RESOLVED that: 1. The new four-year (2+1+1) Modernisation of Council Homes Contract is awarded to Contractor 1 with a forecast annual cost £400,000.00. 2. Delegated authority be granted to the S151 Officer (in consultation with the Deputy Leader and Cabinet Member for Housing and Property Services) to complete the associated modernisation contract. (Proposed by Cllr R B Evans and seconded by Cllr B A Moore) Reason for the decision – the Council has a legal duty to maintain the stock and meet the Decent Homes Standard. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
AWARD OF MODERNISATION OF COUNCIL HOMES CONTRACT 2022–2026
Cabinet Member: Cllr Bob Evans, Deputy Leader and Cabinet Member for Housing and Property Services Responsible Officer: Simon Newcombe, Corporate Manager for Public Health, Regulation and Housing
Reason for Report: To advise Members on the results for the tendering of the Modernisation of Council Homes Contract 2022–2026 and confirm the award of the contract.
RECOMMENDATION: That Cabinet approve the following
1. The new four-year (2+1+1) Modernisation of Council Homes Contract is awarded to Contractor 1 with a forecast annual cost £400,000.00.
2. Delegated authority be granted to the S151 Officer (in consultation with the Deputy Leader and Cabinet Member for Housing and Property Services) to complete the associated modernisation contract.
Contracted Works: The contract will deliver the supply and installation of kitchen and bathrooms to Mid Devon District Council housing stock.
Relationship to Corporate Plan: To contribute towards meeting the Decent and Affordable Homes target by making best use of the existing stock.
Financial Implications: The budget for the works is £400,000.00 per annum. Capital investment in the MDDC stock will result in a lower revenue cost in the coming years, which will enable Mid Devon Housing and its repairs service to operate more effectively and manage future maintenance costs.
Legal Implications: We have a legal duty to maintain the stock and meet the Decent Homes Standard. The conditions of engagement are based on a JCT Measured Term Contract (MTC) 2016, combined with the contractual requirements. This provides a robust framework for managing and controlling the performance of the contractor to meet our legal obligations.
Risk Assessment: The principal risk is failing to limit costs due to additional works and delivery of the programme. The performance of the contract shall be monitored monthly; corrective action will be taken where performance falls below Key Performance Indicator Targets. These include: 1) Customer satisfaction; 2) Variations and extras; 3) Delivery of programme; 4) Number of defects; 5) Availability of funding
Impact on Climate Change: Maintaining homes to the Devon Homes Standard has an indirect, beneficial impact on reducing carbon emissions within the Mid Devon Housing Service and therefore as a Council.
MID DEVON DISTRICT COUNCIL Cabinet Report Modernisation of Council Homes Contract 2022 – 2026 1 Introduction
1.1The term of this contract is 2 years with two possible 1 year extensions subject to budgets, performance and the approval of the Portfolio Holder for Housing.
1.2The procurement procedure was a mini competition carried out using the Capital Works Dynamic Purchasing System via the PFH (Procurement for Housing) Framework.
2 Framework Benefits
2.1The Procurement for Housing (PFH) Framework is Contracting Authority who develop frameworks in England, Scotland and Wales. Members currently include Registered Providers of Social Housing, Local Authorities, TMO’s, ALMOs, Health Authorities, Police and Fire Services.
2.2Shared procurement expertise and resource with end to end contract support.
2.3Keep the flexibility and ownership of managing the contract and specification as you choose.
2.4The requirement has been advertised and capable suppliers have been identified through competitive procurement.
2.5All suppliers have been fully assessed for their experience, technical and professional ability.
2.6Compliant with the Public Contracts Regulation 2015
3 Procurement Process
3.1Expressions of interest were sent to 15 contractors supplying the South West on the PFH Capital Works Dynamic Purchasing System. 3 contractors returned interest, a mini competition between the 3 suppliers was then carried out by the Procurement Service of Mid Devon District Council. To ensure quality of contractors, a number of minimum requirements were set out within the ITT. Any contractor failing to meet these would be disqualified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.