Mid Devon District Council
Cabinet, Tuesday 26 October 2021 at 10.00am

Beech Road, Tiverton - Project Delivery (1-21-49)

Approved Executive 3 papers

Cabinet approved this item on Tuesday 26 October 2021. Below is the council's own wording, with the papers it was decided on.

Item88

Resolved

RESOLVED that: The Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services be given delegated authority to award the contract for works required to provide three social rented houses at Beech Road in Tiverton. (i) To Contractor 1 under a JCT Design and Build Contract 2016 (as amended). (ii) To approve a £22k increase be approved for project contingency as detailed in paragraph 5.9 of the report. (Proposed by Cllr R B Evans and seconded by Cllr C R Slade) Reason for the decision – there is a need for the tender to be approved to allow the housing project to be progressed. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

CABINET

26 OCTOBER 2021

BEECH ROAD, TIVERTON – PROJECT DELIVERY

Cabinet Member(s): Cllr Bob Evans, Deputy Leader and Cabinet Member for Housing and Property Services Responsible Officer: Andrew Busby, Corporate Manager Property, Leisure and Climate Change

Reason for Report: Following the withdrawal of Contractor 2, for Cabinet to award the contract for the construction of three Council properties, using a JCT Design & Build 2016 Contract (as amended) to Contractor 1.

Recommendation: The Deputy Chief Executive (S151) and the Deputy Leader and Cabinet Member for Housing and Property Services are delegated authority to award the contract for works required to provide three social rented houses at Beech Road in Tiverton.

(i) Contractor 1 under a JCT Design and Build Contract 2016 (as amended).

(ii) To approve a £22k increase for project contingency as detailed in para 5.9.

Financial Implications: These are explained in the report and will be managed within HRA budget and 1:4:1 budget allocations received as part of the right to buy process.

Budget and Policy Framework: The construction of new homes has been identified in the Capital Medium Term Financial Plan. The cost for the on-going maintenance of the asset will be met from the Housing Maintenance Fund (HMF).

Legal Implications: Upon awarding the contract, the Council will be engaged and bound by the terms of the JCT Design and Build 2016 (as amended) contract with the chosen contractor.

Risk Assessment: An open and transparent tendering process had been undertaken to avoid the potential for challenge and to ensure value for money. An Employers Agent has been engaged to review the quality scoring of Contractor 1 to address any concerns.

Equality Impact Assessment: The design of the properties considers the needs of all and planning permission has already been approved under reference 17/00323FULL. Our housing need has been considered as detailed on Table 1.

Relationship to Corporate Plan: Homes: Deliver more affordable housing and greater numbers of social rented homes.

Impact on Climate Change: The contractor will be required to be committed to managing and minimising the environmental impact. This project will be planned in a manner, which takes account of the environmental impact, seeking to reduce such

Cabinet –Beech Road –Project Delivery 261021 v1 1 effect as much as possible. This will include consideration of the impact of travelling to the site and effective planning to reduce the number of deliveries. The introduction and promotion of environmental monitoring will be a key element of management of the project. The impact of these works will result in an increase in the Council’s reported carbon footprint under the relevant scope which will be reported in 2021/22 figures and the Council will look at measures to offset the additional carbon used on this project.

1.0Introduction

1.1The Council is committed to increasing its affordable housing stock through the development of existing Council owned land.

1.2The land that the Council plan to develop at Beech Road is within the Council ownership (HRA fund) as shown on attached map Annex B.

1.3Planning permission was previously applied for in 2015 reference 15/00062/FULL to address the adopted drains easement restrictions. A further application was applied for and approved to build three one-bedroom dwellings reference 17/00323FULL. Works completed following ground investigation work has secured this permission.

1.4An agreement was previously made as part of the planning application for the Council to provide an off-street parking space for a neighbouring property prior to any commencement of building works on the parking area.

1.5The Council has now completed its consultation with those households who use the parking spaces to ensure that they are fully aware of the development proposals. There is no additional issues arising from that consultation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Beech Road WPD Location map 261021Appendix B 377 KB Download
PDF
Beech Road -Site Plan 261021Appendix C 190 KB Download
PDF
Beech Road, Tiverton: Project Delivery (1-21-49)Report 373 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 27 attended
BD
Councillor Bob DeedAssociate Member, present
RC
Councillor Richard ChestertonCommittee Member, apologies
CD
Councillor Chris DawCommittee Member, present
BE
Councillor Bob EvansCommittee Member, present
DK
Councillor Dennis KnowlesCommittee Member, present
AM
Councillor Andrew MooreCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present
NW
Councillor Nikki WoollattCommittee Member, present
SW
Stephen WalfordOfficer, in attendance
AJ
Andrew JarrettOfficer, in attendance
JM
Jill MayOfficer, in attendance
RM
Richard MarshOfficer, in attendance

All 27 on the meeting page

On this subject at Mid Devon

Search all
  1. Beech Road, Tiverton - Project Delivery (1-21-49)This decision
  2. Beech Road, Tiverton - Design and Build Tender (00-15-25)Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies