed; and

2. That the overview of the process be noted.

Financial Implications: In 2016 Mid Devon District Council, Taunton Deane Borough Council (now Somerset West & Taunton Council), Cullompton Town Council and Wellington Town Council agreed to contribute £100k towards feasibility work; the District Councils contributing £40k each and the Town Councils £10k each. To date £31,281 has been spent on timetabling and initial feasibility work.

It is estimated that to complete the first formal stage of the project, production of a Strategic Outline Business Case is needed. This will cost approximately £200-250k. The project has monies unspent from previous committed contributions towards the project amounting to £68,719, but there is clearly a shortfall which will still need to be funded. A government funding bid has been submitted and we await the outcome of that process. The financial implications will need to be reassessed once a decision on the government funding has been received.

Servicing the governance arrangements (set out in section 3 below) can be met from existing budgets.

It is too early to know how much it will cost to complete delivery of the two railway stations; however the Strategic Outline Business Case will establish an indicative cost. It will also provide a basis for exploring further funding opportunities. Importantly once a scheme has completed a Strategic Outline Business Case and satisfactorily progressed to the ‘Decision to Develop’ stage it is much more likely to benefit from government funding.

MDDC Report Cullompton Railway Stations Project 1 V1 Budget and Policy Framework: As explained above there are existing funds available from partners totalling £68,719. Additional funding would be needed to complete the Strategic Outline Business Case (SOBC) in its entirety. Once the partners know whether the government funding bid is successful a decision would need to be made as to whether to continue with the full Strategic Outline Business Case, undertake first stage of SOBC only or discontinue the project.

The Local Plan Review includes a site allocation for a Cullompton Railway Station.

Legal Implications: No significant legal implications anticipated at this time as a result of the governance structure proposed. Legal implications could arise throughout the project development process. Should these arise they will be reported to Cabinet through future update reports.

Risk Assessment: Robust, suitable and appropriate governance arrangements for the new stations project are necessary to drive the project progress, allow it to operate efficiently and to build relationships with stakeholders. Effective governance arrangements will also ensure that best use is made of funding opportunities. The governance arrangements provide a structure within which the project will develop and be accountable.

Risks will be constantly reviewed as the project develops. Decisions whether to continue with the project will be made at each significant gateway milestone as explained later in the report. This will allow the opportunity to withdraw from the project should the risks outweigh the likelihood of satisfactory delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cull RS Appendix 1 Proposed Project Governance ArrangementsAppendix 105 KB Download
PDF
Cullompton and Wellington New Railway Stations Project: Governance, Process, Project Funding and Next Steps (1-00-03)Report 147 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 32 attended
MD
Maria De LeiburneOfficer, expected
BD
Councillor Bob DeedAssociate Member, present
LT
Councillor Luke TaylorCommittee Member, present
GB
Councillor Graeme BarnellCommittee Member, present
SC
Councillor Simon ClistCommittee Member, present
DK
Councillor Dennis KnowlesCommittee Member, present
EW
Councillor Elizabeth WainwrightCommittee Member, present
AW
Councillor Alex WhiteCommittee Member, present
NW
Councillor Nikki WoollattCommittee Member, present
SW
Stephen WalfordOfficer, in attendance
CO
Carole OliphantSecretary, expected
JC
Jenny CliffordOfficer, in attendance

All 32 on the meeting page

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies