It was AGREED that contact be made with the head of IT to express the concerns of the Committee and ask what could be done to resolve the outstanding issues. · Concerns regarding the fragility of the Payroll system following a recent upgrade which had resulted in issues requiring daily intervention from IT Services. However, the ability to run the payroll from home had been tested and there were back up plans in place should an issue occur. These back ups were all contained within the business continuity plan. Note : * Report previously circulated; copy attached to the signed minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Mid Devon District Council Audit Committee March 2021
Robert Hutchins Head of Audit Partnership Introduction The Audit Committee, under its Terms of Reference contained in Mid Devon District Council’s Constitution, is Page required to consider the Chief Internal Auditor’s annual report, to review and approve the Internal Audit Contents programme, and to monitor the progress and performance of Internal Audit. Introduction 1 The Accounts and Audit (Amendment) (England) Regulations 2015 introduced the requirement that all Opinion Statement 2 Authorities carry out an annual review of the effectiveness of their internal audit system and incorporate the results of that review into their Annual Governance Statement (AGS), published with the annual Statement of Executive Summary Audit Results 2 Accounts. Value Added 3 The Public Sector Internal Audit Standards require the Head of Internal Audit to provide an annual report Audit Coverage & Progress Against 3 providing an opinion for use by the organisation to inform its governance statement. This report provides our Plan proposed opinion for 2020-21 based on work undertaken to date in the Opinion Statement. The Internal Audit plan for 2020-21 was presented and approved by the Audit Committee in June 2020, and subsequently revised in October 2020. The following report and appendices set out the background to audit service provision; summaries of audit work undertaken during the year and provides an opinion on the overall Appendices adequacy and effectiveness of the Authority’s internal control environment. 1 – Summary of Audit Results 4 Expectations of the Audit Committee from this progress report 2 – Clearance of audit 11 Audit Committee members are requested to consider: recommendations the assurance statement within this report. the basis of our opinion and the completion of audit work against the plan. the scope and ability of audit to complete the audit work. audit coverage and findings provided. the overall performance and customer satisfaction on audit delivery. approve the amendments to the audit plan. In review of the above the Audit Committee are required to consider the assurance provided alongside that of the Executive, Corporate Risk Management and external assurance including that of the External Auditor as part of the Governance Framework and satisfy themselves from this assurance that the internal control framework continues to be maintained.
Robert Hutchins Head of Devon Audit Partnership
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Audit Action Tracking Report (00:30:00)RESOLVED that the recommendations regarding the Patch Management audit remain as a high priority and not be reduced t...
Risk Management Policy (00:38:00)RESOLVED that the updated Risk Management Policy be approved. (Proposed by the Chair) Reason for the decision Effecti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.