RESOLVED that the contract for works required to decorate the Council’s homes for 2021-2026 be awarded to Contractor 5. (Proposed by Cllr R B Evans and seconded by Cllr D J Knowles) Reason for decision - there was a need to confirm the award of the tender so that the specified work could be progressed. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
External Painting and Repairs before Painting of Council Homes 2021-2026 Cabinet Member Cllr Bob Evans, Cabinet Member for Housing & Property Responsible Officer Mike Lowman, Operational Manager for Building Services
Reason for Report: To advise Members on the results for the tendering of the External Painting and Repairs of the Council’s homes for the next five years (2021- 2026) and confirm award of the contract.
RECOMMENDATION: It is recommended Members agree that the contract for works required to decorate the Council’s homes for 2021-2026 be awarded to Contractor 5.
Financial Implications: The budget for the works is £300,000.00 per annum and will be managed within the HRA budget. Investment in the MDDC stock will result in a lower revenue cost in the coming years, which will enable the Repairs Service to operate more effectively and manage future maintenance costs.
Legal Implications: We have a legal duty to maintain the stock and meet the Decent Homes Standard. The conditions of engagement are based on a JCT Intermediate Building Contract with Contractors Design 2016, combined with the contractual requirements.
Risk Assessment: The principal risk is failing to limit costs due to additional works and delivery of the programme. The performance of the contract shall be monitored monthly; corrective action will be taken where performance falls below Key Performance Indicator Targets. These include: 1) Customer satisfaction; 2) Variations and extras; 3) Delivery of programme; 4) Number of defects; 5) Managing Health and Safety.
Equality Impact Assessment: All staff have received Equality and Diversity awareness training. MDDC discuss equality and diversity at the progress meetings and encourage the contractor to carry out awareness training.
Relationship to Corporate Plan: To contribute towards maintaining the housing stock and meeting the Decent and Affordable Homes target.
Impact on Climate Change: Investment in the MDDC stock will lower the amount of fossil fuels used to run and maintain the homes.
1.0Introduction
1.1The term of this contract is three years with the option to extend the contract for a further two individual years subject to performance.
1 MDDC Report : External painting and Repairs before Painting 2021-2026 V2 1.2 Due to the nature and value of this procurement, the appropriate procedure was an open tender process. This means that anyone who expressed an interest in the contract would be invited to tender.
1.3To ensure quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these would be disqualified.
2.0Procurement Process
2.1Expressions of interest were invited via a notice in the Supplying the Southwest Procurement Portal published on the 21 October 2020.
2.2Evaluation criteria set out in the ITT:
Quality 40% Mobilisation of the works 10% Communication 10% Materials and Equipment 10% Waste and recycling 10%
Price 60%
2.3Responses were required by midday on 20 November 2019.
2.4There were a total of 21 expressions of interest of which 7 submitted their tenders on time, 0 opted out and 14 did not respond.
2.5Evaluations were carried out during November and early December 2020, by representatives from Mid Devon District Council’s Planned Maintenance and Procurement service.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.